Spry Civil Construction Pty Ltd v Aussie-Drain Pty Ltd; Aussie-Drain Pty Ltd v Spry Civil Construction Pty Ltd

Link copied
Case Copied 57 min read

SUPREME COURT OF SOUTH AUSTRALIA

(Magistrates Appeal: Civil)

SPRY CIVIL CONSTRUCTION PTY LTD v AUSSIE-DRAIN PTY LTD; AUSSIE-DRAIN PTY LTD v SPRY CIVIL CONSTRUCTION PTY LTD

[2025] SASC 99

Judgment of the Honourable Justice B Doyle 

20 June 2025

CONTRACTS - BUILDING, ENGINEERING AND RELATED CONTRACTS - PERFORMANCE OF WORK - REMEDIES FOR BREACH OF CONTRACT

MAGISTRATES - APPEAL AND REVIEW - SOUTH AUSTRALIA - APPEAL TO SUPREME COURT

The respondent and cross-appellant (‘Aussie-Drain’) agreed by a contract entered into with the appellant and cross-respondent (‘Spry’) to carry out sub-surface drainage works at the Murray Bridge Racecourse.  The contract was for a lump sum but included a clause that if rock was encountered, prices ‘need to be reviewed’.

After carrying out about 37% of the required work, Aussie-Drain encountered rock.  In order to complete the works, a rock saw was required and a different and more labour-intensive work method was called for.  In the course of discussions, Aussie-Drain’s principal asserted that it was ‘not my job anymore’.  Although one of Aussie-Drain’s workers remained on site, the other workers left and returned to Victoria. 

A magistrate found that Aussie-Drain repudiated the contract.  With reference to the rule in Sumpter v Hedges [1898] 1 QB 673, Aussie-Drain’s claim for a restitutionary award in respect of the work it had carried out failed, save that the magistrate recognised an exception for the cost of the materials it had supplied. The magistrate also made an award in Aussie-Drain’s favour for work carried out (and materials supplied by it that were used in such work) after its repudiation of the contract.

On appeal, Spry contends that the magistrate erred by finding that Aussie-Drain was entitled to recover in respect of the materials supplied by it in partially completing the works prior to repudiating the contract.  Additionally, Spry contends that in respect of the subsequent work, the magistrate erred by including in the award a component reflecting GST. 

By its cross-appeal, Aussie-Drain contends that:

1.when rock was encountered, the contract was automatically terminated, and the magistrate therefore erred by finding that Aussie-Drain repudiated the contract;

2.consequently, and in any event, it was entitled to recover on a quantum meruit basis for the work done and materials supplied by it before rock was encountered because the benefit of that work was freely accepted by Spry.

Held, allowing the appeal in part and dismissing the cross-appeal:

1.      the contract was not automatically terminated when Aussie-Drain struck rock;

2.      the magistrate did not err by finding that Aussie-Drain repudiated the contract;

3.in accordance with the rule in Sumpter v Hedges, Aussie-Drain was precluded from recovering both for the work done and the materials supplied or installed on site prior to its repudiation of the contract;

4.the magistrate did not err by including a component reflecting GST in the award made for work carried out and materials supplied after Aussie-Drain’s repudiation of the contract.

A New Tax System (Goods and Services Tax) Act 1999 (Cth) s 9-5, Public…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Spry Civil Construction Pty Ltd v Aussie-Drain Pty Ltd; Auss... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2025] SASC 99
Decision Date

CaseChat Overview and Summary

Spry Civil Construction Pty Ltd and Aussie-Drain Pty Ltd are the parties in this case. The dispute between them concerns the performance of a construction contract for the installation of sub-soil drainage at the Murray Bridge Racecourse. The case was initially heard in the South Australian Magistrates Court, but an appeal has been brought to the Supreme Court of South Australia. The primary issues the court had to decide were whether Aussie-Drain was entitled to recover for all work performed before a specified date and whether there was a distinction in the provision of labour and materials prior to that date.

The court examined the contract terms and the scope of work agreed upon between the parties. The court found that the contract was clear in its stipulations and that Aussie-Drain had agreed to a fixed lump sum price for the installation of drainage piping, including both the supply and installation of materials. The court also considered the timelines and the impact of any delays or variations on the contract. Given that Aussie-Drain did not succeed in its argument that it should recover for all work performed before 8 October 2021, the court did not need to address the distinction between the provision of labour and materials prior to that date. The court found that Aussie-Drain’s claim for additional work beyond the scope of the original contract was not justified.

The Supreme Court allowed Spry’s appeal and reduced the award to Spry Civil Construction Pty Ltd on the basis sought. The court’s decision was based on the clear terms of the contract and the failure of Aussie-Drain to substantiate its claims for additional work and variations. The final orders of the court reflected the court's findings and resulted in a reduction of the award to Spry Civil Construction Pty Ltd, aligning with the outcome sought by Spry.

Orders

Orders of the court

Background

Background to the litigation

If these two issues are resolved adversely to Aussie-Drain, it accepts that Spry’s appeal should be allowed and the award reduced on the basis sought by Spry. That is to say, if it does not succeed in its contention that it should recover for all the work it carried out before 8 October 2021, Aussie-Drain does not seek to support the distinction made by the magistrate between the provision of labour and the provision of materials prior to that date. The salient facts Neither party challenges any of the magistrate’s findings as to the basal or background facts. So far as is relevant to the issues for resolution, the facts as found are summarised below. The Murray Bridge Racing Club engaged Spry to construct an inner turf track at the Murray Bridge Racecourse in 2021.[14] [14] Reasons [9]. The inner turf track was to be situated within the course proper. To ensure the integrity of the inner turf track, it was necessary to create a system of sub-soil drainage. That involved digging narrow trenches, five metres apart, running from the outer edge to the inner edge of the inner turf track. The trenches were to slope towards the centre of the racecourse. A length of agricultural pipe was then to be placed in each of the trenches, with holes pierced into the pipe to allow for drainage of moisture into the pipes. The pipes were to be capped on the outer (top) end and fed into a collection pipe on the inside end. The collection pipe finished with a collection drain, to allow for the overall removal of moisture from the inner turf track.[15][15] Reasons [9]. Aussie-Drain was engaged for the ‘Stormwater and Subsoil Drainage’ portion of the project. Spry’s Mr Rasheed contacted Aussie-Drain’s Mr Boersma and invited him to provide a quote for the works.[16][16] Reasons [10]-[11]. The request for a quote was by email and specified in outline the work to be done, including by attaching plans and specifications. The work involved the installation of 8,225 metres of drainage piping and the supply of that piping (but not the collector pipes). The email asked Aussie-Drain to provide ‘details within your submission of any inclusions and/or exclusions that you have allowed within your pricing’. It stated that ‘[y]our price must be a fixed lump sum with a SOR for variations’.[17][17] Reasons [12]. Mr Boersma’s email of 26 July 2021 in response attached a quotation in these terms:[18][18] Reasons [14].SamThank you for the opportunity to quote for the Drainage at the Inner Turf Track.8225 m 65 mm AG drains + Sand @ $15.50 = $127,487.5010% GST $ 12,748.75Total $140,236.25The price includes Installation and supply of all materials, including flushing caps. Disposal of spoil stockpiled on site.If rock is encountered or digging under utilities is required prices need to be reviewed.RegardsBill Mr Rasheed spoke with Mr Boersma by telephone on 2 August 2021 and accepted the quotation by email dated 2 August 2021.[19] [19] Reasons [15]. The Reasons state that the telephone discussion occurred on 2 September 2021. The parties to the appeal agree this is a slip.

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established