| IN THE COURT OF APPEAL OF NEW ZEALAND |
| CA150/2015 [2015] NZCA 313 |
| BETWEEN | VERMILLION WAGENER LIMITED, TREMONT HOLDINGS LIMITED, SAGE PROPERTY MANAGEMENT LIMITED AND TMT AMENITIES LIMITED |
| AND | BODY CORPORATE 401803 |
| Hearing: | 28 April 2015 |
Court: | Harrison, Keane and Wylie JJ |
Counsel: | T J Rainey and J P Wood for Appellants |
Judgment: | 21 July 2015 at 12.30 pm |
JUDGMENT OF THE COURT
AThe appeal is dismissed.
BThe appellants must pay the respondent costs for a standard appeal on a band A basis together with usual disbursements.
____________________________________________________________________
REASONS OF THE COURT
(Given by Harrison J)
Introduction
The appellants (collectively Vermillion) are the developer and related companies of a 106 unit title residential development in St Lukes, Auckland, known as the Tremont complex. The respondent, Body Corporate 401803, is the Body Corporate.
At issue on this appeal from a judgment of Muir J in the High Court[1] is the validity of agreements by the Body Corporate to guarantee and assume primary liability for all rental and other sums payable by third parties to Vermillion Wagener Ltd, and its related and successor company Tremont Holdings Ltd, as lessor of three units within the complex – one being a residential unit occupied by the complex manager, Sage Property Management Ltd (Sage) (the apartment lease); the other two units comprising a swimming pool, tennis courts, gymnasium and other amenities (the amenities lease).
[1]Body Corporate 401803 v Vermillion Wagener Ltd [2015] NZHC 285, (2015) 15 NZCPR 758.
In the period between June 2008 and June 2013 the Body Corporate paid Vermillion and Tremont about $1.32 million under the agreements but has since suspended payments pending the result of this litigation.
The Body Corporate applied for summary judgment on its claim that both guarantees, and a related guarantee obligation imposed by the management agreement with Sage, were void.[2] Muir J held that the Body Corporate had no power to guarantee the apartment lease in the absence of an express duty under the Unit Titles Act 1972 (the UTA 1972), which was then in force, or the amended rules, to secure accommodation for the building manager.[3] The Judge also held that the Body Corporate had no separate duty to provide the amenities and thus no power to guarantee the amenities lease.[4] As Vermillion had no arguable defence to the Body Corporate’s claim, summary judgment was entered. Vermillion now appeals.
[2]The Body Corporate had earlier defended a challenge to its resolutions requiring Tremont to contribute toward the legal costs of the summary judgment application by levies imposed on all unit owners including Tremont: Tremont Holdings Ltd v Body Corporate 401803 [2014] NZHC 988, (2014) 15 NZCPR 525. In a judgment delivered concurrently today (Tremont Holdings Ltd v Body Corporate 401803 [2015] NZCA 314), this Court has dismissed an appeal by Tremont.
[3]At [115] and [122].
[4]At [104] and [105].
The Body Corporate has not cross-appealed against Muir J’s dismissal of its application for…
Keep reading for free
Create a free CaseChat account to read Vermillion Wagener Ltd v Body Corporate 401803 and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2015] NZCA 313
- Decision Date
CaseChat Overview and Summary
The Court of Appeal had to decide whether the Body Corporate had the legal power to guarantee obligations assumed by third parties under two separate leases. The court examined the Body Corporate’s powers and duties under the Unit Titles Act 1972 and the rules to determine if it was reasonably necessary for the Body Corporate to enter into non-subrogated long-term obligations to pay rental and other charges due under the two leases.
The Court of Appeal found that the Body Corporate had no power to guarantee the apartment lease or the amenities lease. The court rejected Vermillion's arguments that the Body Corporate had express powers under the Unit Titles Act 1972, the rules, or derived powers under s 16 of the UTA 1972 to guarantee the manager’s lease obligations or the amenities lease. The court held that without an identifiable duty, the Body Corporate could not assume a primary obligation to pay rent or other charges. The Body Corporate’s guarantee of the apartment lease was void because there was no power or duty to secure accommodation for the building manager. The court also held that the Body Corporate’s guarantee of the amenities lease was void because the Body Corporate had no power to guarantee the amenities lease, and the amenities deed did not impose any duties relating to the provision of amenities.
The appeal was dismissed, and the appellants were ordered to pay the Body Corporate costs for a standard appeal on a band A basis together with usual disbursements.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi