Adelaide Corporation v Jennings Industries Ltd

Link copied
Case Copied 36 min read

HIGH COURT OF AUSTRALIA

Murphy, Wilson, Brennan, Deane and Dawson JJ.

THE CORPORATION OF THE CITY OF ADELAIDE v. JENNINGS INDUSTRIES LIMITED

(1985) 156 CLR 274

14 February 1985

Building Contract

Building Contract—Delay—Failure and insolvency of sub-contractor—Whether implied term to nominate new sub-contractor—Requirement of architect for builder to complete—Default by builder—Completion by proprietor—Whether cost to be borne by proprietor or builder.

Decisions


MURPHY J. I agree with the judgment of Mr Justice Wilson. The appeal should be allowed; the judgment of the Full Court of the Supreme Court of South Australia should be set aside and the judgment of Mr Justice Matheson restored.

WILSON J. These proceedings are the result of a building dispute between the parties. In March 1971, the appellant as proprietor entered into a contract with the respondent as builder for the construction of the Adelaide Festival Centre. The contract provided, inter alia, for the supply and installation of various mechanical services to be undertaken by a sub-contractor to be nominated by the proprietor. The contract provided for a prime cost sum of $584,124.00 for this section of the contract works. Following the procedure prescribed by cl. 15 of the conditions attached to the Articles of Agreement ("the Conditions"), the proprietor nominated a firm of six companies trading under the name of W. Curl &Sons ("the Sub-Contractor") and the builder entered into a contract with that firm.

2. The facts surrounding the execution of the works are not in dispute. The work proceeded and on 10 July 1973 the architect who was supervising the contract on behalf of the proprietor issued a notice of practical completion which, save with respect to some sections of the works which are not material, was operative from 2 June 1973. The notice stipulated a defects liability period in respect of mechanical services of 52 weeks expiring on 1 June 1974. Unfortunately, the Sub-Contractor experienced financial difficulty in the latter part of 1973 and this interfered with its completion of certain remedial work. A special manager was appointed to conduct the Sub-Contractor's affairs but the remedial work remained unfinished. Accordingly the architect wrote to the builder on 1 February 1974 urging it to terminate the sub-contract and arrange with another sub-contractor to complete the work. The builder made a further effort to have the Sub-Contractor fulfil its obligations but without success. On 1 March 1974 it wrote to the special manager pointing out the failure of the Sub-Contractor to co-operate and adding:

"We therefore have no alternative other than to place all items
of maintenance and finalisation of the original contract in the hands of others, and debit all costs against Curl's contract. ..."


3. In anticipation of the approaching end of the defects liability period consulting engineers carried out inspections in April and May 1974 and compiled a lengthy list of outstanding items relating to the mechanical services sub-contract. A copy of this list was supplied to the builder under covering letter from the engineers dated 30 May 1974 and was…
CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Adelaide Corporation v Jennings Industries Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[1985] HCA 7
Decision Date

CaseChat Overview and Summary

The Adelaide Corporation (the proprietor) and Jennings Industries Ltd (the builder) were parties to a building contract. The dispute arose when a nominated sub-contractor, responsible for a significant portion of the work, failed and became insolvent. The architect required the builder to complete the sub-contracted work, which the builder refused to do. The proprietor then completed the work itself and sought to recover the costs from the builder. The matter proceeded to the Full Court of the Supreme Court of South Australia, and subsequently to the High Court of Australia.

The High Court was required to determine whether an implied term existed within the building contract obliging the proprietor to nominate a new sub-contractor upon the insolvency of the original nominated sub-contractor. Furthermore, the Court had to consider whether the builder was in default by refusing to complete the work that had been sub-contracted, and consequently, whether the costs incurred by the proprietor in completing the work should be borne by the builder or the proprietor.

The High Court held that there was no implied term requiring the proprietor to nominate a new sub-contractor. The Court reasoned that the contract placed the responsibility for the sub-contractor's performance on the builder, and the builder's refusal to complete the work constituted a default under the contract. Consequently, the proprietor was entitled to complete the work and recover the costs from the builder. The appeal was allowed with costs, the order of the Full Court of the Supreme Court of South Australia was set aside, and in lieu thereof, the appeal to that Court was dismissed with costs.

Orders

Orders of the court

Appeal allowed with costs, order of the Full Court of the Supreme Court of South Australia set aside and, in lieu thereof, order that the appeal to that Court be dismissed with costs.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.