JURISDICTION : SUPREME COURT OF WESTERN AUSTRALIA
IN CHAMBERS
CITATION: RALMANA PTY LTD -v- BGC CONTRACTING PTY LTD [No 2] [2017] WASC 373
CORAM: KENNETH MARTIN J
HEARD: 10 NOVEMBER 2017
DELIVERED : 20 DECEMBER 2017
FILE NO/S: CIV 1156 of 2015
CIV 2434 of 2015
Consolidated by Orders dated 24 September 2015
BETWEEN: RALMANA PTY LTD
Plaintiff
AND
BGC CONTRACTING PTY LTD
First DefendantJOHN BEATTIE
Second Defendant
Catchwords:
Practice and procedure - Pleadings - Project development - Earthworks - Strikeout applications by defendant - Case management of large construction dispute - Fundamental problems - Turns on own facts
Legislation:
Nil
Result:
Strikeout orders issued
Category: B
Representation:
Counsel:
Plaintiff: Mr G R Ritter QC & Mr C B Sullivan
First Defendant : Mr M G Lundberg & Ms D J Osborn
Second Defendant : Mr M G Lundberg & Ms D J Osborn
Solicitors:
Plaintiff: HopgoodGanim
First Defendant : King & Wood Mallesons
Second Defendant : King & Wood Mallesons
Case(s) referred to in judgment(s):
Andrews v Australia and New Zealand Banking Group Ltd [2012] HCA 30; (2012) 247 CLR 205
Bell Group Ltd (in liq) v Westpac Banking Corp [No 9] [2008] WASC 239; (2008) 39 WAR 1
Codelfa Construction Pty Ltd v State Rail Authority of New South Wales [1982] HCA 24; (1982) 149 CLR 337
Hoyt's Pty Ltd v Spencer [1919] HCA 64; (1919) 27 CLR 133
Hughes v St Barbara Mines Ltd [No 4] [2010] WASC 160
Paciocco v Australia and New Zealand Banking Group Ltd [2016] HCA 28; (2016) 258 CLR 525
Ralmana Pty Ltd v BGC Contracting Pty Ltd [2016] WASC 131
Secured Income Real Estate (Australia) Ltd v St Martins Investments Pty Ltd [1979] HCA 51; (1979) 144 CLR 596
Spiers Earthworks Pty Ltd v Landtec Projects Corporation Pty Ltd [No 2] [2012] WASCA 53; (2012) 287 ALR 360
Waltons Stores (Interstate) Ltd v Maher [1988] HCA 7; (1988) 164 CLR 387
KENNETH MARTIN J:
Introduction
I am dealing with three distinct interlocutory applications concerning pleadings and amendment issues in this action.
Two of the applications are advanced by the defendants, BGC Contracting Pty Ltd (BGC) and Mr John Beattie, under amended chamber summonses of 6 November 2017 (both amended by leave under my orders of 24 October 2017).
The first chamber summons is brought by the defendants collectively. By their chamber summons, the defendants challenge multiple paragraphs of the plaintiff's, Ralmana Pty Ltd (RJV), fourth further substituted amended statement of claim filed 1 November 2017, which is the current substituted statement of claim (CSSOC).
The second chamber summons is brought by BGC only, dated 6 November 2017. This chamber summons seeks to strike out various paragraphs of RJV's Reply pleading to the defendants' defence and amended defence to counterclaim, filed 1 November 2017 (amended defence to counterclaim).
The two chamber summonses challenge paragraphs within the CSSOC and amended defence to counterclaim by invoking all subparagraphs of O 20 r 19(1) of…
Keep reading for free
Create a free CaseChat account to read Ralmana Pty Ltd v BGC Contracting Pty Ltd [No 2] and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Find similar cases
Other decisions on the same topics. Each opens in a new tab.
