FEDERAL COURT OF AUSTRALIA

Maersk Crewing Australia Pty Ltd v Construction, Forestry, Maritime, Mining and Energy Union [2021] FCAFC 231

Appeal from: Maersk Crewing Australia Pty Ltd v Construction, Forestry, Maritime, Mining and Energy Union (No 2) [2020] FCA 1694
File number: WAD 302 of 2020
Judgment of: WHITE, BANKS-SMITH AND JACKSON JJ
Date of judgment: 17 December 2021
Catchwords: INDUSTRIAL LAW - primary judge dismissed application for declarations that Fair Work Commission (FWC) lacked jurisdiction to make arbitral award - dispute over manning levels on vessels - meaning of 'dispute' in s 739(4) of Fair Work Act 2009 (Cth) - construction of enterprise agreement - separate settlement agreement between union and company - terms of enterprise agreement included dispute resolution procedure providing for arbitration by FWC if matter unresolved after certain steps complied with - whether matter resolved by separate agreement - accord and satisfaction - enforceability of separate agreement - intention to create contractual relations - separate agreement incapable of modifying enterprise agreement or circumventing arbitral jurisdiction of FWC to resolve arbitral dispute - dispute in fact unresolved throughout dispute resolution procedure - appeal dismissed - remitted to primary judge for consideration of appropriate relief, if any
Legislation:

Constitution Chapter III

Fair Work Act 2009 (Cth) ss 19, 50, 172, 186, 201, 562, 587, 595, 738, 739, 740

Judiciary Act 1903 (Cth) s 39B

Fair Work Regulations 2009 (Cth) Schedule 6.1

Workers' Compensation Act 1902 (WA)

Cases cited:

Ahmed v Harbour Radio Pty Ltd [2009] FCA 1113; (2009) 180 FCR 313

Atkins v Freight Services Pty Ltd v Fair Work Ombudsman [2017] FCA 1134

Automotive, Food, Metals, Engineering, Printing and Kindred Industries Union v ALS Industrial Australia Pty Ltd [2015] FCAFC 123; (2015) 235 FCR 305

British Russian Gazette & Trade Outlook Ltd v Associated Newspapers Ltd [1933] 2 KB 616

Byrne v Australian Airlines Ltd (1995) 185 CLR 410

Chimimport PLC v G D'Alesio SAS (The Paloa D'Alesio) [1994] 2 Lloyd's Rep 366

Clarence City Council v Commonwealth [2020] FCAFC 134; (2020) 280 FCR 265

Communications, Electrical, Electronic, Energy, Information, Postal, Plumbing and Allied Services Union of Australia v Corke Instrument Engineering (Australia) Pty Ltd [2005] FCA 799

Construction, Forestry, Maritime, Mining and Energy Union v Maersk Crewing Australia Pty Ltd [2019] FWC 1745

Construction, Forestry, Mining, and Energy Union v Australian Industrial Relations Commission [2001] HCA 16; (2001) 203 CLR 645

El-Mir v Risk [2005] NSWCA 215; (2006) 22 BCL 16

Energy Australia Yallourn Pty Ltd v Automotive, Food, Metal, Engineering, Printing and Kindred Industries Union [2017] FCA 1245

Energy Australia Yallourn Pty Ltd v Automotive, Food, Metal, Engineering, Printing and Kindred Industries Union [2018] FCAFC 146; (2018) 264 FCR 342

Ermogenous v Greek Orthodox Community of SA Inc [2002] HCA 8; (2002) 209 CLR 95

Hancock Prospecting Pty Ltd v Rinehart [2017] FCAFC 170; (2017) 257 FCR 442

Hanlon v Refined Sugar Services Pty Ltd [2002] FCA 1395

Josephson v Walker [1914] HCA 68;

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Maersk Crewing Australia Pty Ltd v Construction, Forestry, M... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2021] FCAFC 231
Decision Date

