SUPREME COURT OF QUEENSLAND
CITATION:
Callide Power Management P/L v Callide Coalfields (Sales) P/L [2008] QCA 182
PARTIES:
CALLIDE POWER MANAGEMENT PTY. LIMITED
ACN 082 468 700
(applicant/respondent)
v
CALLIDE COALFIELDS (SALES) PTY LTD
ACN 082 543 986
(respondent/appellant)FILE NO/S:
Appeal No 500 of 2008
SC No 8437 of 2007DIVISION:
Court of Appeal
PROCEEDING:
General Civil Appeal
ORIGINATING COURT:
Supreme Court at Brisbane
DELIVERED ON:
11 July 2008
DELIVERED AT:
Brisbane
HEARING DATE:
10 June 2008
JUDGES:
Keane and Muir JJA and Mackenzie AJA
Separate reasons for judgment of each member of the Court, each concurring as to the orders madeORDER:
Appeal dismissed1.
Appellant to pay the respondent's costs of and incidental to the appeal to be assessed on the standard basis2.
CATCHWORDS:
CONTRACT – GENERAL CONTRACTUAL PRINCIPLES – CONSTRUCTION AND INTERPRETATION OF CONTRACTS – where the appellant was unable, due to events of force majeure, to meet its contractual obligations to deliver quantities of coal to the respondent during a certain period – where the respondent amended by notice the quantities of coal required to be supplied by the appellant to it in future deliveries – whether such amendment was permissible under the contract
Adelaide Corporation v Jennings Industries Ltd (1985) 156 CLR 274; [1985] HCA 7, considered
Australian Broadcasting Commission v Australasian Performing Right Association Ltd (1973) 129 CLR 99; [1973] HCA 36, applied
Codelfa Construction Pty Ltd v State Rail Authority of New South Wales (1982) 149 CLR 337; [1982] HCA 24, applied
McCann v Switzerland Insurance Ltd (2000) 203 CLR 579; [2000] HCA 65, considered
Sandra Investments Pty Ltd v Booth (1983) 153 CLR 153; [1983] HCA 46, considered
Toll (FGCT) P/L v Alphapharm P/L (2004) 219 CLR 165; [2004] HCA 52, appliedCOUNSEL:
R W Gotterson QC for the appellant
D B Fraser QC, with P W Telford, for the respondentSOLICITORS:
Minter Ellison for the appellant
BCI Duells Lawyers for the respondent
KEANE JA: Callide Coalfields (Sales) Pty Ltd ("CCS") supplies coal to Callide Power Management Pty Ltd ("CPM") under a contract made on 11 May 1998 ("the agreement"). During January and February 2007, CCS claimed that its obligation to deliver coal to CPM at the contracted rate was suspended by events of force majeure under the agreement. On 9 June 2007 CPM gave CCS notices calling upon it to deliver amounts of coal which would have the effect of catching up the shortfall for the calendar year 2007 which would otherwise have resulted from the earlier suspension of deliveries.
CCS contended that it was not obliged to comply with these notices; and CPM responded by seeking a declaration that, in accordance with the proper construction of the agreement, CCS was bound to comply with the notices. The learned primary judge upheld CPM's construction of the agreement and declared that CCS was obliged to comply with the notice.
CCS appeals against the decision of the learned…
Keep reading for free
Create a free CaseChat account to read Callide Power Management P/L v Callide Coalfields (Sales) P/... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Find similar cases
Other decisions on the same topics. Each opens in a new tab.
Details
- Case
- [2008] QCA 182
- Decision Date
CaseChat Overview and Summary
The primary legal issue before the court was whether the respondent had the authority to amend the contractual obligations unilaterally, particularly in light of the appellant's failure to deliver coal due to force majeure. The court was required to interpret the contract to determine if there were provisions that allowed for such amendments and whether the respondent's actions were justified under the circumstances. The court had to consider the principles of contract construction and interpretation, focusing on the terms of the contract and the specific clauses that governed amendments and variations.
The court found that the contract did indeed allow for the respondent to amend the quantities of coal required for future deliveries. The relevant clause permitted adjustments in the event of certain contingencies, including the appellant's failure to deliver as agreed. The court held that the respondent's notice of amendment was valid and permissible under the contract. The appellant's argument that the force majeure events should exempt them from the contract's amendment clause was rejected. The court concluded that the contract terms were clear and that the respondent had the right to adjust future deliveries.
The appeal was dismissed, and the appellant was ordered to pay the respondent's costs of and incidental to the appeal, to be assessed on the standard basis.
Orders
Orders of the court
Appeal dismissed1.
Appellant to pay the respondent's costs of and incidental to the appeal to be assessed on the standard basis2.
Background
Background to the litigation
Decision
Reasons for decision
Ratio Decidendi