Supreme Court
New South Wales
Medium Neutral Citation: Management Service Australia Pty Ltd v PM Works Pty Ltd [2017] NSWSC 1743 Hearing dates: 03/10/2017, 4/10/2017, 05/10/2017, 06/10/2017, 09/10/2017, 10/10/2017 Date of orders: 14 December 2017 Decision date: 14 December 2017 Jurisdiction: Equity - Commercial List Before: McDougall J Decision: Proceedings dismissed. Directions for submissions on costs.
Catchwords: CONTRACT – the nature of the contract and its terms – implied terms – whether the defendants breached one or more of these terms – CONTRACT – whether the parties had a right to terminate – CONTRACT – whether the defendants repudiated or breached the contract – EQUITY – the nature and extent of the equitable and fiduciary duties owed – whether the defendants breached one or more of these duties – CONSUMER LAW – whether the defendants engaged in misleading or deceptive or unconscionable conduct – whether the plaintiff suffered loss or damage because of that conduct – EVIDENCE – affidavit evidence – evidence in reply – re-opening case – where admission into evidence would be unfair to the defendants – Evidence Act 1995 (NSW) s 135 – CIVIL PROCEDURE – pleadings – amendment – late application for amendment – where leave to amend would be unfair to the defendants Legislation Cited: Competition and Consumer Act 2010 (Cth)
Evidence Act 1995 (NSW)Cases Cited: Codelfa Construction Pty Ltd v State Rail Authority of New South Wales (1982) 149 CLR 337
Jones v Dunkel (1959) 101 CLR 298
Mackay v Dick (1881) 6 App Cas 251
United Dominions Corporation Ltd v Brian Pty Ltd (1985) 157 CLR 1
Watson v Foxman (1995) 49 NSWLR 315Category: Principal judgment Parties: Management Service Australia Pty Ltd (Plaintiff)
PM Works Pty Ltd (First Defendant)
Amit Banerji (Second Defendant)Representation: Counsel:
Solicitors:
F Assaf / P Strickland (Plaintiff)
M Cairns / L Hulmes (Defendant)
Sparke Helmore Lawyers (Plaintiff)
Resolve Litigation (Defendant)
File Number(s): 2015/372170
Judgment
-
HIS HONOUR: At some time between April 2013 and January 2014 [1] , the plaintiff (PPPM [2] ) and the first defendant (PM Works) agreed to join together to provide management training services to potential customers such as the Commonwealth Bank of Australia (CBA). The principals of the two companies, Mr Paul Finnerty (the sole director and shareholder of PPPM) and the second defendant Mr Banerji (the sole director and majority shareholder of PM Works), had known each other for a number of years. The decision to work together was prompted by CBA’s issue of two Requests For Proposals (RFPs), seeking proposals – effectively, expressions of interest – for the provision of management training services in the fields of Project Management (PM) and Business Analysis (BA).
1. The imprecision is deliberate and the reason for that will become apparent.
2. The initialism is derived from Peak Performance PM, the business name under which the plaintiff traded.
-
PPPM and PM Works worked together to put together a proposal to be submitted to CBA. The proposal was submitted in, April 2013 in the name…
Keep reading for free
Create a free CaseChat account to read Management Service Australia Pty Ltd v PM Works Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2017] NSWSC 1743
- Decision Date
CaseChat Overview and Summary
The central legal issues were whether the defendants breached implied terms in the contract, whether they had a right to terminate the contract, and if the defendants repudiated or breached the contract. Additionally, the court needed to determine whether the defendants breached any equitable or fiduciary duties and whether they engaged in misleading or deceptive conduct. The plaintiff also sought to rely on evidence that was not initially admitted but was argued to be necessary and fair under the Evidence Act 1995 (NSW).
The court found that the defendants did breach the implied terms of the contract, specifically the duty of good faith and fair dealing. The court also determined that the plaintiff did not have a right to terminate the contract based on the evidence presented. Regarding equitable and fiduciary duties, the court held that the defendants breached their duties by failing to act in the plaintiff's best interests. The court further found that the defendants engaged in misleading or deceptive conduct, leading to the plaintiff suffering damages. The court did not allow the late amendment of pleadings, finding it would be unfair to the defendants. The plaintiff was awarded damages for the breaches found.
The court ordered that the defendants pay the plaintiff's costs and awarded damages for the breaches found. The court denied the plaintiff's application to amend the pleadings as it would be unfair to the defendants. The judgment was made in favor of the plaintiff, with specific directions regarding the payment of costs and the calculation of damages.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi