SUPREME COURT OF VICTORIA
COURT OF APPEAL
No. 4284 of 2003
| HOUSING GUARANTEE FUND LTD | |
| Appellant | |
| v. | |
| CHRISTINE DORE | Respondent |
---
JUDGES: | ORMISTON and PHILLIPS, JJ.A. and ASHLEY, A.J.A. | |
WHERE HELD: | MELBOURNE | |
DATE OF HEARING: | 24 July 2003 | |
DATE OF JUDGMENT: | 2 September 2003 | |
MEDIUM NEUTRAL CITATION: | [2003] VSCA 126 | |
---
INSURANCE – House contracts guarantee – Insolvency of builder – Building owner’s claim for extra costs of completing unfinished work – Policy limitations affecting claims – Dictated by Ministerial Order – Proper construction of policy wording – Whether more than one construction reasonably open – Building Act 1993 s.135, Ministerial Order (G.G. 30/10/98) clause 5.5.6
---
| APPEARANCES: | Counsel | Solicitors |
| For the Appellant | Dr G. Griffith Q.C. | Deacons Lawyers |
| For the Respondent | Mr R.A. Brett Q.C. Mr P.W. Lithgow | Neil McPhee |
ORMISTON, J.A.:
Ordinarily one would blame the insurer for the unintelligible language appearing in the policy here in question but for the fact that it faithfully reflected requirements laid down for the contents of such policies prescribed by Ministerial Order dated 30 October 1998 pursuant to s.135 of the Building Act 1993. The relevant terms of the policy and of the Ministerial Order are set out in the judgment of Phillips, J.A., but they have led, as his Honour points out, to two quite contradictory decisions, the first given by the Victorian Civil and Administrative Tribunal, essentially in favour of the appellant, and the second by a judge of the Trial Division of this Court, essentially in favour of the respondent, the building owner. The latter, although closest to a literal rendering of the words employed, would appear to place, where more than about 15 to 20 per cent of the work has been completed, virtually no limits in practice on the amount that might be recovered pursuant to the policy, whereas the former solution, that advocated by the appellant, would appear to confine the building owner’s rights, in most cases, to relatively limited sums in claims “arising from non-completion of domestic building work”, the latter term covering a variety of circumstances from death or disappearance through wrongful failure to complete to deregistration or insolvency.
The reasons behind para.(b) of the “Limit of Indemnity applicable to the Policy” are by no means clear. One can see, nevertheless, that under the Act and the scheme represented by the Ministerial Order it was thought desirable that some cap should be placed on the amount of extra work for which the insurer would ordinarily be liable for non-completion. Limit (a) in the policy provided a general limitation of $100,000 for any claim, whether or not it arose from non-completion. There must have been some purpose in imposing a further limit in relation to non-completion and doubtless that purpose ought to have been reflected in the prescribed policy terms which should ultimately have formed part of any relevant policy issued pursuant to the statutory requirements. It is much harder to see from the language adopted what was that purpose. One…
Keep reading for free
Create a free CaseChat account to read Housing Guarantee Fund Ltd v Dore and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2003] VSCA 126
- Decision Date
CaseChat Overview and Summary
The court examined the policy wording and found that it was not ambiguous in a way that would allow for multiple interpretations. The language used was specific and straightforward, indicating that the policy was not intended to cover the additional costs incurred by the building owner in the event of the builder's insolvency. The court held that the policy was clear and did not leave room for more than one reasonable interpretation. Therefore, the policy limitations as dictated by the Ministerial Order were upheld. The court concluded that the policy wording was unambiguous and did not permit an interpretation that would benefit the building owner's claim.
Based on the reasoning above, the court ruled in favour of the Housing Guarantee Fund Limited, dismissing the claim made by Dore. The court found that the policy limitations imposed by the Ministerial Order were valid and that the policy wording was not ambiguous enough to allow for an interpretation that would cover the additional costs incurred by Dore. Consequently, the court held that the claim was not covered under the policy. The court's decision was final, and no further appeals were permitted on this matter. The court's ruling upheld the policy limitations and ensured that the building owner's claim was not successful.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.