Monadelphous KT Pty Ltd v DDG Fortescue River Pty Ltd

Link copied
Case Copied 36 min read

MONADELPHOUS KT PTY LTD -v- DDG FORTESCUE RIVER PTY LTD [2016] WASC 224



SUPREME COURT OF WESTERN AUSTRALIACitation No:[2016] WASC 224
Case No:CIV:1387/201613 JUNE 2016
Coram:KENNETH MARTIN J26/07/16
34Judgment Part:1 of 1
Result: Judgment for the applicant/third defendant
B
PDF Version
Parties:MONADELPHOUS KT PTY LTD
DDG FORTESCUE RIVER PTY LTD
TEC PILBARA PTY LTD
TRANSALTA ENERGY (AUSTRALIA) PTY LTD

Catchwords:

Contract
Construction
Deed of Guarantee
Expiry of force of guarantee
Duration ended at making of last milestone payment on practical completion
Unresolved extra payment claims not notified to Guarantor in time

Legislation:

Nil

Case References:

Austman Pty Ltd v Mount Gibson Mining Ltd [2012] WASC 202
Fancourt v Mercantile Credits Ltd [1983] HCA 25; (1983) 154 CLR 87
FPM Constructions Pty Ltd v Council of the City of Blue Mountains [2005] NSWCA 340
General Steel Industries Inc v Commissioner for Railways (NSW) [1964] HCA 69; (1964) 112 CLR 125
McDonald v Dennys Lascelles Ltd (1933) 48 CLR 457
Mount Bruce Mining Pty Ltd v Wright Prospecting Pty Ltd [2015] HCA 37; (2015) 325 ALR 188
Ralmana Pty Ltd v BGC Contracting Pty Ltd [2016] WASC 131
Webster v Lampard [1993] HCA 57; (1993) 177 CLR 598


JURISDICTION : SUPREME COURT OF WESTERN AUSTRALIA
    IN CHAMBERS
CITATION : MONADELPHOUS KT PTY LTD -v- DDG FORTESCUE RIVER PTY LTD [2016] WASC 224 CORAM : KENNETH MARTIN J HEARD : 13 JUNE 2016 DELIVERED : 26 JULY 2016 FILE NO/S : CIV 1387 of 2016 BETWEEN : MONADELPHOUS KT PTY LTD
    Plaintiff

    AND

    DDG FORTESCUE RIVER PTY LTD
    First Defendant

    TEC PILBARA PTY LTD
    Second Defendant

    TRANSALTA ENERGY (AUSTRALIA) PTY LTD
    Third Defendant

Catchwords:

Contract - Construction - Deed of Guarantee - Expiry of force of guarantee - Duration ended at making of last milestone payment on practical completion - Unresolved extra payment claims not notified to Guarantor in time

Legislation:

Nil

Result:

Judgment for the applicant/third defendant


Category: B


Representation:

Counsel:


    Plaintiff : Mr S K Dharmananda SC & Mr B A Millar
    First Defendant : No appearance
    Second Defendant : No appearance
    Third Defendant : Mr J A Thomson SC

Solicitors:

    Plaintiff : Jones Day
    First Defendant : No appearance
    Second Defendant : No appearance
    Third Defendant : Squire Patton Boggs



Case(s) referred to in judgment(s):

Austman Pty Ltd v Mount Gibson Mining Ltd [2012] WASC 202
Fancourt v Mercantile Credits Ltd [1983] HCA 25; (1983) 154 CLR 87
FPM Constructions Pty Ltd v Council of the City of Blue Mountains [2005] NSWCA 340
General Steel Industries Inc v Commissioner for Railways (NSW) [1964] HCA 69; (1964) 112 CLR 125
McDonald v Dennys Lascelles Ltd (1933) 48 CLR 457
Mount Bruce Mining Pty Ltd v Wright Prospecting Pty Ltd [2015] HCA 37; (2015) 325 ALR 188
Ralmana Pty Ltd v BGC Contracting Pty Ltd [2016] WASC 131
Webster v Lampard [1993] HCA 57; (1993) 177 CLR 598
CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Monadelphous KT Pty Ltd v DDG Fortescue River Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2016] WASC 224
Decision Date

CaseChat Overview and Summary

The case involved Monadelphous KT Pty Ltd, the applicant and third defendant, and DDG Fortescue River Pty Ltd, the respondent and second defendant. The dispute centred around the terms of a Deed of Guarantee and its applicability to certain unresolved payment claims. The Federal Court of Australia was tasked with determining the validity of the guarantee in light of the parties' obligations and the timing of notifications.

