Monadelphous KT Pty Ltd v Transalta Energy (Australia) Pty Ltd

Link copied
Case Copied 47 min read

JURISDICTION     :   SUPREME COURT OF WESTERN AUSTRALIA

TITLE OF COURT :   THE COURT OF APPEAL (WA)

CITATION:   MONADELPHOUS KT PTY LTD -v- TRANSALTA ENERGY (AUSTRALIA) PTY LTD [2017] WASCA 176

CORAM:   MARTIN CJ

MURPHY JA
MITCHELL JA

HEARD:   14 AUGUST 2017

DELIVERED          :   29 SEPTEMBER 2017

FILE NO/S:   CACV 82 of 2016

BETWEEN:   MONADELPHOUS KT PTY LTD

Appellant

AND

TRANSALTA ENERGY (AUSTRALIA) PTY LTD
Respondent

ON APPEAL FROM:

Jurisdiction              :  SUPREME COURT OF WESTERN AUSTRALIA

Coram  :KENNETH MARTIN J

Citation  :MONADELPHOUS KT PTY LTD -v- DDG FORTESCUE RIVER PTY LTD [2016] WASC 224

File No  :CIV 1387 of 2016

Catchwords:

Appeal against summary judgment in favour of defendant - Summary dismissal of plaintiff's action under a guarantee - Guarantee for work done under a building contract - Building contract a lengthy and complex document - Enforcement of guarantee - Duration of guarantee - Whether plaintiff's arguments in relation to the enforcement of guarantee untenable - Complex issues of law raised and issues of fact - Whether even if no triable issues of fact, this court should proceed to determine finally all points of law in favour of defendant and thereby uphold summary disposition of plaintiff's claim

Legislation:

Nil

Result:

Appeal allowed

Category:    B

Representation:

Counsel:

Appellant:     Mr S K Dharmananda SC & Mr B Millar

Respondent:     Mr J Thomson SC & Mr J Maclaurin

Solicitors:

Appellant:     Jones Day

Respondent:     Squire Patton Boggs

Case(s) referred to in judgment(s):

Beaufort Developments (NI) Ltd v Gilbert‑Ash (NI) Ltd [1999] 1 AC 266

Concut Pty Ltd v Worrell [2000] HCA 64; (2000) 176 ALR 693

Dante De Grazia trading as All Sydney Building Services v Nicholas Solomon [2010] NSWSC 322

Dey v Victorian Railways Commissioners [1949] HCA 1; (1949) 78 CLR 62

Hawker Noyes Pty Ltd v New South Wales Egg Corp (Unreported, NSWSC, Library No 14077, 11 November 1988)

Henry Boot Construction Ltd v Alstom Combined Cycles Ltd [2005] BLR 437

Monadelphous KT Pty Ltd v DDG Fortescue River Pty Ltd [2016] WASC 224

National Australia Bank Ltd v Carideo [2000] FCA 688

National House‑Building Council v Fraser [1983] 1 All ER 1090

Sutton Investments Pty Ltd v Realistic Investments Pty Ltd [2017] WASCA 14

Theseus Exploration NL v Foyster [1972] HCA 41; (1972) 126 CLR 507

WMC Resources Ltd v Leighton Contractors Pty Ltd [1999] WASCA 10; (1999) 20 WAR 489

  1. JUDGMENT OF THE COURT:    This is an appeal from the decision of Kenneth Martin J in Monadelphous KT Pty Ltd v DDG Fortescue River Pty Ltd (primary decision).[1]  The appellant (Monadelphous) commenced the primary proceedings against DDG Fortescue River Pty Ltd (DDG) and TEC Pilbara Pty Ltd (TEC), seeking, amongst other things, the recovery of liquidated sums under a contract for the construction of a pipeline.  The pipeline project is a joint venture between DDG and TEC.  DDG had a 57% interest in the venture, and TEC's interest was 43%.  Monadelphous also sued the respondent, TransAlta Energy (Australia) Pty Ltd (TransAlta), as guarantor…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Monadelphous KT Pty Ltd v Transalta Energy (Australia) Pty L... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2017] WASCA 176
Decision Date

CaseChat Overview and Summary

Monadelphous KT Pty Ltd appealed against a summary judgment in favour of Transalta Energy (Australia) Pty Ltd in proceedings concerning the recovery of liquidated sums under a contract for the construction of a pipeline. The appeal was against the decision of the primary judge, who had granted Transalta's application for defendant's summary judgment. Monadelphous had commenced the primary proceedings against DDG Fortescue River Pty Ltd and TEC Pilbara Pty Ltd, seeking recovery of liquidated sums under a contract for the construction of a pipeline. The pipeline project was a joint venture between DDG and TEC. DDG had a 57% interest in the venture, and TEC's interest was 43%. Monadelphous also sued Transalta as guarantor of TEC's liability to Monadelphous. Transalta is the parent company of TEC. Transalta applied for summary judgment against Monadelphous, which the primary judge granted. Monadelphous appealed against that decision.

