Ralmana Pty Ltd v BGC Contracting Pty Ltd

Link copied
Case Copied 42 min read

RALMANA PTY LTD -v- BGC CONTRACTING PTY LTD [2016] WASC 131



SUPREME COURT OF WESTERN AUSTRALIACitation No:[2016] WASC 131
Case No:CIV:1156/201523 FEBRUARY 2016
Coram:KENNETH MARTIN J28/04/16
27Judgment Part:1 of 1
Result: Parts of statement of claim struck out
B
PDF Version
Parties:RALMANA PTY LTD
BGC CONTRACTING PTY LTD

Catchwords:

Practice and procedure
Strike out application
Construction contract
Subcontract
Statement of claim
Liquidated claims
Extensions of time to be applied for and granted by Head Contractor's Representative
Delay costs claim based on grant of extension of time by Head Contractor's Representative
No plea as to extension of time being applied for or granted
Contended reliance on Rules of the Supreme Court 1971 (WA) O 20 r 8(4) to the effect that unnecessary to plead conditions precedent
No plea of material facts as to extension of time being refused by Head Contractor's Representative
Assumption Court may allow an extension of time de novo on a delay costs claim
Pleading defective and core components struck out

Legislation:

Nil

Case References:

Australian Development Corporation Pty Ltd v White Constructions (ACT) Pty Ltd (1996) 12 BCL 317
Baese Pty Ltd v RA Bracken Building Pty Ltd (1990) 6 BCL 137
Bahr v Nicolay (No 2) [1988] HCA 16; (1988) 164 CLR 604
Barclay Mowlem Construction Ltd v Dampier Port Authority [2006] WASC 281; (2006) 33 WAR 82
Body Corporate Strata Plan Number 4303 v Albion Insurance Co Ltd [1982] VR 699
Day v William Hill (Park Lane) Ltd [1949] 1 KB 632
Decor Ceilings Pty Ltd v Cox Constructions Pty Ltd (No 2) [2005] SASC 483; (2007) 23 BCL 347
Jennings Construction Ltd v QH & M Birt Pty Ltd (1986) 8 NSWLR 18
Leighton Contractors Pty Ltd v South Australian Superannuation Fund Investment Trust (1995) 12 BCL 38
Opat Decorating Service (Aust) Pty Ltd v Hansen Yuncken (SA) Pty Ltd (1994) 11 BCL 360
WMC Resources Ltd v Leighton Contractors Pty Ltd [1999] WASCA 10; (1999) 20 WAR 489
Zuk v Miller [1957] SASR 25


JURISDICTION : SUPREME COURT OF WESTERN AUSTRALIA
    IN CHAMBERS
CITATION : RALMANA PTY LTD -v- BGC CONTRACTING PTY LTD [2016] WASC 131 CORAM : KENNETH MARTIN J HEARD : 23 FEBRUARY 2016 DELIVERED : 28 APRIL 2016 FILE NO/S : CIV 1156 of 2015 BETWEEN : RALMANA PTY LTD
    Plaintiff

    AND

    BGC CONTRACTING PTY LTD
    Defendant

Catchwords:

Practice and procedure - Strike out application - Construction contract - Subcontract - Statement of claim - Liquidated claims - Extensions of time to be applied for and granted by Head Contractor's Representative - Delay costs claim based on grant of extension of time by Head Contractor's Representative - No plea as to extension of time being applied for or granted - Contended reliance on Rules of the Supreme Court 1971 (WA) O 20 r 8(4) to the effect that unnecessary to plead conditions precedent - No plea of material facts as…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Ralmana Pty Ltd v BGC Contracting Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details

Case
[2016] WASC 131
Decision Date

CaseChat Overview and Summary

In the case of Ralmana Pty Ltd v BGC Contracting Pty Ltd, the dispute involved a claim related to a construction contract and a subcontract. The plaintiff, Ralmana, sought damages from the defendant, BGC Contracting, for alleged breaches of the subcontract. The matter was heard in the Supreme Court of Western Australia. The plaintiff's statement of claim included a delay costs claim, which was based on the assertion that an extension of time had been granted by the Head Contractor's Representative. However, the plaintiff did not plead that the extension of time was applied for or granted, nor did they plead material facts as to the Head Contractor's Representative refusing to grant the extension of time.

The central legal issue before the court was whether the plaintiff's statement of claim was sufficient in light of the procedural requirements under the Rules of the Supreme Court 1971 (WA). Specifically, the court needed to determine whether the plaintiff's reliance on Rule 18(4) of those rules, which suggests that conditions precedent need not be pleaded, was appropriate in this context. The court also had to consider whether the plaintiff's omission to plead the necessary facts regarding the extension of time rendered the statement of claim defective.

The court found that the plaintiff's statement of claim was defective because it did not include the necessary details about the application for and grant of an extension of time by the Head Contractor's Representative. The court noted that the plaintiff had not made a plea that the extension of time was applied for or granted, nor had they pleaded the material facts concerning the refusal of the extension of time. Additionally, the court did not accept the plaintiff's assumption that it could grant an extension of time de novo on a delay costs claim. As a result, the court struck out certain parts of the statement of claim.

Orders

Orders of the court

Parts of statement of claim struck out

Background

Background to the litigation

Decision

Reasons for decision

Ratio Decidendi

Legal principle established