Fair Work Ombudsman v Quest South Perth Holdings Pty Ltd (No 4)

Link copied
Case Copied 26 min read

FEDERAL COURT OF AUSTRALIA

Fair Work Ombudsman v Quest South Perth Holdings Pty Ltd (No 4) [2017] FCA 580

File number(s): WAD 185 of 2011
Judge(s): GILMOUR J
Date of judgment: 7 June 2017
Catchwords: INDUSTRIAL LAW – penalties and declaratory relief – breach of multiple provisions of the Fair Work Act 2009 (Cth) including div 6 (sham contracting provisions) – grouping of contraventions – whether there was a single course of conduct – assessment of penalties –relevant considerations
Legislation:

Crimes Act 1911 (Cth) s 4AA

Fair Work Act 2009 (Cth) ss 3, 357, 358, 359, 371, 371(1), 539(2) item 11, 546(2)(a), 546(2)(b), 546(3), 546(3)(a), 550, 557, 557(1), 557(2), Chapter 3 - Part 3-1, Division 6

Workplace Relations Act 1996 (Cth) s 719(2)

Independent Contractors Bill 2006 (Cth), Explanatory Memorandum

Cases cited:

Australian Building and Construction Commissioner v Inner Strength Steel Fixing Pty Ltd [2012] FCA 499

Australian Opthalmic Supplies Pty Ltd v McAlary Smith (2008) 165 FCR 560

Commonwealth v Director, Fair Work Building Industry Inspectorate (2015) 326 ALR 476

Director, Fair Work Building Industry Inspectorate v Construction, Forestry Mining and Energy Union [2015] FCAFC 59

Fair Work Ombudsman v A Dalley Holdings Pty Ltd [2013] FCA 509

Fair Work Ombudsman v Centennial Financial Services Pty Ltd [2011] FMCA 459

Fair Work Ombudsman v EA Fuller & Sons Pty Ltd [2013] FCCA 5

Fair Work Ombudsman v Maclean Bay Pty Ltd [2012] FCA 557

Fair Work Ombudsman v Quest South Perth Holdings Pty Ltd (2015) 228 FCR 346

Fair Work Ombudsman v Quest South Perth Holdings Pty Ltd (2015) 256 CLR 137

Fair Work Ombudsman v Quest South Perth Holdings Pty Ltd (No 2) [2013] FCA 582

Fair Work Ombudsman v Tiger Telco Pty Ltd (in liq) [2012] FCA 479

Kelly v Fitzpatrick (2007) 166 IR 14

Mason v Harrington Corporation Pty Ltd [2017] FMCA 7

Mornington Inn Pty Ltd v Jordan [2008] FCAFC 70

Pearcev The Queen (1998) 194 CLR 610

Plancor Pty Ltd v Liquor, Hospitality and Miscellaneous Union (2008) 171 FCR 357

Ponzio v B&P Caelli Constructions Pty Ltd (2007) 158 FCR 543

Date of hearing: Determined on the papers
Registry: Western Australia
Division: General Division
National Practice Area: Employment & Industrial Relations
Category: Catchwords
Number of paragraphs: 96
Solicitor for the Applicant: Mr M Kelleher of Clayton Utz
Counsel for the First Respondent: The First Respondent did not appear
Counsel for the Second Respondent: The Second Respondent did not appear
 Counsel for the Third Respondent: The Third Respondent did not appear

ORDERS

WAD 185 of 2011
BETWEEN:

FAIR WORK OMBUDSMAN

Applicant

AND:

QUEST SOUTH PERTH HOLDINGS PTY LTD

First Respondent

CONTRACTING SOLUTIONS PTY LTD
Second Respondent

MR ASHVIN LUCHMAYA

Third Respondent

JUDGE:

GILMOUR J

DATE OF ORDER:

7 JUNE 2017

THE COURT ORDERS THAT:

1.The first respondent pay a penalty of $16,500 in respect to its contravention of s 357(1) of the Fair Work Act 2009 (Cth) (FW Act), by representing to Margaret Best that the contract of employment under which she was employed…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Fair Work Ombudsman v Quest South Perth Holdings Pty Ltd (No... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2017] FCA 580
Decision Date

CaseChat Overview and Summary

The Fair Work Ombudsman (FWO) brought proceedings against Quest South Perth Holdings Pty Ltd and others for multiple breaches of the Fair Work Act 2009 (Cth). Quest had engaged in conduct that involved reclassifying its employees as independent contractors through a contracting system operated by Contracting Solutions Pty Ltd. This arrangement was found to be unlawful under the Fair Work Act, particularly in contravention of sections 357, 358, and 359. The court was tasked with determining the appropriate penalties for these breaches, assessing the relevant considerations such as the seriousness of the breaches and the need to ensure compliance with minimum standards.

The key legal issues included whether the contraventions constituted a single course of conduct for penalty assessment purposes, the relevance of contrition, corrective action, and co-operation with enforcement authorities, and the importance of ensuring compliance with minimum standards as outlined in the Fair Work Act. The court considered the deliberate and indifferent nature of Quest and its manager's conduct, their failure to defend the proceedings adequately, and the absence of any meaningful corrective action or contrition.

The court held that Quest and its manager, Luchmaya, were liable for the contraventions. It found that the breaches were part of a single course of conduct, justifying the application of penalties for each contravention. The court did not reduce penalties for the lack of contrition or corrective action, noting the seriousness of the breaches and the need to uphold minimum standards. The penalties were assessed based on the maximum statutory penalties, adjusted for the circumstances of each contravention.

The court ordered Quest to pay penalties for each contravention, with amounts varying based on the specific breach. Additionally, Luchmaya, as an individual respondent, was ordered to pay a penalty for his involvement in the contraventions. Each party was required to pay their respective penalties to the Commonwealth within 30 days of the judgment.

Orders

Orders of the court

1. The first respondent pay a penalty of $16,500 in respect to its contravention of s 357(1) of the Fair Work Act 2009 (Cth) (FW Act), by representing to Margaret Best that the contract of employment under which she was employed by the first respondent was a contract for services under which she performed work as an independent contractor.

2. The first respondent pay a penalty of $16,500 in respect to its contravention of s 357(1) of the FW Act, by representing to Ms Carol Roden that the contract of employment under which she was employed by the first respondent was a contract for services under which she performed work as an independent contractor.

3. The first respondent pay a penalty of $21,450 in respect to its contravention of s 358 of the FW Act by threatening to dismiss Ms Jessica Buttrum-Virco in order to engage her as an independent contractor to perform the same, or substantially the same, work under a contract for services.

4. The third respondent pay a penalty of $4,290 in respect to his contravention of s 359 of the FW Act, by way of his involvement in the first respondent’s contravention of s 358 of the FW Act within the meaning of s 550 of the FW Act.

5. The first and third respondents each pay penalties to the Consolidated Revenue Fund of the Commonwealth in accordance with subsection 546(3) of the FW Act within 30 days.

Note: Entry of orders is dealt with in Rule 39.32 of the Federal Court Rules 2011.

