FEDERAL COURT OF AUSTRALIA

Patrick Stevedores Holdings Pty Ltd v Construction, Forestry, Maritime, Mining and Energy Union [2019] FCA 1647

File number: NSD 620 of 2018
Judge: FLICK J
Date of judgment: 9 October 2019
Catchwords: INDUSTRIAL LAW – statement of agreed facts – agreement as to form of declaratory relief and penalties – principles to be applied – whether agreed penalties within permissible range   
Legislation:

Fair Work Act 2009 (Cth) ss 19, 417, 421, 546

Petroleum Retail Marketing Sites Act1980 (Cth) s 10

Workplace Relations Act 1996 (Cth)

Cases cited:

Australian Building and Construction Commissioner v Construction, Forestry, Mining and Energy Union [2017] FCAFC 113, (2017) 254 FCR 68

Australian Building and Construction Commissioner v Construction, Forestry, Mining and Energy Union (The BKH Contractors Case) (No 2) [2018] FCA 1563

Australian Ophthalmic Supplies Pty Ltd v McAlary-Smith [2008] FCAFC 8, (2008) 165 FCR 560

Commonwealth v Director, Fair Work Building Industry Inspectorate [2015] HCA 46, (2015) 258 CLR 482

Communications, Electrical, Energy, Information, Postal, Plumbing and Allied Services Union of Australia v Laing (1998) 89 FCR 17

DP World Sydney Ltd v Maritime Union of Australia (No 2) [2014] FCA 596, (2014) 318 ALR 22

Fair Work Ombudsman v Maritime Union of Australia [2012] FCA 1232

Fair Work Ombudsman v Quest South Perth Holdings Pty Ltd (No 4) [2017] FCA 580

Kelly v Fitzpatrick [2007] FCA 1080, (2007) 166 IR 14

Markarian v The Queen [2005] HCA 25, (2005) 215 ALR 213

Ministry for Industry, Tourism and Resources v Mobil Oil Australia Pty Ltd [2004] FCAFC 72, (2004) ATPR 41-993

NW Frozen Foods Pty Ltd v Australian Competition and Consumer Commission (1996) 71 FCR 285

Plancor Pty Ltd v Liquor, Hospitality and Miscellaneous Union [2008] FCAFC 170, (2008) 171 FCR 357

Qantas Airways Ltd v Transport Workers’ Union of Australia [2011] FCA 470, (2011) 280 ALR 503

Registered Organisations Commission v Mijatov [2018] FCA 939

Date of hearing: 3 & 12 June 2019
Registry: New South Wales
Division: Fair Work Division
National Practice Area: Employment & Industrial Relations
Category: Catchwords
Number of paragraphs: 39
Counsel for the Applicant: Mr Y Shariff
Solicitor for the Applicant: Seyfarth Shaw Australia
Counsel for the Respondents: Mr R Reitano
Solicitor for the Respondents: Slater & Gordon Lawyers

ORDERS

NSD 620 of 2018
BETWEEN:

PATRICK STEVEDORES HOLDINGS PTY LTD

Applicant

AND:

CONSTRUCTION, FORESTRY, MARITIME, MINING AND ENERGY UNION

First Respondent

PAUL MCALEER

Second Respondent

JUDGE:

FLICK J

DATE OF ORDER:

9 OCTOBER 2019

THE COURT DECLARES THAT:

1.The First Respondent contravened s 417(1) of the Fair Work Act 2009 (Cth) by organising industrial action taken by employees of Patrick Stevedores Holdings Pty Ltd at Port Botany NSW in the form of a refusal to perform work on the day, evening and night shifts of 14 April 2018, and on the night shift ending on 16 April 2018, prior to the nominal expiry date of the Patrick Terminals Enterprise Agreement 2016.

2.The Second Respondent…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Patrick Stevedores Holdings Pty Ltd v Construction, Forestry... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2019] FCA 1647
Decision Date

CaseChat Overview and Summary

The case of Patrick Stevedores Holdings Pty Ltd v Construction, Forestry, Maritime, Mining and Energy Union [2021] FCA 1061 involved a dispute over alleged breaches of the Fair Work Act 2009 (Cth) by the Construction, Forestry, Maritime, Mining and Energy Union (CFMMEU) and an individual, Mr McAleer. The CFMMEU and Mr McAleer were accused of organising industrial action that constituted a refusal to perform work by employees of Patrick Stevedores Holdings Pty Ltd at Port Botany, NSW, in April 2018. The court was required to determine the appropriate penalties for these alleged breaches and whether the penalties agreed upon by the parties were within the permissible range.

The legal issues before the court included whether the agreed penalties were appropriate given the circumstances, and whether they fell within the permissible range as per the Fair Work Act 2009 (Cth). The court evaluated the penalties based on several factors, including the deliberate nature of the industrial action, the absence of contrition, the need for deterrence, and prior contraventions by the CFMMEU and Mr McAleer. The court also considered the significance of the agreement between the parties occurring shortly before the commencement of the proceedings.

The Federal Court concluded that the penalties agreed upon by the parties were appropriate. The court emphasised that the penalties should serve both as a general and specific deterrence. While the court acknowledged the prior contraventions and the positions held by the respondents, it found that the agreed penalties were within the permissible range and therefore should be imposed. The court also ordered declaratory relief in line with the parties' joint proposal.

The final orders included the imposition of a $30,000 penalty on the CFMMEU and a $6,000 penalty on Mr McAleer, to be paid within 30 days. The primary proceeding and the cross-claim were dismissed, and there was no order as to costs.

Orders

Orders of the court

3. A pecuniary penalty of $30,000 is imposed on the First Respondent pursuant to s 546 of the Fair Work Act 2009 (Cth) in respect of the contravention referred to in the Declaration in paragraph 1 above.

4. A pecuniary penalty of $6,000 is imposed on the Second Respondent pursuant to s 546 of the Fair Work Act 2009 (Cth) in respect of the contravention referred to in the Declaration in paragraph 2 above.

5. The above penalties are to be paid to the Applicant in accordance with s 546(3) of the Fair Work Act 2009 (Cth) within 30 days of the date of this order.

6. The primary proceeding is otherwise dismissed.

7. The Cross-claim is dismissed.

8. There is no order as to costs in respect of either the primary proceeding or the Cross-claim.

Note: Entry of orders is dealt with in Rule 39.32 of the Federal Court Rules 2011.

Background

Background to the litigation

When referring to the definition of industrial action in the now-repealed Workplace Relations Act 1996 (Cth), French J in Communications, Electrical, Energy, Information, Postal, Plumbing and Allied Services Union of Australia v Laing (1998) 89 FCR 17 at 30-31 observed:While par (a) of the definition relates to the “performance of work”, par (b) is more broadly expressed. It refers to “a ban, limitation or restriction on the performance of work, or on the acceptance of or offering for work”. The central meaning of the term “ban” in the industrial, as in its ordinary usage, is to “prohibit or interdict”: the Macquarie Dictionary. Communication between persons or an organisation and persons is essential to a “ban”. And while the notion of “limitation” or “restriction” may have a meaning related to manner of actual performance of work, that meaning is picked up in par (a) of the definition. Under par (b) it extends to the communication of a limitation or restriction. Communication picked up under pars (b) and (c) must no doubt purport to be at least hortatory, if not authoritative and binding, upon the person or persons to whom they are directed.See also: Qantas Airways Ltd v Transport Workers’ Union of Australia [2011] FCA 470 at [317], (2011) 280 ALR 503 at 566 per Moore J. The background facts If reference is made to the affidavit evidence that was filed in anticipation of the hearing as to liability, it emerges that the operations at the Terminal included the use of various equipment, including “quay cranes” and “Reach Stackers”. Quay cranes, also called “portainers” or “ship to shore” cranes, are used to extend out over ships which berth at the Terminal and to load and unload shipping containers. The “Reach Stackers” are used to move shipping containers on and off trains. The resolution of breakdowns and maintenance at the Terminal, according to the Engineering and Maintenance Manager at the Terminal (Mr Maurice Hayes), involves Patrick Stevedores:·employing Technical Specialists whose role is to initially diagnose faults, deploy Operations Support Crews and to assist with the resolution of faults with which the Operation Support Crews cannot deal; ·employing Reliability Engineers who have specialist knowledge of various aspects of the machinery used at the Terminal; and ·engaging contractors to perform various functions on site. At all relevant time the Operations Support Crew functions were contracted to Kalmar Equipment (Australia) Pty Ltd (“Kalmar”). Although this summary is extracted from affidavits not read in this proceeding, none of this description is controversial. As set forth in the Statement of Agreed Facts, in April 2018 Kalmar was engaged in enterprise bargaining with its employees who worked at the Terminal. Its employees were represented by the CFMMEU. The CFMMEU notified Kalmar that the Kalmar employees would be engaging in protected stoppage of work for 24 hours commencing at 5.30am on 14 April 2018. This stoppage of work by the Kalmar employees represented by the CFMMEU occurred as notified. Further, on 15 April 2018, there were no electrical tradesmen provided by Kalmar to work the night shift.

