Sui v Jiang

Link copied
Case Copied 54 min read

Supreme Court


New South Wales

Medium Neutral Citation: Sui v Jiang and Anor [2021] NSWSC 435
Hearing dates: 30 September 2020, 22 October 2020, 12 November 2020, 22 February 2021
Date of orders: 30 April 2021
Decision date: 30 April 2021
Jurisdiction:Common Law
Before: Johnson J
Decision:

1. Verdict for each of the First Defendant and the Second Defendant on the claim by the Plaintiff.

2. The Plaintiff’s claims against the First Defendant and the Second Defendant are dismissed.

3. In the absence of any written submissions (not exceeding three pages) from the parties on the question of costs being provided by email to Johnson J’s Associate by 4.00 pm on 7 May 2021, the Court will make an order in Chambers that the Plaintiff pay 50% of the costs of the proceedings of the First and Second Defendants calculated on the ordinary basis.

4. In the event that written submissions are made on the question of costs in accordance with paragraph 3 above, the Court will determine the question of costs on the papers.

Catchwords:

CONTRACT – claim for damages for breach of contract – written agreement in Mandarin Chinese prepared by non-lawyer (the Plaintiff) – whether terms of contract constituted loan agreement or shareholder investment agreement – proper construction of contract as a whole considered – claim dismissed

Legislation Cited:

Civil Procedure Act 2005

Cases Cited:

Bofinger v Kingways Group Limited (2009) 239 CLR 269; [2009] HCA 44

Codelfa Construction Pty Ltd v State Rail Authority of New South Wales (1982) 149 CLR 337; [1982] HCA 24

Ecosse Property Holdings Pty Ltd v Gee Dee Nominees Pty Ltd (2017) 261 CLR 544; [2017] HCA 12

Electricity Generation Corporation v Woodside Energy Ltd (2014) 251 CLR 640; [2014] HCA 7

Equuscorp Pty Ltd v Glengallen Investments Pty Ltd (2004) 218 CLR 471; [2004] HCA 5

Eureka Operations Pty Ltd v Viva Energy Australia Ltd [2016] VSCA 95

GL Nederland (Asia) Pty Ltd v Expertise Events Pty Ltd [1999] NSWCA 62

In the Matter of Jimmy’s Recipe Pty Ltd (No. 2) [2020] NSWSC 632

Leichhardt Municipal Council v Green [2004] NSWCA 341

Mount Bruce Mining Pty Limited v Wright Prospecting Pty Limited (2015) 256 CLR 104; [2015] HCA 37

Rosniak v Government Insurance Office (1997) 41 NSWLR 608

Ruthol Pty Ltd v Mills [2003] NSWCA 56

South Western Sydney Local Health District v Gould (2018) 97 NSWLR 513; [2018] NSWCA 69

Sunbird Plaza Pty Limited v Maloney (1988) 166 CLR 245; [1988] HCA 11

TAL Life Ltd v Shuetrim (2016) 91 NSWLR 439; [2016] NSWCA 68

Zhang v ROC Services (NSW) Pty Ltd (2016) 93 NSWLR 561; [2016] NSWCA 370

Texts Cited:

---

Category:Principal judgment
Parties: Guangyi Sui (Plaintiff)
Zhaoquing Jiang (First Defendant)
Australian Fulin Agriculture Pty Limited (Second Defendant)
Representation:

Counsel:
Mr MW Young SC (Plaintiff)
Dr E Peden SC; Mr B DeBuse (30 September 2020) (Defendants)
Mr B DeBuse (22 October 2020 and 12 November 2020) (Defendants)

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Sui v Jiang and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Find similar cases

Other decisions on the same topics. Each opens in a new tab.

Details

Case
[2021] NSWSC 435
Decision Date

CaseChat Overview and Summary

The matter of Sui v Jiang involved a dispute between the Plaintiff, who prepared a written agreement in Mandarin Chinese, and the Defendant. The Plaintiff sought damages for the alleged breach of the contract, which was intended to either constitute a loan agreement or a shareholder investment agreement. The nature of the contract was ambiguous due to the non-lawyer preparation of the agreement, and the primary issue before the court was to determine the proper construction of the contract as a whole.

The court was required to decide whether the written agreement was a loan agreement or a shareholder investment agreement, as the interpretation of the contract would significantly impact the rights and obligations of the parties. The court examined the language of the contract, the context in which it was prepared, and the intentions of the parties. The court also considered the principles of contractual interpretation, which include the need to give effect to the intentions of the parties and to construe the contract as a whole. After careful analysis of the evidence and arguments presented, the court determined that the contract was not a shareholder investment agreement but rather a loan agreement.

The court's reasoning was based on the language of the contract and the surrounding circumstances. The court found that the language used in the contract was consistent with a loan agreement, and the context in which the contract was prepared supported this interpretation. The court also considered the parties' intentions and the principles of contractual interpretation, which led to the conclusion that the contract was a loan agreement. As a result, the Plaintiff's claim for damages was dismissed. The court held that the contract did not constitute a shareholder investment agreement, and therefore, the Plaintiff was not entitled to the damages sought.

Background

Background to the litigation

Decision

Reasons for decision

Ratio Decidendi

Legal principle established