SUPREME COURT OF SOUTH AUSTRALIA
(Civil: Application)
WÄRTSILÄ AUSTRALIA PTY LTD (ACN 003 736 892) v PRIMERO GROUP LTD (ACN 149 964 045) & ORS
[2020] SASC 162
Judgment of The Honourable Justice Stanley
2 September 2020
ADMINISTRATIVE LAW - JUDICIAL REVIEW - GROUNDS OF REVIEW - JURISDICTIONAL MATTERS
CONTRACTS - BUILDING, ENGINEERING AND RELATED CONTRACTS - REMUNERATION - STATUTORY REGULATION OF ENTITLEMENT TO AND RECOVERY OF PROGRESS PAYMENTS - ADJUDICATION OF PAYMENT CLAIMS
CONTRACTS - BUILDING, ENGINEERING AND RELATED CONTRACTS - THE CONTRACT - CONSTRUCTION OF PARTICULAR CONTRACTS AND IMPLIED CONDITIONS - OTHER MATTERS
Wärtsilä was engaged by AGL Barker Inlet Pty Ltd (AGL) under an Engineering, Procurement and Construction contract (EPC) to construct the Barker Inlet power station on Torrens Island. Wärtsilä engaged Primero under a subcontract dated 18 April 2018 (subcontract) to perform civil, mechanical and electrical works and to supply tanks for the construction of the power station.
On 2 March 2020 Primero served a purported payment claim under s 13 of the Building and Construction Industry Security of Payment Act 2009 (SA) (the Act) for the sum of $85,751,118 (ex-GST).
On 10 March 2020 Wärtsilä served Primero with a payment schedule pursuant to s 14 of the Act. Wärtsilä’s assessment of the payment schedule was made notwithstanding that Wärtsilä also set out that the payment claim was not a valid claim under the Act on the basis that, inter alia, there was no available reference date to support the payment claim.
On 31 March 2020 Primero served an adjudication application on the second respondent Resolution Institute, as the authorised nominating authority for the purposes of s 17(3)(b) of the Act. By that application Primero resiled from its reliance on three other reference dates and in lieu thereof contended that there were available reference dates of 15 February 2020 or 28 February 2020. The second of those relied upon “SW Completion”.
On 9 April 2020 Wärtsilä served an adjudication response under the Act expanding on Wärtsilä’s assessment in its payment schedule. The response, inter alia, identified why there was no available reference date to support the claim and why, as a consequence, the payment claim was invalid for the purposes of the Act.
On 27 April 2020 the adjudicator determined that the payment claim was a valid claim under the Act on the basis, inter alia, that it was supported by a reference date of 28 February 2020. Wärtsilä sought an order from this Court in the nature of certiorari to quash this adjudication determination.
At issue is whether Primero had complied with the requirements for SW Completion by 28 February 2020. The parties accept that for SW Completion to have occurred the Manufacturer's Data Reports (MDRs) had to be provided to Wärtsilä and had to be available for inspection by Wärtsilä at the facility land.
Whether this occurred depends upon whether these requirements were satisfied by Primero sending to Wärtsilä an email which included an hyperlink that allowed access to documents stored on a OneDrive…
Keep reading for free
Create a free CaseChat account to read WÄRtsilÄ Australia Pty Ltd (ACN 003 736 892) v Primero Group... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Details
- Case
- [2020] SASC 162
- Decision Date
CaseChat Overview and Summary
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence before the court
Decision
Reasons for decision
Ratio Decidendi
Legal principle established
At issue is the proper construction of the subcontract. The principles applicable to contractual construction are explained by the High Court in Electricity Generation Corporation v Woodside Energy Ltd[8] and in Mount Bruce Mining Pty Ltd v Wright Prospecting Pty Ltd.[9]Consideration [8] [2014] HCA 7 at [35], (2014) 251 CLR 640 at 656-657. [9] [2015] HCA 37 at [46]-[52], (2015) 256 CLR 104 at 116-117.The issue At issue is whether Primero achieved SW Completion by providing to Wärtsilä the documents specified in item (2) and by making available at the facility land the documents specified in item (8). The parties dispute whether the subcontract expressly specified how this was to occur. Findings concerning the hyperlink I find that on 28 February 2020 Primero provided to Wärtsilä by email a OneDrive hyperlink providing access to a file in the cloud constituting the MDRs. I also find that on that date Wärtsilä was unable to download completely that documentation. I accept the evidence of Ms Amanat in that regard. I find the hyperlink did not amount to provision of the documents for the purposes of item (2) of the definition of SW Completion because the provision of the hyperlink merely provided a means by which Wärtsilä was permitted to download documents stored in the cloud. Until it did so, those documents had not been provided. I also find that the hyperlink did not amount to making the documents available for inspection by Wärtsilä at the facility land for the purposes of item (8) because until all the documents were downloaded, they were not capable of being inspected at the facility land. The contractual requirement in item (2) that the specified documents be “provided to the Contractor” must be understood in its commercial context. The same proposition applies in relation to the contractual requirement in item (8) that the specified documents are “available for inspection by the Contractor at the Facility Land”. The meaning of “provided” and “available for inspection” The construction of the obligation in the subcontract that documents be “provided” and “available for inspection” can be distilled to a constructional choice between providing a means by which the documents are merely capable of being accessed (by hardcopy or electronically) by the recipient, and the provision of a means by which the documents are not only capable of being accessed (by hardcopy or electronically), but are capable of being read (in hardcopy or electronically) in their entirety, and completely downloaded, by the recipient (in the case of electronic delivery). For the reasons which follow the latter construction is to be preferred. While the ordinary grammatical meaning of “provided” is supplied or furnished[10] the expression must be understood to mean, in the context of the subcontract, that the documents are in the possession of Wärtsilä such that they are capable of being accessed and read. In the same way, the requirement that the documents specified in item (8) are available for inspection at the facility land is satisfied when the documents could be accessed and read at Wärtsilä’s site office on Torrens Island. That is consistent with the definition of “available” in the Australian Concise Oxford Dictionary meaning “capable of being used; at one’s disposal”. Moreover, the contractual obligation was not merely that the specified documents were “available”. The obligation was that the documents were available “for inspection by the Contractor at the Facility Land”. The commercial purpose of this obligation was to enable Wärtsilä to view and consider the documents on a continuing basis. As a matter of fact this could not occur unless Primero permitted Wärtsilä to have continuing access to the documents through the hyperlink or Wärtsilä downloaded the documents. [10] The Australian Concise Oxford Dictionary, 3rd edition.