CITATION: Dante De Grazia trading as All Sydney Building Services v Nicholas Solomon & Ors [2010] NSWSC 322 HEARING DATE(S): 15/02/10, 18/02/10, 19/02/10, 22/02/10 - 26/02/10, 1/03/10 - 5/03/10, 8/03/10, 10/03/10 - 12/03/10
JUDGMENT DATE :
28 April 2010JURISDICTION: Equity Division
Technology and Construction ListJUDGMENT OF: Einstein J DECISION: The parties are to submit short minutes of order. CATCHWORDS: CONTRACTS - Building, engineering and related contracts - The Contract - Claim by builder for variations and delay costs - Whether Court can adjust date for practical completion under contract - Whether architect/proprietors estopped from pleading that that builder’s claims were not made in compliance with the relevant contractual procedures and therefore must fail - The principle in Liebe v Molloy - Whether the plaintiff builder’s claims for variations and delays made out on the evidence - Relevant principles where the architects are simultaneously the proprietors - Whether architect had duty to act impartially - Whether this duty breached - Performance of work - Whether it is possible to assess delay where construction programming has not occurred - Whether the expert evidence relied upon by the parties should be accepted - Cross-claim by defendants against builder for defective work - PROCEDURE - Courts and judges generally - Courts - Relevant principles for making a finding of fraudulent conduct - Whether allegation of fraudulent conduct made out - TRADE AND COMMERCE - Trade Practices Act 1974 (Cth) and related legislation - Consumer protection - Misleading or deceptive conduct or false representations - Whether brochure produced by cross-defendants was misleading or deceptive - Whether cross-claimants proved reliance on particular representations - Whether causation shown in cross-claim - Whether relevant limitation period had expired - Whether evidence showed that cross-defendants’ product was not fit for purpose. LEGISLATION CITED: Evidence Act 1995
Home Building Act 1989
Sale of Goods Act 1923
Trade Practices Act 1974 (Cth)CATEGORY: Principal judgment CASES CITED: Aleyn v Belchier (1758) 28 ER 634
Arenson v Casson Beckman Rutley & Co [1977] AC 405
Beaufort Developments (NI) Ltd v Gilbert-Ash (NI) Ltd [1999] 1 AC 266
Briginshaw v Briginshaw (1938) 60 CLR 336
Butcher v Lachlan Elder Realty Pty Ltd (2004) 218 CLR 592
Canterbury Pipe Lines Ltd v Christchurch Drainage Board (1979) 16 BLR 86
Dixon v South Australian Railways Commissioner (1923) 34 CLR 71
Fink v Fink (1946) 74 CLR 127
Gould v Vaggelas (1984) 56 ALR 31
Henjo Investments Pty Ltd v Collins Marrickville Pty Ltd (No 1) (1988) 79 ALR 83
Hickman & Co v Roberts [1913] AC 229
John Holland Construction & Engineering Pty Ltd v Majorca Projects Pty Ltd (1996) 13 BCL 235
Jones v Dunkel (1959) 101 CLR 298
London Borough of Merton v Stanley Hugh Leach Ltd (1985) 32 BLR 51
Liebe v Molloy (1906) 4 CLR 347
Lubenham v South Pembrokeshire DC (1986) 33 BLR 39
Lubhman Fidelities and Investments v South Pembrook Shire District Council (1986) 33 BLR 39
Makita (Australia) v Sprowles (2001) 52 NSWLR 705
Medtel Pty…
Keep reading for free
Create a free CaseChat account to read Dante De Grazia trading as All Sydney Building Services v Ni... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Details
- Case
- [2010] NSWSC 322
- Decision Date
CaseChat Overview and Summary
In the case of Dante De Grazia trading as All Sydney Building Services v Nicholas Solomon, the plaintiff sought damages for alleged variations and delays in the construction of a residential property. The dispute involved contractual obligations, claims for variations and delay costs, and allegations of defective work. The case was heard in the Supreme Court of New South Wales. The central legal issues revolved around the enforceability of the contractual procedures for claiming variations and delays, the impartiality of the architect who was also a proprietor, and the assessment of delay costs in the absence of a construction programme. Additionally, the defendants counterclaimed for defective work by the plaintiff.
The court examined whether it could adjust the date for practical completion under the contract and whether the architects and proprietors were estopped from arguing that the builder's claims were not made in compliance with the contractual procedures. The court found that the principle in Liebe v Molloy applied, and therefore, the builder's claims for variations and delays were considered on the evidence presented. The court assessed whether the architect had a duty to act impartially and if this duty was breached. The court also evaluated the expert evidence provided by both parties and determined whether it was sufficient to assess delay costs in the absence of a construction programme.
The court concluded that the builder's claims for variations and delay costs were valid based on the evidence. It found that the architect had a duty to act impartially, which was breached. The court also determined that the evidence provided by both parties was acceptable for assessing delay costs. In relation to the cross-claim, the court found that the defendants had not proven fraudulent conduct by the builder and that the cross-claimants had not shown reliance on particular representations or causation in their claim for misleading or deceptive conduct under the Trade Practices Act 1974 (Cth). The court dismissed the cross-claim and made orders in favour of the plaintiff for the amount claimed for variations and delay costs.
The court examined whether it could adjust the date for practical completion under the contract and whether the architects and proprietors were estopped from arguing that the builder's claims were not made in compliance with the contractual procedures. The court found that the principle in Liebe v Molloy applied, and therefore, the builder's claims for variations and delays were considered on the evidence presented. The court assessed whether the architect had a duty to act impartially and if this duty was breached. The court also evaluated the expert evidence provided by both parties and determined whether it was sufficient to assess delay costs in the absence of a construction programme.
The court concluded that the builder's claims for variations and delay costs were valid based on the evidence. It found that the architect had a duty to act impartially, which was breached. The court also determined that the evidence provided by both parties was acceptable for assessing delay costs. In relation to the cross-claim, the court found that the defendants had not proven fraudulent conduct by the builder and that the cross-claimants had not shown reliance on particular representations or causation in their claim for misleading or deceptive conduct under the Trade Practices Act 1974 (Cth). The court dismissed the cross-claim and made orders in favour of the plaintiff for the amount claimed for variations and delay costs.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi