WÄRtsilÄ Australia Pty Ltd (ACN 003 736 892) v Primero Group Ltd (ACN 149 964 045)

Link copied
Case Copied 59 min read

SUPREME COURT OF SOUTH AUSTRALIA

(Civil: Application)

WÄRTSILÄ AUSTRALIA PTY LTD (ACN 003 736 892) v PRIMERO GROUP LTD (ACN 149 964 045) & ORS

[2020] SASC 162

Judgment of The Honourable Justice Stanley

2 September 2020

ADMINISTRATIVE LAW - JUDICIAL REVIEW - GROUNDS OF REVIEW - JURISDICTIONAL MATTERS

CONTRACTS - BUILDING, ENGINEERING AND RELATED CONTRACTS - REMUNERATION - STATUTORY REGULATION OF ENTITLEMENT TO AND RECOVERY OF PROGRESS PAYMENTS - ADJUDICATION OF PAYMENT CLAIMS

CONTRACTS - BUILDING, ENGINEERING AND RELATED CONTRACTS - THE CONTRACT - CONSTRUCTION OF PARTICULAR CONTRACTS AND IMPLIED CONDITIONS - OTHER MATTERS

Wärtsilä was engaged by AGL Barker Inlet Pty Ltd (AGL) under an Engineering, Procurement and Construction contract (EPC) to construct the Barker Inlet power station on Torrens Island.  Wärtsilä engaged Primero under a subcontract dated 18 April 2018 (subcontract) to perform civil, mechanical and electrical works and to supply tanks for the construction of the power station.

On 2 March 2020 Primero served a purported payment claim under s 13 of the Building and Construction Industry Security of Payment Act 2009 (SA) (the Act) for the sum of $85,751,118 (ex-GST).

On 10 March 2020 Wärtsilä served Primero with a payment schedule pursuant to s 14 of the Act.  Wärtsilä’s assessment of the payment schedule was made notwithstanding that Wärtsilä also set out that the payment claim was not a valid claim under the Act on the basis that, inter alia, there was no available reference date to support the payment claim.

On 31 March 2020 Primero served an adjudication application on the second respondent Resolution Institute, as the authorised nominating authority for the purposes of s 17(3)(b) of the Act.  By that application Primero resiled from its reliance on three other reference dates and in lieu thereof contended that there were available reference dates of 15 February 2020 or 28 February 2020.  The second of those relied upon “SW Completion”. 

On 9 April 2020 Wärtsilä served an adjudication response under the Act expanding on Wärtsilä’s assessment in its payment schedule.  The response, inter alia, identified why there was no available reference date to support the claim and why, as a consequence, the payment claim was invalid for the purposes of the Act. 

On 27 April 2020 the adjudicator determined that the payment claim was a valid claim under the Act on the basis, inter alia, that it was supported by a reference date of 28 February 2020.  Wärtsilä sought an order from this Court in the nature of certiorari to quash this adjudication determination.

At issue is whether Primero had complied with the requirements for SW Completion by 28 February 2020.  The parties accept that for SW Completion to have occurred the Manufacturer's Data Reports (MDRs) had to be provided to Wärtsilä and had to be available for inspection by Wärtsilä at the facility land. 

Whether this occurred depends upon whether these requirements were satisfied by Primero sending to Wärtsilä an email which included an hyperlink that allowed access to documents stored on a OneDrive…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read WÄRtsilÄ Australia Pty Ltd (ACN 003 736 892) v Primero Group... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details

Case
[2020] SASC 162
Decision Date

CaseChat Overview and Summary

Wärtsilä Australia Pty Ltd sought judicial review of a decision of an adjudicator who had determined that a payment claim made by Primero Group Ltd was valid under the Building and Construction Industry (Security of Payment) Act 1999 (Cth). The court was required to determine whether the adjudicator had jurisdiction to determine the validity of the payment claim and whether the payment claim was valid. The primary issue was whether Primero had provided the specified documents to Wärtsilä and made them available for inspection by 28 February 2020. The court found that Primero had not provided the documents to Wärtsilä in the manner required by the subcontract, as Wärtsilä was unable to download the documents in their entirety from the hyperlink provided by Primero. The court held that the adjudicator had jurisdiction to determine the validity of the payment claim, but the payment claim was invalid because Primero had not provided the documents to Wärtsilä in the manner required by the subcontract. The court granted Wärtsilä’s application for judicial review and quashed the adjudicator’s determination. The court ordered that the parties bear their own costs of the application for judicial review.

