FEDERAL COURT OF AUSTRALIA
Australian Competition and Consumer Commission v Origin Energy Limited [2015] FCA 55
Table of Corrections 29 May 2015 In paragraph 33 the case…
Keep reading for free
Create a free CaseChat account to read Australian Competition and Consumer Commission v Origin Ener... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Find similar cases
Other decisions on the same topics. Each opens in a new tab.
Details
- Case
- [2015] FCA 55
- Decision Date
CaseChat Overview and Summary
The court considered whether the imposition of separate penalties on Origin, Origin Electricity, and Origin Gas was appropriate, given that they had different levels of culpability and had chosen to organise their affairs in a way that created separate subsidiaries for retail supply. The court held that the penalties agreed upon by the parties were structured to reflect their differing culpability and that it was not appropriate to ignore their separate status. The court also noted that the agreed penalties were within the range of penalties that would be reasonable in all the circumstances. In light of this, the court decided to give effect to the parties' agreement with respect to the penalties, publication orders, costs, and a verification certificate.
The court made orders in the terms proposed by the parties. Origin Energy Limited was ordered to pay a pecuniary penalty of $125,000, while Origin Electricity and Origin Gas were each ordered to pay a pecuniary penalty of $100,000. The respondents were also ordered to jointly publish a notice in a weekday edition of The Advertiser newspaper and to distribute notices to their South Australian residential customers. Additionally, the respondents were ordered to pay the ACCC's costs of the proceeding and to provide a signed certificate verifying compliance with the publication orders.
Orders
Orders of the court
Pecuniary Penalty
4. Within 30 days of the date of this order, Origin pay to the Commonwealth of Australia a pecuniary penalty of $125,000 in respect of the acts constituting its contraventions of sections 29(1)(g) and 29(1)(i) of the ACL.
5. Within 30 days of the date of this order, Origin Electricity and Origin Gas each pay to the Commonwealth of Australia a pecuniary penalty of $100,000 in respect of the acts constituting their contraventions of sections 29(1)(g) and 29(1)(i) of the ACL.
Publication Orders
6. Within 21 days of the date of this order, the Respondents jointly publish, at their own expense, a notice in a weekday edition of The Advertiser newspaper which is in the terms and form of Annexure A, and complies with the following specifications:
(a) is placed within the first 10 pages of the newspaper;
(b) is of a size of approximately a quarter of a page in that newspaper;
(c) has a banner font of sans serif 12 point, bold;
(d) has a headline font of 12 point, bold;
(e) contains in the body of text font that is no less than 11 point size; and
(f) has the ACCC and Commonwealth logos of at least 20 millimetres in height and centered.
7. Each of Origin Electricity and Origin Gas, at its own expense, within 120 days of the date of this order:
(a) cause a DL sized insert in the terms of Annexure A to be distributed once with each of its South Australian residential customers’ invoices sent by post; or
(b) cause a document in the terms of Annexure A to be distributed once with each of its South Australian residential customers’ invoices sent electronically,
(c) to all persons with whom:
(d) Origin Electricity entered into a DailySaver Electricity Energy Plan between 1 February 2013 and 30 June 2013 for the supply of electricity to residential premises in South Australia; and
(e) Origin Gas entered into a DailySaver Gas Energy Plan between 1 February 2013 and 30 June 2013 for the supply of natural gas to residential premises in South Australia,
save that if a person commenced a DailySaver Electricity Energy Plan and DailySaver Gas Energy Plan during the Relevant Period, only one notice needs to be sent to that person.
Costs
8. Within 30 days of the date of this order, the Respondents pay the Applicant $25,000 in respect of the Applicant's costs of the proceeding.
Verification Certificate
9. Within 160 days of the date of this order, the Respondents provide to the Applicant a signed certificate verifying compliance with orders 6 and 7 above and:
(a) in respect of paragraph 6 above, attaching a copy of the notices caused to be published in accordance with these orders; and
(b) in respect of paragraph 7 above, attaching a copy of one DL sized insert and a copy of the electronic notice caused to be distributed in accordance with these orders.
ANNEXURE A
A MESSAGE TO SOUTH AUSTRALIAN RESIDENTIAL CUSTOMERS WHO SIGNED UP TO ORIGIN’S DAILYSAVER ENERGY PLAN BETWEEN 1 FEBRUARY TO 30 JUNE 2013
Origin sells electricity and natural gas to residential customers in South Australia.
From 1 February to 30 June 2013, Origin’s website and the contracts sent to customers contained statements that under a DailySaver energy plan, residential customers would receive a discount on their usage charges of up to 16% for electricity and up to 12% for gas for the 12 month plan.
The rates used to calculate energy usage charges under the DailySaver plan, before the application of the discounts, were the same as the rates which applied under other Origin energy plans offered in conjunction with its market retail contract at the time. However, they were higher than the rates for energy usage charges which applied at the time under Origin’s Standard Retail Contract (also known as its Standing Offer).
If you entered into a DailySaver energy plan for electricity and/or natural gas between 1 February and 30 June 2013 and believe you were misled about the rates used to calculate the energy usage charges to which the discount would be applied, please contact [insert details].
Origin has been ordered to publish this message following court action by the ACCC
For more information visit www.accc.gov.au
Note: Entry of orders is dealt with in Rule 39.32 of the Federal Court Rules 2011.
Background
Background to the litigation
Decision
Reasons for decision
Ratio Decidendi