Details
- Case
- [2017] WASC 373
- Decision Date
CaseChat Overview and Summary
The court examined the 'prevention principle' as discussed in the case of Spiers Earthworks Pty Ltd v Landtec Projects Corporation Pty Ltd [No 2]. It noted that while the principle may offer potential relief, the current pleadings by Ralmana did not meet the minimum threshold required to invoke it. The court highlighted that the pleadings under paragraph 30(c) of Ralmana's amended defence to counterclaim were fundamentally deficient and did not provide a rational basis for applying the prevention principle. The deficiencies extended to other parts of the defence, such as the claims under the Cumulative Accommodation Cap, Cumulative Flight Cap, and the Maximum Fuel Cap. Consequently, the court determined that these parts of the defence should be struck out as they failed to disclose any arguable defence.
In its judgment, the court agreed with BGC that Ralmana should be required to produce a proposed minute of a further amended defence to counterclaim before any leave to amend could be granted. This minute would need to address the deficiencies identified and potentially support the invocation of the prevention principle. The court ordered that the pleadings under paragraphs 30(b), 30(c), 36(b), 41(b), and 46(b) of Ralmana's amended defence to counterclaim be struck out. The parties were directed to confer and agree on a reasonable time frame for Ralmana to submit a proposed minute of the amended defence to counterclaim, which would then be evaluated for the grant of leave to amend.
Background
Background to the litigation
Decision
Reasons for decision
Ratio Decidendi
Legal principle established
An explanation of the 'prevention principle' may be found in the observations of McLure P in Spiers Earthworks Pty Ltd v Landtec Projects Corporation Pty Ltd [No 2] [2012] WASCA 53; (2012) 287 ALR 360 particularly at [42], [47], [48] and [49]. I note her Honour's analysis of the somewhat conflicting Australian case authority as regards consequences of a principal relying on the failure to comply with notice requirements between [53] and [57]. Whatever might be said about the theoretical potential availability to RJV of the so called prevention principle, it is very plain that what is currently seen pleaded under par 30(c) of RJV's amended defence to counterclaim (and in the ensuing subsequent counterparts of that plea) does not yet even approach a minimum threshold of even arguably invoking the prevention principle or then, and more importantly, providing a rational base of factually pleaded circumstances to support its potential application to this action. In the end, that deficiency was necessarily accepted by senior counsel for RJV by recognising the problem and seeking leave to amend par 30(c). BGC, under its challenges against this plea (see pars 64 ‑ 69 of the defendants' consolidated submissions) drew attention to multiple asserted deficiencies - including in the subsequent counterpart pleas in the defence to counterclaim as regards fees payable under the Cumulative Accommodation Cap, Cumulative Flight Cap and the Maximum Fuel Cap. Given the manifest inadequacy of the current par 30(c) pleading, it is not presently possible, or productive, to try and conduct an evaluation of RJV's as suggested future conceptual invocation of the prevention principle against BGC's counterclaims for liquidated damages. In all the circumstances, the present plea under par 30(c) will be struck out as failing to disclose any arguable defence. BGC suggested, and I must agree, that RJV should be required, as the price of obtaining leave to amend as regards raising the prevention principle, to produce and circulate a proposed minute of further amended defence to counterclaim. The minute might then be evaluated under the conferral process from a perspective of determining whether any further attempts by RJV to invoke the so called prevention principle can legitimately support a grant of leave to amend the defence to counterclaim to raise such a plea. Given the wholly barren state of the pleading to date as regards underlying facts relied upon to support an application of the prevention principle ‑ it is appropriate that RJV proceed on this basis by producing a minute of amended defence and counterclaim as a precursor to any grant of leave to amend in that respect. Consequently, BGC has at the end succeeded in respect of all the relief it sought in respect of its amended chamber summons by striking out pars 30(b), 30(c), 36(b), 41(b) and 46(b) of RJV's amended defence to counterclaim. The parties can resolve by conferral a reasonable amount of time for RJV to bring in a proposed minute of further amended defence to counterclaim to address identified deficiencies to the current par 30(c) and its subsequent counterparts. That minute may then be further considered from the perspective of a grant of leave in future.