| IN THE COURT OF APPEAL OF NEW ZEALAND I TE KŌTI PĪRA O AOTEAROA |
| CA663/2021 [2023] NZCA 266 |
| BETWEEN | PHILIP JOHN WOOLLEY |
| AND | FONTERRA CO-OPERATIVE GROUP LIMITED |
| Hearing: | 8 and 9 November 2022 |
Court: | Brown, Goddard and Clifford JJ |
Counsel: | P A Morten and M A Robertson for Appellant |
Judgment: | 29 June 2023 at 10.30 am |
JUDGMENT OF THE COURT
AThe appellant’s application for leave to adduce further evidence is granted.
BThe appeal is dismissed.
CThe appellant must pay the respondent costs for a standard appeal on a band A basis plus usual disbursements. We certify for two counsel.
____________________________________________________________________
Table of Contents
Para No
Introduction [1]
The milk supply agreement [4]
Factual overview [8]
Events culminating in the Enforcement Order [9]
Fonterra’s decision to suspend milk collection [18]
Opus is retained [21]
Mr Woolley’s attempt at brinkmanship [22]
The Opus Certificate [26]
The suspension of milk collection is maintained [27]
The Environment Court’s ruling of 10 July 2015 (Ruling 3) [35]
The High Court judgment [38]
Issues on appeal [46]
Mr Woolley’s application to adduce further evidence [49]
Contractual preconditions to the exercise of Fonterra’s power
to suspend milk collection [50]
Was the sufficiency of the Certificate within the exclusive
jurisdiction of the Environment Court? [53]
Was Ruling 3 a judgment in rem? [58]
Did the Certificate satisfy the requirements of the
Enforcement Order? [70]
An implied term to act “reasonably” in the exercise of a
contractual discretion [86]
Absolute contractual rights/contractual discretions [86]
The pleadings [89]
The default rule [94]
An expanded default rule? [97]
Was the maintenance of the suspension of milk collection after
5 September 2014 a breach of an implied term? [103]
Was the default rule applicable here? [103]
Was Fonterra in breach of the default rule? [105]
Should the expanded default rule apply in this case? [112]
Result [116]
REASONS OF THE COURT
(Given by Brown J)
Introduction
The appellant, Mr Woolley, the owner and operator of a dairy farm known as Glenmae, entered into a milk supply agreement (MSA) with the respondent (Fonterra). An enforcement order issued by the Environment Court on 4 April 2014 on the application of the Marlborough District Council (MDC) ordered the cessation of the milking operation at Glenmae (the Enforcement Order). It prohibited the recommencement of milking until certification was provided by a registered engineer that the effluent disposal system at Glenmae was functioning properly in accordance with a resource consent.[1] Fonterra then exercised the power in the MSA to suspend milk collection.
[1]Marlborough District Council v Woolley [2014] NZEnvC 79 [Enforcement order].
Mr Woolley engaged Opus International Consultants Ltd (Opus) who provided a certification dated 5 September 2014 (the Certificate) by way of a response to the Enforcement Order. The MDC disputed the sufficiency of the Certificate. In those circumstances, and where there had not been a ruling of the Environment Court on the issue of compliance with the Enforcement Order,…
Keep reading for free
Create a free CaseChat account to read Woolley v Fonterra Co-operative Group Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2023] NZCA 266
- Decision Date
CaseChat Overview and Summary
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.