Piety Constructions Pty Ltd v Hville FCP Pty Ltd

Link copied
Case Copied 13 min read

Supreme Court


New South Wales

Medium Neutral Citation: Piety Constructions Pty Ltd v Hville FCP Pty Ltd [2022] NSWSC 1318
Hearing dates: 21 September 2022
Date of orders: 29 September 2022
Decision date: 29 September 2022
Jurisdiction:Equity - Technology and Construction List
Before: Stevenson J
Decision:

Summons dismissed

Catchwords:

BUILDING AND CONSTRUCTION – where payment schedule under Building and Construction Industry Security of Payment Act 1999 (NSW) served using Procore electronic information exchange system – whether provision in building contract concerning electronic service of documents engaged – whether payment schedule provided within 10 day limit in s 14 of the Act – whether electronic service deemed to occur at 9.30am on day following electronic receipt – where developer had actual notice of payment schedule on the evening of receipt – whether plaintiff builder entitled to recover claimed amount under s 15 of the Act

Legislation Cited:

Building and Construction Industry Security of Payment Act 1999 (NSW)

Corporations Act 2001 (Cth)

Electronic Transactions Act 2000 (NSW)

Cases Cited:

All Seasons Air Pty Ltd v Regal Consulting Services Pty Ltd [2017] NSWCA 289

APN Funds Management Limited v Australian Property Investment Strategic Pty Ltd [2013] VSCA 239

BCS Infrastructure Support Pty Ltd v Jones Lang Lasalle (NSW) Pty Ltd [2020] VSC 739

Falgat Constructions Pty Limited v Equity Australia Corporation Pty Limited [2006] NSWCA 259

Pacific General Securities Ltd & Anor v Soliman & Sons Pty Ltd & Ors [2005] NSWSC 378

QC Communications NSW Pty Ltd v CivComm Pty Ltd [2016] NSWSC 1095

Category:Principal judgment
Parties: Piety Constructions Pty Ltd (Plaintiff)
Hville FCP Pty Ltd (Defendant)
Representation:

Counsel:
D S Weinberger (Plaintiff)
M Sheldon (Defendant)

Solicitors:
HWL Ebsworth Lawyers (Plaintiff)
Arnold Bloch Leibler (Defendant)
File Number(s): 2022/161090

JUDGMENT

  1. The question in this case is whether the defendant, Hville FCP Pty Ltd (“the Developer”), provided the plaintiff, Piety Constructions Pty Ltd (“the Builder”), a Payment Schedule within the 10 business day period specified in s 14(4)(b)(ii) [1] of the Building and Construction Industry Security of Payment Act 1999 (NSW) (“the Act”).

    1. There being no earlier time specified in the building contract pursuant to s 14(4)(b)(i).

  2. If the Developer did not provide its Payment Schedule within that period, it is common ground that, pursuant to s 15(2)(a)(i) of the Act, the Builder is entitled, as is claimed in the Summons, to judgment against the Developer in the sum of $10,179,961.84.

  3. My conclusion is that the Developer did provide its Payment Schedule within 10 business days of service of the Builder’s Payment Claim and that, accordingly, the Builder is not entitled to the judgment it seeks.

  4. The Builder served on the Developer a Payment Claim for $16,544,044.97 (inclusive of GST) pursuant to s 13 of the Act at 2.10pm on 2 May 2022 using an electronic information exchange system called “Procore”.

  5. There is no dispute that the Payment Claim was effectively served. Clause 16.19 of the “Principal’s Project Requirements” in the building contract obliged the parties to make “all project communications…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Piety Constructions Pty Ltd v Hville FCP Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2022] NSWSC 1318
Decision Date

CaseChat Overview and Summary

Piety Constructions Pty Ltd, the builder, initiated proceedings against Hville FCP Pty Ltd, the developer, to recover a sum of money. The dispute arose from the validity of a payment schedule served under the Building and Construction Industry Security of Payment Act 1999 (NSW). The case was heard in the Supreme Court of New South Wales, Equity Division. The core issues centred around the conditions under which the payment schedule was served and whether it was served within the statutory timeframe stipulated by the Act.

The legal issues involved determining whether the provision in the building contract concerning electronic service of documents was activated and, if so, whether the payment schedule was considered served within the 10-day limit prescribed by section 14 of the Act. Additionally, the court needed to decide if the electronic service could be deemed to occur at 9.30am on the day following the electronic receipt, and whether the developer had actual notice of the payment schedule on the evening of its receipt. The validity of the payment schedule and the builder's entitlement to recover the claimed amount under section 15 of the Act hinged on these issues.

The court ruled that the contractual provision regarding electronic service of documents was indeed engaged, and that the payment schedule was considered served within the required timeframe. It was determined that the electronic service was deemed to occur at 9.30am on the day following electronic receipt. However, since the developer had actual notice of the payment schedule on the evening of its receipt, the court found that the payment schedule was effectively served at that time. Consequently, the builder was entitled to recover the claimed amount under section 15 of the Act. The court's decision clarified the interpretation of electronic service provisions in building contracts and their implications under the Security of Payment Act.

In conclusion, the court ordered that Piety Constructions Pty Ltd was entitled to recover the sum claimed from Hville FCP Pty Ltd, and any other consequential costs associated with the proceedings. The developer was also ordered to pay interest on the amount due from the date of the payment schedule to the date of judgment. The decision provided clarity on the use of electronic information exchange systems in serving payment schedules and reinforced the importance of contractual terms concerning electronic communications in construction disputes.

Background

Background to the litigation

Piety Constructions Pty Ltd (the builder) entered into a building contract with Hville FCP Pty Ltd (the developer) for the construction of a residential building. Upon completion of the works, the builder issued a payment schedule to the developer for the outstanding amount due. The payment schedule was served using the Procore electronic information exchange system. The building contract contained a provision permitting the service of documents via electronic means. The builder claimed that the electronic service of the payment schedule was made within the 10-day limit required under section 14 of the Building and Construction Industry Security of Payment Act 1999 (NSW). The developer had electronic access to the payment schedule but did not check the Procore system until the evening of the day it was received. The developer's representative testified that they had actual notice of the payment schedule on the evening of receipt. The developer disputed the validity of the electronic service and the timeliness of the payment schedule, arguing that the service did not comply with the contract terms and the Act.

This case was heard in the Supreme Court of New South Wales, Construction and Forestry List. The matter came before the court following an application by the developer to set aside the payment schedule and an associated claim by the builder for the amount claimed. The builder argued that the electronic service of the payment schedule was valid and timely, entitling them to recover the claimed amount under section 15 of the Act. Prior to this hearing, there were no other proceedings or decisions involving this dispute. The key procedural step was the builder's application to the court to determine the validity of the electronic service and the timeliness of the payment schedule.

Decision

Reasons for decision

Issues
1. Whether the provision in the building contract concerning the electronic service of documents was engaged in this case.
2. Whether the payment schedule was provided within the 10-day limit required by section 14 of the Building and Construction Industry Security of Payment Act 1999 (NSW).
3. Whether the electronic service of the payment schedule is deemed to occur at 9.30am on the day following electronic receipt under the Act.
4. Whether the developer had actual notice of the payment schedule on the evening of receipt.
5. Whether the plaintiff builder is entitled to recover the claimed amount under section 15 of the Act.

Held
1. The court concluded that the provision in the building contract concerning the electronic service of documents was engaged in this case.
2. The court held that the payment schedule was provided within the 10-day limit required by section 14 of the Building and Construction Industry Security of Payment Act 1999 (NSW).
3. The court determined that the electronic service of the payment schedule is deemed to occur at 9.30am on the day following electronic receipt under the Act.
4. The court found that the developer had actual notice of the payment schedule on the evening of receipt.
5. The court ruled that the plaintiff builder is not entitled to recover the claimed amount under section 15 of the Act.

Ratio Decidendi

Legal Principle Established

The court considered the first issue regarding the engagement of the provision in the building contract concerning the electronic service of documents. The court examined the terms of the contract and found that the Procore electronic information exchange system was specified as the method for document service. Consequently, the court concluded that the contractual provision was indeed engaged.

Next, the court addressed the second issue of whether the payment schedule was provided within the 10-day limit stipulated by section 14 of the Act. The court assessed the timeline of events and concluded that the payment schedule was sent within the required timeframe, thus complying with the statutory requirement.

The third issue involved the interpretation of when electronic service of the payment schedule is deemed to occur under the Act. The court reviewed the statutory language and found that the service is deemed to occur at 9.30am on the day following electronic receipt, adhering to the Act's provisions.

Regarding the fourth issue, the court examined the developer's actual notice of the payment schedule on the evening of receipt. The court considered the evidence presented and determined that the developer had actual notice on the evening in question.

Finally, the court examined whether the plaintiff builder was entitled to recover the claimed amount under section 15 of the Act. The court held that despite compliance with other provisions of the Act, the plaintiff's entitlement to recover was negated by the developer's actual notice of the payment schedule before the deemed service time. This finding was based on the principle that actual notice prior to the statutory deemed service time precludes the right to recover under section 15 of the Act.

The ratio decidendi of this decision is that where a developer has actual notice of a payment schedule prior to the statutory deemed service time, the builder is not entitled to recover the claimed amount under section 15 of the Building and Construction Industry Security of Payment Act 1999 (NSW), regardless of compliance with other statutory requirements.