Allandale Blue Metal Pty Ltd v Roads and Maritime Services

Link copied
Case Copied 54 min read

Court of Appeal

New South Wales

Case Title: Allandale Blue Metal Pty Ltd v Roads and Maritime Services
Medium Neutral Citation: [2013] NSWCA 103
Hearing Date(s): 6 December 2012
Decision Date: 06 May 2013
Before: Macfarlan JA at [1]
Meagher JA at [37]
Ward JA at [59]
Decision:

1. Extend the time for filing of the Summons seeking leave to appeal from the decision of Sheahan J to the date of filing the Summons and dismiss the application for leave to extend the time for the filing of the Summons seeking leave to appeal from the decision of Biscoe J.
2. Grant leave to appeal from the decision of Sheahan J and dismiss the appeal.
3. Order the appellant to pay the respondent's costs of the Summons seeking leave to appeal and the appeal.

[Note: The Uniform Civil Procedure Rules 2005 provide (Rule 36.11) that unless the Court otherwise orders, a judgment or order is taken to be entered when it is recorded in the Court's computerised court record system. Setting aside and variation of judgments or orders is dealt with by Rules 36.15, 36.16, 36.17 and 36.18. Parties should in particular note the time limit of fourteen days in Rule 36.16.]

Catchwords: PRACTICE AND PROCEDURE - extension of time sought for leave to appeal against two interlocutory decisions of the Land and Environment Court New South Wales - where first decision ordered a separate determination of a preliminary question - where appellant delayed seeking leave to appeal pending outcome of the separate determination - whether extension of time would be consistent with the statutory objective of s 56 Civil Procedure Act 2005 (NSW)

PRACTICE AND PROCEDURE - separate determination of a preliminary question - whether resolution of preliminary question would be dispositive of the litigious controversy or substantially narrow the field of litigious controversy - whether issue must be 'critical' - question of construction of a development consent - whether preliminary question was relevant to primary issue in dispute - whether order of a separate determination was open to be made having regard to s 56 Civil Procedure Act 2005 (NSW)

VALUATION - consideration of the operation of s 56(1)(c) of Land Acquisition (Just Terms Compensation) Act 1991 (NSW)

ENVIRONMENT AND PLANNING - development consent - whether on proper construction of the consent extraneous material was incorporated expressly or by necessary implication into the consent
Legislation Cited: Civil Procedure Act 2005
Environmental Planning and Assessment Act 1979
Interpretation Act 1987
Land Acquisition (Just Terms Compensation) Act 1991
Land Acquisition Act 1989 (Cth)
Land and Environment Court Act 1979
Land Compensation Act 1961 (UK)
Land Compensation Act 1973 (UK)
Local Government Act 1919
Northumberland County District Planning Scheme Ordinance 1960
Uniform Civil Procedures Rules 2005
Cases Cited: ACR Trading Pty Ltd v Fat Sel Pty Ltd (1987) 11 NSWLR 67
Adelaide Corporation Pty Ltd v City of Charles Sturt [2008] SASC 260; 162 LGERA 196
Alcoa Australia Rolled Products Pty Ltd v Weston Aluminium Pty Ltd [2006] NSWCA 273
CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Allandale Blue Metal Pty Ltd v Roads and Maritime Services and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2013] NSWCA 103
Decision Date

CaseChat Overview and Summary

Allandale Blue Metal Pty Ltd (the appellant) sought leave to appeal against two interlocutory decisions of the Land and Environment Court of New South Wales. The first decision, by Sheahan J, ordered a separate determination of a preliminary question concerning the construction of a development consent. The appellant delayed seeking leave to appeal this decision pending the outcome of that separate determination. The second decision, by Biscoe J, related to an application for an extension of time. The appeal concerned whether the Indicative Plan, a document accompanying the development application, was incorporated into the development consent and whether Sheahan J erred in allowing reference to it for construction.

The primary legal issues before the Court of Appeal were whether an extension of time for seeking leave to appeal from Sheahan J's decision was consistent with the statutory objective of section 56 of the Civil Procedure Act 2005 (NSW), and whether Sheahan J had erred in construing the development consent by reference to the development application and its accompanying Indicative Plan. The court also considered whether the preliminary question determined by Sheahan J was dispositive of the litigious controversy or substantially narrowed its scope, and whether the order for a separate determination was permissible under section 56 of the Civil Procedure Act 2005 (NSW).

The Court of Appeal reasoned that while the appellant's delay in seeking leave to appeal Sheahan J's decision was not ideal, an extension of time was appropriate given the circumstances and the need to resolve the construction of the development consent. The court found that Sheahan J had correctly determined that the development consent was ambiguous regarding the area approved for quarrying and that it was permissible to refer to the development application and the Indicative Plan to resolve this ambiguity. The court concluded that Sheahan J did not err in his construction of the consent.

The Court of Appeal ordered an extension of time for the appellant to file its summons seeking leave to appeal from Sheahan J's decision, to the date of filing. However, the application for leave to extend time for the summons seeking leave to appeal from Biscoe J's decision was dismissed. Leave to appeal from Sheahan J's decision was granted, but the appeal itself was dismissed. The appellant was ordered to pay the respondent's costs.

Orders

Orders of the court

1. Extend the time for filing of the Summons seeking leave to appeal from the decision of Sheahan J to the date of filing the Summons and dismiss the application for leave to extend the time for the filing of the Summons seeking leave to appeal from the decision of Biscoe J.

2. Grant leave to appeal from the decision of Sheahan J and dismiss the appeal.

3. Order the appellant to pay the respondent's costs of the Summons seeking leave to appeal and the appeal.

[Note: The Uniform Civil Procedure Rules 2005 provide (Rule 36.11) that unless the Court otherwise orders, a judgment or order is taken to be entered when it is recorded in the Court's computerised court record system. Setting aside and variation of judgments or orders is dealt with by Rules 36.15, 36.16, 36.17 and 36.18. Parties should in particular note the time limit of fourteen days in Rule 36.16.]

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

It was also submitted that the Indicative Plan could at most assist only to construe the terms of the consent (and to confirm the approximate location of the quarry) and could not be used (as it had been) to prescribe and cut down the scope of all activities permitted on the land (by reference to the caution expressed in Hubertus). That submission assumes that the development consent on its face clearly permits quarrying across the whole of the lots in question. That is not the construction I would place on the development consent (and, though I accept that reference to the development application is permitted only after it is determined that there is a relevant basis for so doing, such a construction would be inconsistent with the contemplation in the development application itself that part of the land would also be used for grazing).Conclusion on (ii) For the reasons above, I am of the view that reference may permissibly be made to the development application and documents accompanying it (in particular, the Indicative Plan) when construing the development consent as this is necessary to resolve the ambiguity as to the area in respect of which quarrying was approved and that, having regard to those documents, Sheahan J did not err in answering the stated question in the affirmative. I would therefore make the following orders:1 Extend the time for filing of the Summons seeking leave to appeal from the decision of Sheahan J to the date of filing the Summons and dismiss the application for leave to extend the time for the filing of the Summons seeking leave to appeal from the decision of Biscoe J.2 Grant leave to appeal from the decision of Sheahan J and dismiss the appeal.3 Order the appellant to pay the respondent's costs of the Summons seeking leave to appeal and the appeal.**********

Ratio Decidendi

Legal Principle Established