JURISDICTION : SUPREME COURT OF WESTERN AUSTRALIA
IN CHAMBERS
CITATION: NEPEAN CONVEYORS PTY LTD -v- LINKFORCE INDUSTRIAL SERVICES PTY LTD [2024] WASC 71
CORAM: SEAWARD J
HEARD: 1 AND 8 MARCH 2024
DELIVERED : 14 MARCH 2024
PUBLISHED : 14 MARCH 2024
FILE NO/S: CIV 1252 of 2024
BETWEEN: NEPEAN CONVEYORS PTY LTD
Plaintiff
AND
LINKFORCE INDUSTRIAL SERVICES PTY LTD
Defendant
Catchwords:
Practice and procedure - Application for interlocutory injunction to prevent adjudication under the Construction Contracts Act 2004 (WA) - Serious question to be tried - Whether construction contract is not a construction contract for the purposes of the Act - Balance of convenience favours defendant
Legislation:
Construction Contracts (Former Provisions) Act 2004 (WA)
Result:
Application dismissed
Category: B
Representation:
Counsel:
| Plaintiff | : | Mr M R Collins |
| Defendant | : | Mr D Pratt |
Solicitors:
| Plaintiff | : | Thomson Geer Lawyers |
| Defendant | : | Tottle Partners |
Cases referred to in decision:
Diploma Construction (WA) Pty Ltd v KPA Architects Pty Ltd [2014] WASCA 91
Duro Felguera Australia Pty Ltd v Samsung C&T Corporation [2016] WASC 119
Enerflex Process Pty Ltd v Kempe Engineering Services (Australia) Pty Ltd [2013] WASC 406
Field Deployment Solutions Pty Ltd v SC Projects Australia Pty Ltd [2015] WASC 60
Lucas Stuart Pty Ltd v Hemmes Hermitage Pty Ltd (2012) 28 BCL 226; [2010] NSWCA 283
Mineralogy Pty Ltd v Sino Iron Pty Ltd [2016] WASCA 105
Oasis Newman Operations Pty Ltd v Hockley [2023] WASC 79
Perrinepod Pty Ltd v Georgiou Building Pty Ltd [2011] WASCA 217; (2011) 43 WAR 319
Re Graham Anstee-Brook; Ex Parte Karara Mining Ltd [2012] WASC 129
Samsung C & T Corporation v Loots [2016] WASC 330
Samsung C&T Corporation v Duro Felguera Australia Pty Ltd [2018] WASCA 27; (2018) 52 WAR 281
Sugar Australia Pty Ltd v Lend Lease Services Pty Ltd (2015) 31 BCL 407; [2015] VSCA 98
SEAWARD J:
Introduction
This is the plaintiff's application for an interlocutory injunction seeking to prevent the defendant from commencing an adjudication application under the Construction Contracts (Former Provisions) Act 2004 (WA) (the Act).
The plaintiff's application came before me on an urgent basis on Friday 1 March 2024 on an ex parte basis. After hearing from counsel for the plaintiff, I granted an interim injunction until further order of the court and listed the matter for an inter partes hearing on Tuesday 5 March 2024. I indicated to counsel for the plaintiff that I had availability during the week to hear the application for the interlocutory injunction on other days of the week if, following service of the papers and conferral with the defendant, the defendant sought additional time to file any submissions in response. Following that conferral, the parties provided my chambers with a minute of consent orders programming the application to a hearing on Friday 8 March 2024.
Evidence
The plaintiff relies on the affidavit of Roelof van Rooyen, affirmed on 1 March 2024. Mr van Rooyen is the Managing Director of the plaintiff.
The plaintiff…
Keep reading for free
Create a free CaseChat account to read Nepean Conveyors Pty Ltd v Linkforce Industrial Services Pty... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2024] WASC 71
- Decision Date
CaseChat Overview and Summary
The central legal issue before the court was whether the construction contract between Nepean Conveyors and Linkforce fell within the scope of the 'mining exception' as outlined in section 4(3)(c) of the Construction Contracts Act 2004 (WA). This determination required a detailed analysis of the nature of the work specified in the contract, the purpose and function of the plant to be assembled, and the extent to which the plant was integral to the mining operations. The court had to consider whether the conveyor systems were integral to the extraction or processing of substances, thereby falling under the exemption.