Orders

Orders of the court

Background

Background to the litigation

At issue is whether Primero had complied with the requirements for SW Completion by 28 February 2020. Whether that occurred depends on whether Primero had provided or made available for inspection certain documents to Wärtsilä by that date. I will come back to this issue in greater detail after setting out the factual and legal context to this application. Background Wärtsilä is the Australian subsidiary of Wärtsilä Corporation, a global supplier and provider of energy solutions. Wärtsilä was engaged by AGL Barker Inlet Pty Ltd (AGL) under an Engineering, Procurement and Construction contract (EPC) to construct the Barker Inlet power station on Torrens Island. Wärtsilä engaged Primero under a subcontract dated 18 April 2018 (subcontract) to perform civil, mechanical and electrical works and to supply tanks for the construction of the power station. The terms of the subcontract relevantly mirrored the terms of the EPC such that the obligations assumed by Wärtsilä under the EPC were imposed on Primero pursuant to the subcontract. On 2 March 2020 Primero served a purported payment claim under s 13 of the Act for the sum of $85,751,118 (ex-GST). On 10 March 2020 Wärtsilä served Primero with a payment schedule pursuant to s 14 of the Act assessing the value of the works claimed in the payment claim at $6,402,905.37 (ex-GST), without prejudice to Wärtsilä’s contention that there was no available reference date to support the payment claim. As Wärtsilä had already paid Primero interim on account payments totalling $18,074,80.27, Wärtsilä contended that the net amount payable under Primero’s payment claim was nil dollars. Wärtsilä’s assessment of the payment schedule was made notwithstanding that Wärtsilä also set out that the payment claim was not a valid claim under the Act on the basis that, inter alia, there was no available reference date to support the payment claim. On 31 March 2020 Primero served an adjudication application on the second respondent Resolution Institute, as the authorised nominating authority for the purposes of s 17(3)(b) of the Act. By that application Primero resiled from its reliance on three other reference dates and in lieu thereof contended that there were available reference dates of 15 February 2020 or 28 February 2020. The second of those relied upon SW Completion. On 9 April 2020 Wärtsilä served an adjudication response under the Act expanding on Wärtsilä’s assessment in its payment schedule. The response, inter alia, identified why there was no available reference date to support the claim and why, as a consequence, the payment claim was invalid for the purposes of the Act. On 27 April 2020 the adjudicator determined that the payment claim was a valid claim under the Act on the basis, inter alia, that it was supported by a reference date of 28 February 2020. Wärtsilä’s contentions Wärtsilä contends that the adjudicator lacked jurisdiction because the reference date grounding the entitlement to make the payment claim had not come into existence by 28 February 2020. As a result, the payment claim was invalid. Wärtsilä contends that the work required under the subcontract which had to be completed by 28 February 2020 was, inter alia, the provision of certain reports relating to SW Completion.

Evidence

Evidence before the court

Primero submits that once it sent Wärtsilä an email with an hyperlink providing access to the documents on the OneDrive server on 28 February 2020 the documents were provided and available for inspection at the facility land by anyone who had access to that hyperlink. In those circumstances SW Completion was achieved. Accordingly, the jurisdictional fact existed. The evidence Wärtsilä relied on the evidence of Joakim Fagerudd, Sumaira Amanat, Juha Nurmi, NR Lakshmanan, Mikko Piekkala, and Arash Moradi. Their evidence in chief was by affidavit. Joakim Fagerudd is a project planner and controller at Wärtsilä Finland Oy, the parent company of Wärtsilä. He was directly involved in the management of the construction project on behalf of Wärtsilä. Mr Fagerudd gave evidence that there were discussions between the parties in December 2019 and January 2020 regarding SW Completion and the wavier agreement which, inter alia, imposed the requirement that the MDRs be provided by 28 February 2020. He gave evidence of Primero sending Wärtsilä an hyperlink on 28 February 2020 that purportedly contained the MDRs. Mr Fagerudd read an email from Mr Lakshmanan, a senior project manager at Wärtsilä India Pvt Ltd, a subsidiary of Wärtsilä Finland Oy. This email, dated 3 March 2020, was sent to Dean Ercegovic of Primero informing Mr Ercegovic that Wärtsilä were unable to view the MDRs. On 4 March 2020 Primero delivered via courier a USB disk drive (USB) to the project site which was said to contain the MDRs. The email containing the hyperlink sent on 28 February was the first time that anyone who worked for Wärtsilä was aware that Primero were contending the MDRs were complete, and the USB delivered on 4 March 2020 was the first time a purported copy of the MDRs was at site and able to be reviewed. Mr Fagerudd described in some detail the importance of the content of the MDRs in the context of the contract between Wärtsilä and AGL. When AGL reviewed the MDRs provided on the USB on 4 March 2020 they identified missing documents and information as well as other errors. Wärtsilä having confirmed these issues informed Primero of these deficiencies by letter dated 2 April 2020. In cross-examination Mr Fagerudd agreed that the subcontract and the EPC were prepared as back-to-back contracts. However, Wärtsilä’s scope of work under the EPC included more work than Primero’s scope of work under the subcontract. Wärtsilä was under an obligation in the EPC to provide to AGL the same MDRs that Primero had to provide to Wärtsilä under the subcontract. This was an essential part of achieving “Facility Completion” under the EPC and was an example of the back-to-back nature of the contracts. He agreed that when Primero completed its works to achieve SW Completion under the subcontract, Wärtsilä could then complete its works to achieve Facility Completion under the EPC. Mr Fagerudd was aware that Mr Nurmi forwarded to AGL the email containing the hyperlink provided by Primero. He was also aware that the waiver agreement which imposed the obligation on Primero to provide the MDRs by 28 February 2020 also concerned the waiver of provision of post-completion security, and so Primero would have been aiming to achieve SW Completion on or before that date. He also agreed that Primero had provided a submission of part of the MDRs information on 28 January 2020. At the time of the waiver agreement on 10 February 2020 Wärtsilä had accepted this partial submission, as delivery of part of the MDRs under the subcontract, via provision of an hyperlink contained in an email.

