RALMANA PTY LTD -v- BGC CONTRACTING PTY LTD [2016] WASC 131
| SUPREME COURT OF WESTERN AUSTRALIA | Citation No: | [2016] WASC 131 | |
| Case No: | CIV:1156/2015 | 23 FEBRUARY 2016 | |
| Coram: | KENNETH MARTIN J | 28/04/16 | |
| 27 | Judgment Part: | 1 of 1 | |
| Result: | Parts of statement of claim struck out | ||
| B | |||
| PDF Version |
| Parties: | RALMANA PTY LTD BGC CONTRACTING PTY LTD |
Catchwords: | Practice and procedure Strike out application Construction contract Subcontract Statement of claim Liquidated claims Extensions of time to be applied for and granted by Head Contractor's Representative Delay costs claim based on grant of extension of time by Head Contractor's Representative No plea as to extension of time being applied for or granted Contended reliance on Rules of the Supreme Court 1971 (WA) O 20 r 8(4) to the effect that unnecessary to plead conditions precedent No plea of material facts as to extension of time being refused by Head Contractor's Representative Assumption Court may allow an extension of time de novo on a delay costs claim Pleading defective and core components struck out |
Legislation: | Nil |
Case References: | Australian Development Corporation Pty Ltd v White Constructions (ACT) Pty Ltd (1996) 12 BCL 317 Baese Pty Ltd v RA Bracken Building Pty Ltd (1990) 6 BCL 137 Bahr v Nicolay (No 2) [1988] HCA 16; (1988) 164 CLR 604 Barclay Mowlem Construction Ltd v Dampier Port Authority [2006] WASC 281; (2006) 33 WAR 82 Body Corporate Strata Plan Number 4303 v Albion Insurance Co Ltd [1982] VR 699 Day v William Hill (Park Lane) Ltd [1949] 1 KB 632 Decor Ceilings Pty Ltd v Cox Constructions Pty Ltd (No 2) [2005] SASC 483; (2007) 23 BCL 347 Jennings Construction Ltd v QH & M Birt Pty Ltd (1986) 8 NSWLR 18 Leighton Contractors Pty Ltd v South Australian Superannuation Fund Investment Trust (1995) 12 BCL 38 Opat Decorating Service (Aust) Pty Ltd v Hansen Yuncken (SA) Pty Ltd (1994) 11 BCL 360 WMC Resources Ltd v Leighton Contractors Pty Ltd [1999] WASCA 10; (1999) 20 WAR 489 Zuk v Miller [1957] SASR 25 |
JURISDICTION : SUPREME COURT OF WESTERN AUSTRALIA
- IN CHAMBERS
- Plaintiff
AND
BGC CONTRACTING PTY LTD
Defendant
Catchwords:
Practice and procedure - Strike out application - Construction contract - Subcontract - Statement of claim - Liquidated claims - Extensions of time to be applied for and granted by Head Contractor's Representative - Delay costs claim based on grant of extension of time by Head Contractor's Representative - No plea as to extension of time being applied for or granted - Contended reliance on Rules of the Supreme Court 1971 (WA) O 20 r 8(4) to the effect that unnecessary to plead conditions precedent - No plea of material facts as…
Keep reading for free
Create a free CaseChat account to read Ralmana Pty Ltd v BGC Contracting Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Find similar cases
Other decisions on the same topics. Each opens in a new tab.
Details
- Case
- [2016] WASC 131
- Decision Date
CaseChat Overview and Summary
The central legal issue before the court was whether the plaintiff's statement of claim was sufficient in light of the procedural requirements under the Rules of the Supreme Court 1971 (WA). Specifically, the court needed to determine whether the plaintiff's reliance on Rule 18(4) of those rules, which suggests that conditions precedent need not be pleaded, was appropriate in this context. The court also had to consider whether the plaintiff's omission to plead the necessary facts regarding the extension of time rendered the statement of claim defective.
The court found that the plaintiff's statement of claim was defective because it did not include the necessary details about the application for and grant of an extension of time by the Head Contractor's Representative. The court noted that the plaintiff had not made a plea that the extension of time was applied for or granted, nor had they pleaded the material facts concerning the refusal of the extension of time. Additionally, the court did not accept the plaintiff's assumption that it could grant an extension of time de novo on a delay costs claim. As a result, the court struck out certain parts of the statement of claim.
Orders
Orders of the court
Parts of statement of claim struck out
Background
Background to the litigation
Decision
Reasons for decision
Ratio Decidendi