Evidence

Evidence Before The Court

Decision

Reasons for decision

In the present case, the manner in which consideration has been given to the agreed position of the parties is to start with an independent assessment that the penalties proposed would be within what would otherwise be considered as a “permissible range”, albeit an assessment very much informed by “instinctive synthesis”. That initial assessment has thereafter been reconsidered – or separately “tested” – by reference to a broad review of the factors summarised by Tracey J in Kelly v Fitzpatrick with a view to determining whether the agreed penalties are “appropriate”. Approached in that manner, it has been concluded that the agreed penalties should be imposed when consideration is given to (in particular) the following factors: ·the prior contraventions by the former Maritime Union of Australia, being contraventions in 2010 and 2012 and the prior contraventions by the CFMMEU in 2015 and 2017 in respect to activities at container terminals;·the prior contraventions of s 417 by Mr McAleer in 2012 and 2017 and the fact that he occupies a senior position within the Sydney Branch of the CFMMEU;·the fact that the unlawful industrial action in the present case was deliberate, insofar as the conduct was itself a conscious decision to cease work;·the absence of contrition; and·the need for the quantum of the penalties imposed to act as both a general and specific deterrence and not to be regarded as merely the “cost of doing business” (cf. Director, Fair Work Building Industry Inspectorate [2015] HCA 46 at [110], (2015) 258 CLR at 523 to 524 per Keane J; Fair Work Ombudsman v Maritime Union of Australia [2012] FCA 1232 at [35] per Barker J). The fact that: ·the agreement between the parties came only shortly before the commencement of the proceeding, assumes a more neutral relevance – the contraventions being alleged were, over time, narrowed by the Applicant and (in particular) involved the abandonment in the Further Amended Statement of Claim of the previously alleged contravention of s 421 of the Fair Work Act. Uninformed by the agreement between the parties, penalties greater than those agreed may have been imposed. But no conclusion can be reached that the penalties as agreed are not “appropriate”.CONCLUSIONS The penalties as agreed between the parties should be imposed. Effect should also be given to the form of declaratory relief as jointly proposed by the parties.THE COURT DECLARES THAT: 1.The First Respondent contravened s 417(1) of the Fair Work Act 2009 (Cth) by organising industrial action taken by employees of Patrick Stevedores Holdings Pty Ltd at Port Botany NSW in the form of a refusal to perform work on the day, evening and night shifts of 14 April 2018, and on the night shift ending on 16 April 2018, prior to the nominal expiry date of the Patrick Terminals Enterprise Agreement 2016.2.The Second Respondent contravened s 417(1) of the Fair Work Act 2009 (Cth) by organising industrial action taken by employees of Patrick Stevedores Holdings Pty Ltd at Port Botany NSW in the form of a refusal to perform work on the day, evening and night shifts of 14 April 2018, and on the night shift ending on 16 April 2018, prior to the nominal expiry date of the Patrick Terminals Enterprise Agreement 2016.THE COURT ORDERS THAT:3.A pecuniary penalty of $30,000 is imposed on the First Respondent pursuant to s 546 of the Fair Work Act 2009 (Cth) in respect of the contravention referred to in the Declaration in paragraph 1 above.4.A pecuniary penalty of $6,000 is imposed on the Second Respondent pursuant to s 546 of the Fair Work Act 2009 (Cth) in respect of the contravention referred to in the Declaration in paragraph 2 above.5.The above penalties are to be paid to the Applicant in accordance with s 546(3) of the Fair Work Act 2009 (Cth) within 30 days of the date of this order.6.The primary proceeding is otherwise dismissed.7.The Cross-claim is dismissed.8.There is no order as to costs in respect of either the primary proceeding or the Cross-claim.

Ratio Decidendi

Legal Principle Established