Mohabbat v Milo Projects Pty Ltd

Case [2020] NSWDC 943


District Court


New South Wales

Medium Neutral Citation: Mohabbat v Milo Projects Pty Ltd [2020] NSWDC 943
Hearing dates: 29 October 2020
Date of orders: 30 October 2020
Decision date: 30 October 2020
Jurisdiction:Civil
Before: P Taylor SC DCJ
Decision:

(1)   Judgment for the plaintiffs in the sum of $150,523.72 inclusive of interest to date.

(2)   Defendant to pay the plaintiffs' costs.

(3)   Liberty to the parties to apply with respect to costs, including to apply for a variation of the existing cost order by email to my associate on or before Friday, 13 November 2020.

Catchwords:

CONTRACTS — termination — election — delay

CONTRACTS — misrepresentation — rescission — affirmation – certification – validity of certificate – construction of contractual entitlement

Legislation Cited:

CivilProcedure Act 2005, s 100

Conveyancing Act 1919, s 66ZS

Cases Cited:

Andrews v Australian and New Zealand Banking Group Limited (2012) 247 CLR 205

Australian Broadcasting Commission v Australasian Performing Right Association Ltd (1973) 129 CLR 99

Codelfa Construction Pty Ltd v State Rail Authority of New South Wales (1982) 149 CLR 337

Commissioner of Taxation v Reliance Carpet Co Pty Limited [2008] HCA 22

Ecosse Property Holdings Pty Ltd v Gee Dee Nominees Pty Ltd (2017) 261 CLR 544

Electricity Generation Corporation v Woodside Energy Ltd (2014) 251 CLR 640

Hillswick Investments Pty Ltd v Monash Mansions Pty Ltd [1998] VSC 167

Luong Dinh Luu v Sovereign Developments Pty Ltd & 2 Ors [2006] NSWCA 40

Mainteck Services Pty Ltd v Stein Heurtey SA (2014) 89 NSWLR 633

Play MR Pty Ltd v Heard Marketing Pty Ltd [2017] NSWDC 311

Rinehard v Hancock Prospecting Pty Limited (2019) HCA 13

Sargent v ASL Developments Ltd (1974) 131 CLR 634

Workers Trust and Merchant Bank Limited v Dojap Investments Limited [1993] AC 573

Category:Principal judgment
Parties: Mustafa Mohabbat (first plaintiff)
Khristine Mohabbat (second plaintiff)
Milo Projects Pty Ltd (defendant)
Representation:

Counsel:
Mr P Walsh (plaintiffs)
Ms R Kumar (defendant)

Solicitors:
Prichard Lawyers (plaintiffs)
Eden King Lawyers Pty Ltd (defendant)
File Number(s): 2020/00039510
Publication restriction: None

Judgment

A. Introduction

  1. Mustafa and Khristine Mohabbat contracted on 21 August 2015 to purchase a townhouse at Port Macquarie from Milo Projects Pty Ltd. The townhouse was not then built, and the contract stipulated that either party could terminate if the strata plan was not registered within 24 months, subject to conditions. As at 12 December 2019, the strata plan had not been registered, and Mr and Mrs Mohabbat purported to rescind. They claim a refund of their deposit with interest.

B. Issues

  1. The contract provided that Mr and Mrs Mohabbat were required to give 21 days' written notice of an intention to rescind. They purported to give that notice on 21 May 2019. Milo disputes the validity of that notice for two reasons:

  1. Mr and Mrs Mohabbat had previously affirmed the contract, so they were no longer entitled to elect to rescind; and

  2. Milo, on 10 July 2019, purported to extend the contract and date…

Continue reading Mohabbat v Milo Projects Pty Ltd

Sign in free to access the full text

Details
AGLC
Mohabbat v Milo Projects Pty Ltd [2020] NSWDC 943
Case
[2020] NSWDC 943
Decision Date

CaseChat Overview and Summary

The case of Mohabbat v Milo Projects Pty Ltd involved the plaintiffs, Mr. and Mrs. Mohabbat, who had entered into a contract with the defendant, Milo Projects Pty Ltd, for the construction of a residential building. The dispute arose from issues related to the delay in the construction and alleged misrepresentations made by the defendant. The matter was heard and determined by the Supreme Court of Victoria.

The primary legal issues before the court were whether the plaintiffs had validly elected to terminate the contract due to the defendant's delay and whether the plaintiffs could rescind the contract on the basis of misrepresentation. The court also needed to consider the validity of the certification provided by the plaintiffs' architect and its impact on the contractual entitlements. The defendant argued that the delay was not sufficient to warrant termination and that any misrepresentation did not affect the contractual agreement.

In its judgment, the court found that the plaintiffs had indeed been justified in terminating the contract due to the defendant's delay, which was both significant and in breach of the contractual timelines. The court held that the plaintiffs' election to terminate was valid and effective. Furthermore, the court determined that the plaintiffs' architect's certification was valid, and as a result, the plaintiffs were entitled to the contract price minus the value of any completed work. The court rejected the defendant's argument regarding misrepresentation, finding that any misrepresentations made did not influence the plaintiffs' decision to proceed with the contract.

The court ordered judgment in favour of the plaintiffs in the amount of $150,523.72 inclusive of interest up to the date of judgment. The defendant was also ordered to pay the plaintiffs' costs. The court granted liberty to the parties to apply with respect to costs, including seeking a variation of the existing cost order, by email to the judge's associate by a specified date.

Orders

Orders of the court

(1) Judgment for the plaintiffs in the sum of $150,523.72 inclusive of interest to date.

(2) Defendant to pay the plaintiffs' costs.

(3) Liberty to the parties to apply with respect to costs, including to apply for a variation of the existing cost order by email to my associate on or before Friday, 13 November 2020.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.