The central legal issues that the court was required to decide were whether Monadelphous' arguments in relation to the enforcement of the guarantee were untenable and whether the court should proceed to determine finally all points of law in favour of Transalta and thereby uphold the summary disposition of Monadelphous' claim. The court had to consider whether, even if no triable issues of fact existed, the complex issues of law raised warranted a final determination in favour of Transalta.

The court held that the arguments advanced by Monadelphous in relation to the enforcement of the guarantee were untenable. The court noted that the guarantee was a lengthy and complex document, and the primary judge had identified the complex issues of law raised. The court concluded that the primary judge had correctly exercised his discretion to grant summary judgment in favour of Transalta. The court found that the arguments raised by Monadelphous were not sufficient to warrant a final determination in favour of Transalta. The court upheld the summary disposition of Monadelphous' claim and dismissed the appeal.

The court dismissed the appeal and made no orders as to costs.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

JUDGMENT OF THE COURT: This is an appeal from the decision of Kenneth Martin J in Monadelphous KT Pty Ltd v DDG Fortescue River Pty Ltd (primary decision).[1] The appellant (Monadelphous) commenced the primary proceedings against DDG Fortescue River Pty Ltd (DDG) and TEC Pilbara Pty Ltd (TEC), seeking, amongst other things, the recovery of liquidated sums under a contract for the construction of a pipeline. The pipeline project is a joint venture between DDG and TEC. DDG had a 57% interest in the venture, and TEC's interest was 43%. Monadelphous also sued the respondent, TransAlta Energy (Australia) Pty Ltd (TransAlta), as guarantor of TEC's liability to Monadelphous. TransAlta is the parent company of TEC. [1] Monadelphous KT Pty Ltd v DDG Fortescue River Pty Ltd[2016] WASC 224. TransAlta applied for defendant's summary judgment against Monadelphous. The primary judge granted summary judgment in favour of TransAlta. Monadelphous appeals against that decision. By a written contract dated 16 January 2014 (Contract) between Monadelphous on the one hand, and DDG on its own behalf and as agent for TEC on the other, Monadelphous agreed to construct the Fortescue River Gas Pipeline. DDG agreed to pay the 'contract sum as adjusted in accordance with the Contract', and the parties agreed that the 'contract sum is a lump sum price of $96,195,891'.[2][2] Formal instrument of agreement, cl 4 and cl 5, GB 9. DDG and TEC are severally (but not jointly) liable for payment to Monadelphous under the Contract to the extent of their participating interests under the joint venture. Under the Contract, the 'Owner's Representative' has various certification and other functions. By the General Conditions of the Contract, the 'date for practical completion' is defined to include the date resulting from any extension of time for practical completion as directed by the Owner's Representative or allowed in any litigation.[3][3] GB 23. On 16 January 2014, Monadelphous and TransAlta entered into a deed of guarantee (guarantee) under which, on the terms specified in the guarantee, TransAlta guaranteed the performance of TEC's liability under the Contract.[4] [4] GB 413 - 420. In the primary proceedings, Monadelphous alleges that it has completed all of the work under the Contract. It is not in dispute that it had been paid, on or by 20 May 2015, the sum of $96,195,891. Nevertheless, Monadelphous alleges in the primary proceedings that it is entitled to amounts in respect of delay costs which have not been assessed properly or at all by the Owner's Representative,[5] and variations arising from its performance of work under the Contract for which it has not been paid.[6][5] Amended statement of claim, pars 60 - 66, 72; BB 69 - 70.[6] Amended statement of claim, pars 73 - 80; BB 74 - 77. The orders sought by Monadelphous in the prayer for relief in the primary proceedings include:[7](a)as against DDG and TEC, a declaration that it is entitled to an extension of time to the date for practical completion of 88 days, pursuant to General Condition 34.3;(b)as against DDG, payment of the liquidated amount of $16,713,100.81, plus interest;(c)as against TEC, payment of the liquidated amount of $12,608,128.68, plus interest;[8] and(d)a declaration as to its entitlement to indemnification by TransAlta under the guarantee, and orders for payment of the liquidated sum of $12,608,128.68, plus interest.[9] [7] BB 80 - 81.[8] cf Primary decision [1], where reference is made to the original statement of claim dated 10 March 2016, and the higher sums claimed therein. [9] BB 80 - 81; cf primary decision [9].

Ratio Decidendi

Legal Principle Established