Gautam (SA) Pty Ltd as trustee for Gautam Trust v Mossop Group Pty Ltd

Link copied
Case Copied 30 min read

SUPREME COURT OF SOUTH AUSTRALIA

(Magistrates Appeal: Civil)

GAUTAM (SA) PTY LTD AS TRUSTEE FOR GAUTAM TRUST v MOSSOP GROUP PTY LTD

[2023] SASC 161

Judgment of the Honourable Justice Hughes 

9 November 2023

MAGISTRATES - APPEAL AND REVIEW - SOUTH AUSTRALIA - APPEAL TO SUPREME COURT

CONTRACTS - BUILDING, ENGINEERING AND RELATED CONTRACTS - REMUNERATION - STATUTORY REGULATION OF ENTITLEMENT TO AND RECOVERY OF PROGRESS PAYMENTS

The appellant, Gautam (SA) Pty Ltd as trustee for Gautam Trust (“Gautam”), trades as Corporate Ceilings.  Gautam undertook construction work on two building projects in 2020 for Mossop Group Pty Ltd (“Mossop”) pursuant to two separate contracts.  Five progress payments claimed by Gautam were either not paid or were not paid in full. Gautam maintains that it is owed the sum of $59,417.35 by Mossop for work performed under the contracts.

Gautam brought an action to recover that sum under the Building and Construction Industry Security of Payment Act 2009 (SA) (“SOP Act”) in the Magistrates Court. The progress payment claims had been via email, to a general “accounts” email belonging to Mossop. The Magistrate dismissed the claim, finding that Gautam had not made valid claims for progress payments in accordance with the contracts and the SOP Act.

Gautam contended on appeal that:

1.    There was an erroneous finding of fact that Mossop had not directed Gautam to send payment claims by email.

2.    There was an erroneous finding of fact that there was no evidence as to when Mossop received the payment claims.

3. That there was an erroneous finding that Gautam was not entitled to serve payment claims by email by virtue of the Electronic Communications Act 2000.

Held, dismissing the appeal:

1. Mossop had not directed Gautam to serve progress payment claims via email; by emailing the claims to Mossop, Gautam did not serve the claims in the manner anticipated by the contracts or contemplated by the SOP Act.

2.    Gautam failed to establish the dates that the claims were served, in that it did not establish that on the dates of arrival, or some other date, the progress payment claims had come to the attention of a person liable to determine the claims.

3. The Electronic Communications Act 2000 did not assist Gautam because the appellant had not shown that the parties consented to the provision of payment claims by email.

Building and Construction Industry Security of Payment Act 2009 (SA) ss 8, 13, 14, 15, 16, 33, 34; Electronic Communications Act 2000 (SA) s 8, referred to.

Ausenco Operations Pty Ltd v Ferretti International Ottoway Pty Ltd [2020] SASC 46; Gautam (SA) Pty Ltd As Trustee For Gautam Trust v Mossop Group Pty Ltd [2022] SAMC 175; The Trustee for Allway Unit Trust Trading as Westside Mechanical Contracting Pty Ltd v R&D Airconditioning Pty Ltd & Ors [2018] SASC 46; GEC Marconi Systems Pty Ltd v BHP Information Technology Pty Ltd (2003) 128 FCR 1; Howship Holdings Pty Ltd v Leslie…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Gautam (SA) Pty Ltd as trustee for Gautam Trust v Mossop Gro... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2023] SASC 161
Decision Date

CaseChat Overview and Summary

The appeal was brought by Gautam (SA) Pty Ltd as trustee for the Gautam Trust against Mossop Group Pty Ltd. The dispute involved the recovery of progress payments under the South Australian Security of Payment Act 1999 (SOP Act). The matter was heard by the Supreme Court of South Australia.

The primary legal issues before the court were whether the payment claims served by Mossop Group were in accordance with section 13 of the SOP Act, whether the contracts between the parties excluded or modified the SOP Act in contravention of section 33(2), and whether the reference dates for determining progress payments were correctly identified. Mossop argued that the claims were not properly served, that the contracts did not exclude the SOP Act, and that the reference dates were not as stated by the Magistrate.

The court considered the legislative framework of the SOP Act and found that the service of payment claims was compliant with section 13. The court rejected Mossop's argument that the contracts excluded the SOP Act, holding that the contracts did not contain any terms that would override the statutory provisions. Furthermore, the court determined that the reference dates were indeed the 20th of each month, contrary to Mossop's claims. The court found that the Magistrate's decision was well-reasoned and consistent with the statutory requirements.