The central legal issues revolved around the interpretation of the Deed of Guarantee, specifically the conditions under which it remained in force. The applicant argued that the guarantee had expired at the completion of the last milestone payment, which coincided with the practical completion of the project. The respondent, however, contended that the guarantee continued until all extra payment claims were resolved and that the timing of the notification to the guarantor was crucial.

The Court examined the language of the Deed of Guarantee, noting that it explicitly tied the duration of the guarantee to the making of the final milestone payment. It further found that the unresolved extra payment claims were not communicated to the guarantor in a timely manner, as required by the terms of the guarantee. The Court concluded that, given these circumstances, the guarantee had indeed expired as per its terms, and the applicant was not liable for the claims made by the respondent.

The Court's judgment resulted in a ruling in favour of the applicant, affirming that the guarantee had expired and that the applicant was not bound to meet the claims of the respondent. This decision hinged on the precise terms of the Deed of Guarantee and the procedural requirements for the guarantor to remain liable. The Court did not order any further payment or action from the applicant towards the respondent’s claims.

Orders

Orders of the court

Judgment for the applicant/third defendant

Background

Background to the litigation

Monadelphous KT Pty Ltd (Monadelphous) entered into a contract with DDG Fortescue River Pty Ltd (DDG) for the construction of a power plant. A Deed of Guarantee was executed by Monadelphous, guaranteeing the performance of DDG's obligations under the contract. The Deed of Guarantee specified that its force would end upon the making of the last milestone payment on practical completion of the project. After the project's practical completion and the final milestone payment, Monadelphous was informed of extra payment claims by DDG. However, these claims were not notified to Monadelphous within the stipulated timeframes, leading to a dispute over whether the Deed of Guarantee remained in force to cover these unresolved claims. Monadelphous argued that the Deed of Guarantee had expired, whereas DDG contended that the guarantee continued to cover any unresolved claims.

The matter came before the court following an application by Monadelphous seeking a declaration that the Deed of Guarantee had expired and that it was not liable for any unresolved extra payment claims by DDG. The application was heard by the court, which reviewed the contractual documentation and evidence regarding the timing of the notification of the extra payment claims. The court examined the terms of the Deed of Guarantee, the completion of the project, and the timeliness of the notifications of the claims to determine the scope and duration of the guarantee.

Decision

Reasons for decision

Issues
1. Whether the force of the Deed of Guarantee expired upon the making of the last milestone payment on practical completion of the project.
2. Whether the unresolved extra payment claims were notified to the Guarantor (Monadelphous) within the required timeframes to remain covered by the Deed of Guarantee.
3. Whether the Guarantor (Monadelphous) is liable for any unresolved extra payment claims by DDG under the Deed of Guarantee.

Held
1. The court concluded that the force of the Deed of Guarantee expired upon the making of the last milestone payment on practical completion of the project.
2. The court found that the unresolved extra payment claims were not notified to the Guarantor (Monadelphous) within the required timeframes and thus were not covered by the Deed of Guarantee.
3. Consequently, the Guarantor (Monadelphous) was not liable for any unresolved extra payment claims by DDG under the Deed of Guarantee.

Ratio Decidendi

Legal Principle Established

The court examined the Deed of Guarantee and the contractual arrangements between the parties. It found that the guarantee's force terminated upon the completion of the project, as stipulated by the terms of the Deed of Guarantee. The court held that the Guarantor's liability ceased once the last milestone payment was made on practical completion of the project. Regarding the extra payment claims, the court noted that the Guarantor was not notified within the specified timeframes for these claims to remain covered by the guarantee. The court emphasized that the timely notification of such claims was a condition precedent for the Guarantor's liability. The court held that since the Guarantor was not notified in time, the unresolved extra payment claims were not covered by the guarantee, and the Guarantor was not liable for them. The decision underscores the importance of strict adherence to notification timeframes in construction guarantees and the precise interpretation of guarantee terms in relation to project completion. The court did not depart from prior authority in its reasoning and followed established principles regarding the conditions for the enforcement of guarantees in construction contracts.