The court acknowledged that the plaintiff had established a serious question to be tried concerning the applicability of the 'mining exception' to the contract. However, the court concluded that at the interlocutory stage, it was not possible to ascertain the strength of the plaintiff's case. The court emphasised that a definitive view on the matter would likely require the presentation of evidence regarding the precise nature and scope of the work and its relation to the mining operations. The balance of convenience was found to favour the defendant, leading to the denial of the injunction.
In conclusion, the court dismissed the application for an interlocutory injunction, finding that the plaintiff had not demonstrated a strong enough case to warrant the grant of the injunction. The court also highlighted the need for further evidence to determine the applicability of the 'mining exception' to the contract.
Background
Background to the litigation
The matter came before the court on an application by the plaintiff for an interlocutory injunction. This was the second such application by the plaintiff, the first being an application for judicial review. The primary basis of the plaintiff's case was that the contract was not a construction contract as it concerned work falling within the 'mining exception' under the Construction Contracts Act 2004 (WA). The defendant conceded that the plaintiff could meet the threshold of establishing a serious question to be tried regarding this aspect of the case. The court was required to determine whether there was a serious question to be tried and whether the balance of convenience favoured the defendant in this interlocutory application.
Decision
Reasons for decision
1. Whether there is a serious question to be tried regarding whether the construction contract falls within the 'mining exception' under the Construction Contracts Act 2004 (WA).
2. Whether the balance of convenience favours the defendant in this interlocutory application for an injunction.
Held
1. The court concluded that there is a serious question to be tried regarding whether the construction contract falls within the 'mining exception' under the Construction Contracts Act 2004 (WA).
2. The court found that the balance of convenience favours the defendant in this interlocutory application for an injunction.
Ratio Decidendi
Legal Principle Established
Similar expressions as to the purpose of the Act are found in other cases of this court. See for example Oasis Newman Operations Pty Ltd v Hockley;[23] Diploma Construction (WA) Pty Ltd v KPA Architects Pty Ltd;[24] Perrinepod Pty Ltd v Georgiou Building Pty Ltd;[25] Samsung C & T Corporation v Loots.[26][23] Oasis Newman Operations Pty Ltd v Hockley [2023] WASC 79 at [145] - [146] (Solomon J).[24] Diploma Construction (WA) Pty Ltd v KPA Architects Pty Ltd [2014] WASCA 91 [55] (Pullin JA).[25] Perrinepod Pty Ltd v Georgiou Building Pty Ltd [2011] WASCA 217; (2011) 43 WAR 319 [87] - [88] (Murphy JA).[26] Samsung C & T Corporation v Loots [2016] WASC 330 [65] (Beech J). As this is an application for an interlocutory injunction, my views and opinions as to whether there is a serious question to be tried are views expressed only as to the strength of the serious question to be tried. They are not views as to the final merits of the plaintiff's case. The primary basis of the plaintiff's case in both the application for a declaration the subject of these proceedings, and the application for judicial review, is that the Contract is not a construction contract for the purposes of the Act because it concerns construction work falling within the 'mining exception' contained in s 4(3)(c) of the Act. This position underpins the first two declarations sought in these proceedings, and the first two grounds of the application for judicial review. The question of whether the work the subject of the Contract falls within the exception involves a consideration and understanding of the work to be performed under the Contract, the purpose and function of the plant to be assembled (in this case, two overland conveyor systems for the Roy Hill Iron Ore Pty Ltd expansion project) and then a consideration of the extent to which it can be said that the conveyors are items of plant used for extracting or processing any of the relevant substances referred to in the exemption. This may (depending on that evidence) involve considering whether the plant performs a function so related to the extraction or processing of the substance so as to make it part of plant used for that purpose. In this regard, see the decisions of Re Graham Anstee-Brook; Ex Parte Karara Mining Ltd[27] and Samsung C &T Corporation v Loots.[28][27] Re Graham Anstee-Brook; Ex Parte Karara Mining Ltd [2012] WASC 129 [16].[28] Samsung C &T Corporation v Loots [2016] WASC 330 [354]. The defendant accepts that the plaintiff can meet the threshold of establishing a serious question to be tried in relation to this aspect of the plaintiff's case. This concession is appropriately made. The description of the work contained in the Contract, when compared with the wording of the exemption, forms a reasonable basis to conclude that the exemption might apply. However, I accept the defendant's submission that it is not possible, at this interlocutory stage, for me to form any view about the strength of the plaintiff's case. This is because a consideration of this issue will likely involve the leading of evidence as to the precise nature and scope of the works under the Contract and how that work sits in the context of the Roy Hill mining operations and the provisions of the exception.