Court of Appeal
Supreme Court
New South Wales
- Amendment notes
Medium Neutral Citation: All Seasons Air Pty Ltd v Regal Consulting Services Pty Ltd [2017] NSWCA 289 Hearing dates: 26 October 2017 Decision date: 10 November 2017 Before: Leeming and Payne JJA at [1];
White JA at [48]Decision: 1. Grant leave to appeal.
2. The applicant to file a notice of appeal in the form of the draft in the White Folder, and otherwise dispense with the requirements of service.
3. Appeal dismissed with costs.Catchwords: BUILDING AND CONSTRUCTION – contractor served claim under Building and Construction Security of Payment Act 1999 (NSW) – claim filed before reference date – whether claim valid – whether clause in building contract deemed claim to have been served on reference date Legislation Cited: Building and Construction Industry Security of Payment Act 1999 (NSW), ss 8, 13, 14, 15, 16, 17, 22, 25, 31, 32, 34
Supreme Court Act 1970 (NSW), s 101Cases Cited: Abergeldie Contractors Pty Ltd v Fairfield City Council [2017] NSWCA 113
Carr v Western Australia (2007) 232 CLR 138; [2007] HCA 47
Coleman v Power (2004) 220 CLR 1; [2004] HCA 39
Construction Forestry Mining & Energy Union v Mammoet Australia Pty Ltd (2013) 248 CLR 619; [2013] HCA 36
Felton v Mulligan (1971) 124 CLR 367 at 413; [1971] HCA 39
Fitz Jersey Pty Ltd v Atlas Construction Group Pty Ltd [2017] NSWCA 53
Lazarus v Independent Commission Against Corruption [2017] NSWCA 37; 341 ALR 483
Muller v Dalgety & Co Ltd (1909) 9 CLR 693; [1909] HCA 67
Southern Han Breakfast Point Pty Ltd (in liq) v Lewence Construction Pty Ltd [2016] HCA 52; 91 ALJR 233Category: Principal judgment Parties: All Seasons Air Pty Ltd (Applicant)
Regal Consulting Services (First Respondent)
Melissa McCurdie (Second Respondent)Representation: Counsel:
Solicitors:
D M Macfarlane (Applicant)
S Robertson; M Forgacs (First Respondent)
One Group Legal (Applicant)
Colin Biggers and Paisley Lawyers (First Respondent)
King Lawyers Australia (Second Respondent)
File Number(s): 2017/180343 Decision under appeal
- Court or tribunal:
- Supreme Court of New South Wales
- Jurisdiction:
- Equity Division
- Citation:
- [2017] NSWSC 613
- Date of Decision:
- 19 May 2017
- Before:
- McDougall J
- File Number(s):
- 2017/32925
Judgment
-
LEEMING and PAYNE JJA: This application for leave raises a single question of law on uncontroversial facts. The question is whether a provision in a construction contract which provided that early progress claims were deemed to have been made on the date specified for making a claim meant that a progress claim served prior to the reference date engaged the provisions of the Building and Construction Industry Security of Payment Act 1999 (NSW) (the Act). Although the amount in issue is substantially less than $100,000, and therefore requires a grant of leave by reason of Supreme Court Act 1970 (NSW), s 101(2)(r), there has been a concurrent hearing in accordance with the preference of both parties.
Background
-
In 2015, the parties entered into a written contract, styled…
Keep reading for free
Create a free CaseChat account to read All Seasons Air Pty Ltd v Regal Consulting Services Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2017] NSWCA 289
- Decision Date
CaseChat Overview and Summary
The central legal issue before the Court of Appeal was whether a clause within the building contract, which deemed the payment claim to have been served on the reference date, could operate to validate a claim that was factually served before that date. This required the court to consider the interplay between the contractual provisions and the statutory requirements of the *Security of Payment Act*.
The Court of Appeal, in dismissing the appeal, reasoned that the *Security of Payment Act* sets out specific requirements for the making of a valid payment claim, including that it must be served on or after the reference date. The court held that a contractual provision purporting to deem a claim served before the reference date as having been served on that date could not override the statutory requirement. To permit such a clause would undermine the legislative intent of the Act, which is to provide a statutory framework for progress payments. The court affirmed that the claim, having been served prematurely, was therefore invalid.
Leave to appeal was granted, but the appeal was ultimately dismissed with costs.
Orders
Orders of the court
1. Grant leave to appeal.
2. The applicant to file a notice of appeal in the form of the draft in the White Folder, and otherwise dispense with the requirements of service.
3. Appeal dismissed with costs.