Decision

Reasons for decision

For these reasons it is unnecessary to consider Primero’s contention that by its conduct Wärtsilä waived compliance with cl 40. Conclusion In the circumstances I would grant the application for judicial review and make an order in the nature of certiorari quashing the adjudication determination of 27 April 2020 made by the third respondent. I would hear the parties as to costs.

Ratio Decidendi

Legal principle established

At issue is the proper construction of the subcontract. The principles applicable to contractual construction are explained by the High Court in Electricity Generation Corporation v Woodside Energy Ltd[8] and in Mount Bruce Mining Pty Ltd v Wright Prospecting Pty Ltd.[9]Consideration [8] [2014] HCA 7 at [35], (2014) 251 CLR 640 at 656-657. [9] [2015] HCA 37 at [46]-[52], (2015) 256 CLR 104 at 116-117.The issue At issue is whether Primero achieved SW Completion by providing to Wärtsilä the documents specified in item (2) and by making available at the facility land the documents specified in item (8). The parties dispute whether the subcontract expressly specified how this was to occur. Findings concerning the hyperlink I find that on 28 February 2020 Primero provided to Wärtsilä by email a OneDrive hyperlink providing access to a file in the cloud constituting the MDRs. I also find that on that date Wärtsilä was unable to download completely that documentation. I accept the evidence of Ms Amanat in that regard. I find the hyperlink did not amount to provision of the documents for the purposes of item (2) of the definition of SW Completion because the provision of the hyperlink merely provided a means by which Wärtsilä was permitted to download documents stored in the cloud. Until it did so, those documents had not been provided. I also find that the hyperlink did not amount to making the documents available for inspection by Wärtsilä at the facility land for the purposes of item (8) because until all the documents were downloaded, they were not capable of being inspected at the facility land. The contractual requirement in item (2) that the specified documents be “provided to the Contractor” must be understood in its commercial context. The same proposition applies in relation to the contractual requirement in item (8) that the specified documents are “available for inspection by the Contractor at the Facility Land”. The meaning of “provided” and “available for inspection” The construction of the obligation in the subcontract that documents be “provided” and “available for inspection” can be distilled to a constructional choice between providing a means by which the documents are merely capable of being accessed (by hardcopy or electronically) by the recipient, and the provision of a means by which the documents are not only capable of being accessed (by hardcopy or electronically), but are capable of being read (in hardcopy or electronically) in their entirety, and completely downloaded, by the recipient (in the case of electronic delivery). For the reasons which follow the latter construction is to be preferred. While the ordinary grammatical meaning of “provided” is supplied or furnished[10] the expression must be understood to mean, in the context of the subcontract, that the documents are in the possession of Wärtsilä such that they are capable of being accessed and read. In the same way, the requirement that the documents specified in item (8) are available for inspection at the facility land is satisfied when the documents could be accessed and read at Wärtsilä’s site office on Torrens Island. That is consistent with the definition of “available” in the Australian Concise Oxford Dictionary meaning “capable of being used; at one’s disposal”. Moreover, the contractual obligation was not merely that the specified documents were “available”. The obligation was that the documents were available “for inspection by the Contractor at the Facility Land”. The commercial purpose of this obligation was to enable Wärtsilä to view and consider the documents on a continuing basis. As a matter of fact this could not occur unless Primero permitted Wärtsilä to have continuing access to the documents through the hyperlink or Wärtsilä downloaded the documents. [10] The Australian Concise Oxford Dictionary, 3rd edition.