Background

Background to the litigation

Indeed, in ABCC v Inner Strength, I observed that "[t]he penalty regime established for sham contracting arrangements…is indicative of the seriousness with which the legislature views this type of conduct." Factual background Again, the relevant factual background was uncontentious. The following is a relevant summary drawn variously from the reasons of the first instance judgment and of the Full Court as well as the High Court. Quest operated a business in 2009 known as the Quest on Arlington in South Perth (Quest on Arlington), providing serviced apartment accommodation. Luchmaya was employed by Quest at Quest on Arlington as its Manager from mid-2009 until November 2010. In 2007, Quest employed Best and Roden as housekeepers. On 18 March 2009, Buttrum-Virco started work at Quest as a receptionist (collectively, the Employees). In mid to late 2009, Luchmaya, as a Manager for Quest, contacted a representative of the second respondent, Contracting Solutions Pty Ltd (Contracting Solutions) which operated a contract labour hire business utilising the Odco system. Various meetings occurred between representatives of Quest (primarily Luchmaya) and Contracting Solutions (primarily the fourth respondent, Konstek) in September and early October 2009 with a view to Quest engaging Contracting Solutions to implement its contracting system for housekeeping and reception staff working at Quest's business. The process by which the Employees would be "converted" into independent contractors working at Quest was agreed to be managed by Contracting Solutions on behalf of Quest. The object of the exercise was that the Employees would continue to perform the same work for Quest as they were performing, but rather as independent contractors under Contracting Solutions' system and not as employees. Best and Roden In October 2009, Quest and Contracting Solutions entered into the contracting relationship described above. Best and Roden signed what was known as a "Contractor Application" with Contracting Solutions. Once the arrangement was implemented, Best and Roden performed the same housekeeping work and in the same manner as they had as employees, and remained under the control and direction of Quest. The only difference was that they were paid by Contracting Solutions. Buttrum-Virco Buttrum-Virco did not attend the initial meetings with Contracting Solutions referred to above, and had an individual meeting with a representative of Contracting Solutions. At the meeting, it emerged that Buttrum-Virco intended to move to Melbourne in the near future. She was told by the representative of Contracting Solutions that, "there is probably not much point in you [becoming an individual contractor], it would be better for you to stay an employee." Buttrum-Virco felt insecure about the meeting. She signed the "conversion documentation", but did not fill out any details, and gave it to Luchmaya at her next shift. In late November 2009, Buttrum-Virco had a discussion with Luchmaya. He noted that Buttrum-Virco had not completed the "conversion documentation". Luchmaya threatened Buttrum-Virco saying to her, "if you don't fill out the last few pages you won't get paid."

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established

Luchmaya was the responsible General Manager at Quest at the relevant times. He was intimately involved in the process and set about engaging Contracting Solutions and was largely personally responsible for the implementation of the unlawful system put into place. This I find demonstrates the deliberate nature of Luchmaya's unlawful conduct: see ABCC v Inner Strength at [21]. Contrition, corrective action and co-operation with enforcement authorities Aside from Quest filing a defence, and Luchmaya an amended defence, neither party has actively defended the FWO's application. Quest and Luchmaya did not participate in the liability hearing. McKerracher J granted leave to the FWO to proceed against Quest and Luchamaya in their absence at the liability hearing. Quest also did not participate in the Full Court appeal nor in the appeal to the High Court. Quest's and Luchmaya's conduct in failing to admit any contraventions, and ignoring the Court process, put the FWO to the expense of having to prove its case in relation to the s 358 contraventions at the liability hearing, and in relation to Quest, on appeal to the High Court in relation to the s 357 contraventions. It was for Quest to prove any s 357(2) defence. Self-evidently it did not do so. Haayema gave evidence at the liability hearing, but not on behalf of Quest to satisfy s 357(2). Quest's conscious decision not to positively defend the application is indicative, in my opinion, at least of indifference towards the seriousness of the contraventions and the Court process. In relation to the s 357 contraventions by Quest, although the issue was determined in Quest's favour at the liability hearing, and by the Full Court, the issue which ultimately required the determination by the High Court was only first raised by the Full Court. The FWO submits that this factor should not mitigate any penalties which may be imposed on Quest, as no evidence was led by it at liability hearing to the effect that it considered the application of s 357 which was ultimately considered by the High Court, or otherwise sought to satisfy the defence for which if carried the onus in s 357(2). I accept this submission. On about 30 December 2009, Buttrum-Virco received a payment of $1,451 from Quest. This amount was for accrued annual leave entitlements owed to her after she terminated her employment to become an independent contractor. The FWO submits that this payment was not corrective of the relevant contraventions and should not be considered as corrective action for the purposes of determining an appropriate penalty. There is otherwise no evidence or indication whatsoever of any contrition or corrective action with enforcement authorities by Quest or Luchmaya. Ensuring compliance with minimum standards The FWO submits that ensuring compliance with minimum standards is an important consideration in this case. He submits that one of the principle objects of the FW Act is the maintenance of an effective safety net of employer obligations and effective enforcement mechanisms and that the substantial penalties set by the legislature for contravention of such obligations reinforce the importance placed on compliance with minimum standards: see the objects outlined in s 3 of the FW Act.