FEDERAL COURT OF AUSTRALIA
State of Queensland v Telecommunications Industry Ombudsman [2022] FCAFC 158
Appeal from: State of Queensland v Telecommunications Industry Ombudsman [2021] FCA 522 File number: QUD 167 of 2021 Judgment of: BESANKO, MIDDLETON AND RANGIAH JJ Date of judgment: 16 September 2022 Catchwords: COMMUNICATIONS LAW – Telecommunications Act 1997 (Cth) Sch 3 cl 7 – meaning of “maintenance” as part of power to “maintain a facility” – whether maintenance includes the installation of a new fibre optic cable in a conduit or duct owned by a third party with whom access agreement entered – where consent of landowner required absent authorisation to install or maintain facility under the Act – held: installation of proposed facility not within power to maintain – appeal allowed
COMMUNICATIONS LAW – Telecommunications Act 1997 (Cth) Sch 3 cl 11 – Telecommunications Code of Practice 2018 (Cth) s 6.29(e) – whether failure to make reasonable efforts to enter into an agreement with the State could be a basis for objecting to the proposed activities
COMMUNICATIONS LAW – Telecommunications Code of Practice 2018 (Cth) s 6.29(b) – whether onus is on an objector to show an alternative location for a proposed activity
Legislation: Acts Interpretation Act 1901 (Cth) s 15AA
Competitionand Consumer Act2010 (Cth) Pt XIB and Pt XIC ss 152AB(2), 152AL, 152AR(3)(a) and 152AXB(2)
Telecommunications Act 1997 (Cth) ss 7, 3(1), 3(2), 42(1), 56, 61 and 484; Schs 1 and 3; cll 2, 5, 6, 7(1), 7(3), 11, 17(1), 17(2), 17(3), 17(4), 17(5), 18, 18(1), 18(5), 19(1), 26(2), 33(1), 34, 35, 36, 37(1), 38 and 47; Divs 2, 3 and 4
Telecommunications Code of Practice 2018 (Cth) ss 6.22, 6.29, 6.35 and 6.36(1)
Telecommunications (Low-impact Facilities) Determination 2018 (Cth)
Cases cited: Anthony Hordern & Sons Ltd v Amalgamated Clothing & Allied Trades Union of Australia (1932) 47 CLR 1
Bayside City Council v Telstra Corp Ltd (2004) 216 CLR 595
Coco v The Queen (1994) 179 CLR 427
Electrolux Home Products Pty Ltd v Australian Workers’ Union (2004) 221 CLR 309
Freedom Foods Pty Ltd v Blue Diamond Growers [2021] FCAFC 86; (2021) 286 FCR 437
Hurstville City Council v Hutchison 3G Australia Pty Ltd [2003] NSWCA 179; 200 ALR 308
Lee v New South Wales Crime Commission (2013) 251 CLR 196
Minister for Immigration and Multicultural and Indigenous Affairs v Nystrom (2006) 228 CLR 566
Minister for Immigration and Border Protection v WZAPN (2015) 254 CLR 610
Momcilovic v The Queen (2011) 245 CLR 1
NBN Co Ltd v Pipe Networks Pty Ltd [2015] NSWSC 475; (2015) 295 FLR 256
R v Independent Broad-Based Anti-Corruption Commissioner (2016) 256 CLR 459
State of Queensland v Telecommunications Industry Ombudsman [2021] FCA 522
SZTAL v Minister for Immigration and Border Protection (2017) 262 CLR 362
Telstra Corporation Ltd v Hurstville City Council (2002) 118 FCR 198
Telstra Corporation Ltd v State of Queensland [2016] FCA 1213
Division: General Division Registry: Queensland National Practice Area: Administrative and Constitutional Law and Human…
Keep reading for free
Create a free CaseChat account to read State of Queensland v Telecommunications Industry Ombudsman and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2022] FCAFC 158
- Decision Date
CaseChat Overview and Summary
Orders
Orders of the court
1. Within fourteen (14) days the parties file an agreed form of orders, or in default of agreement, any submissions as to the form of the appropriate orders reflecting the reasons of the Court.
2. Subject to any further directions, the final orders of the Court will be made on the papers.
Note: Entry of orders is dealt with in Rule 39.32 of the Federal Court Rules 2011.
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi
Legal Principle Established
The State relies upon the following grounds of appeal:1.The Primary Judge erred in construing clause 7 of Schedule 3 of the Telecommunications Act 1997 (Cth) in deciding that the term ‘maintenance’ extends to the installation of fibre optic cable by one carrier in or through a telecommunications ‘facility’ of a different carrier over the Appellant’s Kidd Bridge and without the Appellant’s consent or approval.2.The Primary Judge erred in construing clause 11 of Schedule 3 of the Telecommunications Act, and s 6.29 of the Telecommunications Code of Practice 2018, in finding that a failure of a carrier to make reasonable efforts to enter into an agreement with a ‘public utility’ for the manner in which ‘maintenance’ work would be carried out by a carrier is not a ground of objection to the Telecommunications Industry Ombudsman.3.The Primary Judge erred in finding that the statutory scheme places upon an objector the onus of identifying an alternative location for the work of a proponent carrier.ConsiderationGround 1: Whether cl 7 of Sch 3 of the Act extends to allowing a carrier to install an additional facility in the same location as an original facility installed by another carrier Clause 7(1) of Sch 3 of the Act authorises a carrier to, “at any time, maintain a facility”. Clause 7(3)(e) defines “maintenance” to include, “the installation of an additional facility in the same location as the original facility”. As an original facility will generally be located on land not owned by a carrier, cl 7(2) permits a carrier to do “anything necessary or desirable” for the purpose of maintaining a facility, including entering on, and occupying, land. The first ground of appeal challenges the primary judge’s rejection of the State’s argument that cl 7 does not provide Optus with authority to install fibre optic cable within the conduit installed by NBN Co on the Kidd Bridge without having obtained either a facility installation permit under cl 6 or the consent of the State. The ground asserts that the primary judge erred in construing cl 7 of Sch 3 such that the term “maintenance” extends to the installation of fibre optic cable by a carrier in or through a facility of another carrier without the consent of the owner of the land on which the facility is located. The issue is whether cl 7(1) and cl 7(3)(e) authorise a carrier to “maintain” a facility it does not own, including by installing an additional facility in the same location as an original facility installed and owned by another carrier. Before turning to consider the parties’ submissions, it is necessary to provide an overview of the scheme of the Act and its terminology.Overview of the Act and terminology The Act regulates the provision of telecommunications in Australia by “carriers” and “service providers”. In Bayside City Council v Telstra Corp Ltd (2004) 216 CLR 595, Gleeson CJ, Gummow, Kirby, Hayne and Heydon JJ observed at [7] that the regulatory framework is intended to:promote the development of an efficient and competitive telecommunications industry, including the supply of carriage services to the public, and to ensure that such services are reasonably accessible, and are supplied efficiently and economically to meet the social and business needs of the Australian community.