Management Services Australia Pty Ltd t/as Peak Performance PM v PM Works Pty Ltd

Link copied
Case Copied 53 min read

Court of Appeal


Supreme Court


New South Wales

  • Amendment notes
Medium Neutral Citation: Management Services Australia Pty Ltd trading as Peak Performance PM v PM Works Pty Ltd [2019] NSWCA 107
Hearing dates: 12 February 2019
Decision date: 14 May 2019
Before: Bathurst CJ at [1];
Gleeson JA at [2];
Sackville AJA at [3].
Decision:

(1)   Appeal dismissed.

 (2)   Peak Performance pay PM Works’ costs of the appeal.
Catchwords:

CONTRACTS – construction and interpretation – variation of terms – where parties agreed to jointly provide project management training services to third parties – where appellant provided course materials and issued completion certificates – where client dissatisfied – whether parties agreed to vary their agreement – where first respondent subsequently delivered training courses using its own materials and certification services – whether variation agreement required payment of royalty fee to the appellant in such circumstances – whether first respondent bound to engage appellant to provide certification services

 

CONTRACTS – breach – where first respondent developed and used its own course materials – whether first respondent breached agreement as varied by not engaging appellant to provide certification services

  CONTRACTS – termination – repudiation of contract – where first respondent ceased paying royalty fees to the appellant for courses provided to clients using its own materials and certification services – whether contract was repudiated by conduct – whether primary judge erred in inferring parties’ conduct consistent with mutual agreement to terminate their contractual relationship
Legislation Cited: Supreme Court Act 1970 (NSW), s 75A(1), (8)
Cases Cited: Ecosse Property Holdings Pty Ltd v Gee Dee Nominees Pty Ltd [2017] HCA 12; (2017) 343 ALR 58 Electricity Generation Corporation v Woodside Energy Ltd (2014) 251 CLR 640; [2014] HCA 7
Koompahtoo Local Aboriginal Land Council v Sanpine Pty Ltd (2007) 233 CLR 115; [2007] HCA 61
Re Golden Key Ltd [2009] EWCA Civ 636
Mainteck Services Pty Ltd v Stein Heurtey SA (2014) 89 NSWLR 633; [2014] NSWCA 184
Management Service Australia Pty Ltd v PM Works Pty Ltd [2017] NSWSC 1743
Management Services Australia Pty Ltd v PM Works Pty Ltd (No. 2) [2018] NSWSC 336
Mount Bruce Mining Pty Ltd v Wright Prospecting Pty Ltd (2015) 256 CLR 104; [2015] HCA 37
Simic v New South Wales Land and Housing Corporation [2016] HCA 47; (2016) 339 ALR 200 Taouk v Assure (NSW) Pty Ltd [2017] NSWCA 227
Western Export Services Inc v Jireh International Pty Ltd [2011] HCA 45; (2012) 85 ALJR 1
Texts Cited: NC Seddon and RA Bigwood, Cheshire and Fifoot Law of Contract (11th ed, 2017)
Category:Principal judgment
Parties: Management Services Australia Pty Ltd trading as Peak Performance PM (Appellant)
PM Works Pty Ltd (First Respondent)
Amit Banerji (Second Respondent)
Representation:

Counsel:
Mr F Assaf SC / Mr PJ Strickland (Appellant)
Ms M Cairns / Ms L Hulmes (First and Second Respondents)

  Solicitors:
Sparke Helmore Lawyers (Appellant)
Resolve Litigation Lawyers (First and Second Respondents)
File Number(s): 2017/384655
 Decision under appeal 
Court or…
CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Management Services Australia Pty Ltd t/as Peak Performance... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2019] NSWCA 107
Decision Date

CaseChat Overview and Summary

Management Services Australia Pty Ltd trading as Peak Performance PM (the appellant) and PM Works Pty Ltd (the first respondent) entered into an agreement to jointly provide project management training services to third parties. The appellant was responsible for providing course materials and issuing completion certificates. A dispute arose when a client expressed dissatisfaction with the services. Subsequently, the first respondent began delivering training courses using its own materials and certification services. The central issue was whether the parties had varied their original agreement, and if so, whether this variation required the first respondent to pay a royalty fee to the appellant for courses delivered using its own materials and certification, and whether the first respondent was bound to engage the appellant for certification services.

The court was required to determine whether the parties had mutually agreed to vary their original contract. Specifically, it needed to ascertain if the first respondent's subsequent actions, including developing and using its own course materials and certification services, constituted a breach of the agreement as varied. Furthermore, the court had to consider whether the first respondent's cessation of royalty payments for courses provided using its own materials and certification amounted to a repudiation of the contract by conduct, and whether the primary judge had erred in inferring that the parties' conduct was consistent with a mutual agreement to terminate their contractual relationship.

The court found that the parties' conduct indicated a mutual agreement to vary their original contract. The first respondent's use of its own materials and certification services, coupled with the appellant's acquiescence, demonstrated an intention to depart from the original terms. The court reasoned that the primary judge had correctly inferred from the parties' conduct that they had mutually agreed to terminate their contractual relationship. This conclusion was based on the evidence that the first respondent had ceased paying royalty fees and had independently provided training services, and the appellant had not objected to this course of action.

The appeal was dismissed, and the appellant was ordered to pay the first respondent’s costs of the appeal.

Orders

Orders of the court

(1) Appeal dismissed.

(2) Peak Performance pay PM Works’ costs of the appeal.

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established