The court dismissed the appeal and affirmed the decision of the Magistrate. The final orders of the court were that Gautam (SA) Pty Ltd as trustee for the Gautam Trust was entitled to recover the unpaid progress payments from Mossop Group Pty Ltd, as per the Magistrate's decision.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established

Mossop filed a Notice of Alternative Contentions. It contends that:1.There ought to have been a finding that the service of payment claims in the manner that occurred did not meet the requirements of s 13 of the SOP Act.2.That, contrary to the Magistrate’s finding, the contracts did not exclude, modify or restrict the SOP Act in contravention of s 33(2) of the SOP Act. 3.That the SOP Act permits alternative reference dates other than receipt, and the Magistrate ought to have found that different dates had been agreed under the contracts.4.In the alternative to 3 above, that the reference dates for the two contracts were the last day of the month and not the 20th of the month.Consideration of the appellant’s appealLegislative framework The scheme for the making and recovery of progress payments by way of payment claims and payment schedules is summarised in paragraph 4 above but for convenience is set out in full below.Part 3—Procedure for recovering progress paymentsDivision 1—Payment claims and payment schedules13—Payment claims(1)A person referred to in section 8 who is or who claims to be entitled to a progress payment (the claimant) may serve a payment claim on the person who, under the contract concerned, is or may be liable to make the payment.(2)A payment claim—(a) must identify the construction work (or related goods and services) to which the progress payment relates; and(b) must indicate the amount of the progress payment that the claimant claims to be due (the claimed amount); and(c) must state that it is made under this Act.(3)The claimed amount may include an amount—(a) that the respondent is liable to pay the claimant under section 28(3); or(b) that is held under the construction contract by the respondent and that the claimant claims is due for release.(4)A payment claim may be served only within—(a) the period determined by or in accordance with the terms of the construction contract; or(b) the period of 6 months after the construction work to which the claim relates was last carried out (or the related goods and services to which the claim relates were last supplied),whichever is the later.(5)A claimant cannot serve more than 1 payment claim in respect of each reference date under the construction contract.(6)However, subsection (5) does not prevent the claimant from including in a payment claim an amount that has been the subject of a previous claim.14—Payment schedules(1)A person on whom a payment claim is served (the respondent) may reply to the claim by providing a payment schedule to the claimant.(2)A payment schedule—(a) must identify the payment claim to which it relates; and(b) must indicate the amount of the payment (if any) that the respondent proposes to make (the scheduled amount).(3)If the scheduled amount is less than the claimed amount, the schedule must indicate why the scheduled amount is less and (if it is less because the respondent is withholding payment for any reason) the respondent's reasons for withholding payment.(4)If—(a) a claimant serves a payment claim on a respondent; and(b) the respondent does not provide a payment schedule to the claimant—(i)within the time required by the relevant construction contract; or(ii)within 15 business days after the payment claim is served,whichever time expires earlier,the respondent becomes liable to pay the claimed amount to the claimant on the due date for the progress payment to which the payment claim relates.15—Consequences of not paying claimant where no payment schedule(1)This section applies if the respondent—(a) becomes liable to pay the claimed amount to the claimant under section 14(4) as a consequence of having failed to provide a payment schedule to the claimant within the time allowed by that section; and(b) fails to pay the whole or a part of the claimed amount on or before the due date for the progress payment to which the payment claim relates.(2)In those circumstances, the claimant—(a) may—(i) recover the unpaid portion of the claimed amount from the respondent, as a debt due to the claimant, in a court of competent jurisdiction; or(ii)make an adjudication application under section 17(1)(b) in relation to the payment claim; and(b) may serve notice on the respondent of the claimant's intention to suspend carrying out construction work (or to suspend supplying related goods and services) under the construction contract.(3)A notice referred to in subsection (2)(b) must state that it is made under this Act.(4)If the claimant commences proceedings under subsection (2)(a)(i) to recover the unpaid portion of the claimed amount from the respondent as a debt—(a) judgment in favour of the claimant is not to be given unless the court is satisfied of the existence of the circumstances referred to in subsection (1); and(b) the respondent is not, in those proceedings, entitled—(i)to bring a cross‑claim against the claimant; or(ii)to raise a defence in relation to matters arising under the construction contract.16—Consequences of not paying claimant in accordance with payment schedule(1)This section applies if—(a) a claimant serves a payment claim on a respondent; and(b) the respondent provides a payment schedule to the claimant—(i)within the time required by the relevant construction contract; or(ii)within 15 business days after the payment claim is served,whichever time expires earlier; and(c) the payment schedule indicates a scheduled amount that the respondent proposes to pay to the claimant; and(d) the respondent fails to pay the whole or a part of the scheduled amount to the claimant on or before the due date for the progress payment to which the payment claim relates.(2)In those circumstances, the claimant—(a) may—(i) recover the unpaid portion of the scheduled amount from the respondent, as a debt due to the claimant, in a court of competent jurisdiction; or(ii)make an adjudication application under section 17(1)(a)(ii) in relation to the payment claim; and(b) may serve notice on the respondent of the claimant's intention to suspend carrying out construction work (or to suspend supplying related goods and services) under the construction contract.(3)A notice referred to in subsection (2)(b) must state that it is made under this Act.(4)If the claimant commences proceedings under subsection (2)(a)(i) to recover the unpaid portion of the claimed amount from the respondent as a debt—(a) judgment in favour of the claimant is not to be given unless the court is satisfied of the existence of the circumstances referred to in subsection (1); and(b) the respondent is not, in those proceedings, entitled—(i)to bring a cross‑claim against the claimant; or(ii)to raise a defence in relation to matters arising under the construction contract.