CaseChat Overview and Summary

Maersk Crewing Australia Pty Ltd sought declarations from the Court that the Fair Work Commission (FWC) lacked jurisdiction to make an arbitral award in a dispute over manning levels on vessels. The Construction, Forestry, Maritime, Mining and Energy Union (CFMMEU) opposed the application, asserting that the dispute resolution procedure within the Enterprise Agreement (EA) was followed, and the FWC had jurisdiction. The primary judge dismissed Maersk's application, leading to the appeal. The legal issues involved the interpretation of the terms 'dispute' and 'accord and satisfaction' in the Fair Work Act 2009 (Cth), as well as the enforceability of a separate agreement between Maersk and the CFMMEU. The Court examined whether the separate agreement constituted an accord and satisfaction that could modify the EA or circumvent the arbitral jurisdiction of the FWC.

The Full Court held that the separate agreement between Maersk and the CFMMEU did not resolve the underlying dispute, and therefore, the FWC retained jurisdiction to arbitrate. The Court reasoned that the separate agreement was not intended to create contractual relations that could modify the EA or avoid the arbitral jurisdiction of the FWC. The dispute remained unresolved throughout the dispute resolution procedure. The Court found that the separate agreement was not an accord and satisfaction because it did not settle the underlying dispute. The Court also rejected Maersk's reliance on the Energy Australia decision, which involved the binding effect of an arbitral determination. The Full Court concluded that the separate agreement did not have binding effect.

The appeal was dismissed, and the matter was remitted to the primary judge for consideration of the relief, if any, to which the CFMMEU was entitled on the cross-claim. The Court emphasised the importance of following the dispute resolution procedure within the EA and the role of the FWC in resolving disputes under the agreement. The decision underscored the necessity of adhering to the arbitral process as outlined in the EA and the limitations of private agreements in circumventing the jurisdiction of the FWC.

Orders

Orders of the court

1. The appeal is dismissed.

2. The matter is remitted to the primary judge for consideration of the relief, if any, to which the first respondent is entitled on the cross-claim.

Note: Entry of orders is dealt with in Rule 39.32 of the Federal Court Rules 2011.

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

However, in the view I take, it is not necessary to determine whether the concepts of “valid dispute” and “legally cognisable dispute” in the context of ss 595, 738 and 739 do themselves have validity.The Energy Australia decisions It is important to note that the question in Energy Australia Yallourn was whether there was justiciable controversy of the kind necessary to found the jurisdiction of this Court under s 39B(1)(c) of the Judiciary Act 1903 (Cth), and not the question of whether there was a “dispute” which could, pursuant to ss 595 and 739, be arbitrated by the FWC. In Energy Australia FCA, the primary Judge (Bromberg J) held that this Court did not have jurisdiction to hear and determine a claim for declarations concerning the manner of remuneration of casual employees because there was no justiciable controversy between the parties concerning that question. That was so because the issue had been resolved by an arbitral decision of the FWC pursuant to s 739(4) of the FW Act following the referral by a Union of a dispute pursuant to a dispute resolution procedure which had some, but by no means complete, similarity to cl 10 of the present EA. The dispute concerned the manner of payment of casuals. Energy Australia was a party to the dispute and, in accordance with a provision in the dispute resolution procedure, had agreed to be bound by the arbitral award. Energy Australia later sought to agitate the same issue in its claim for the declarations. Although it had participated without protest in the arbitration, it contended that the FWC had lacked jurisdiction to make the award and thereby sought to avoid the conclusion that, after its making, there could not be a justiciable controversy with respect to the claim. The lack of jurisdiction arose, it contended, because the dispute resolution procedure pursuant to which the FWC had purported to act could be invoked only by employees covered by the enterprise agreement and not by any one of the unions covered by it. This issue was resolved against Energy Australia. In determining that the FWC award precluded a justiciable controversy founding the jurisdiction of the Court from arising, Bromberg J relied on the explanation of the legal consequences of private arbitrations given by Hayne, Crennan, Kiefel and Bell JJ in TCL Air Conditioner (Zhonghan) Co Ltd v The Judges of the Federal Court of Australia (2014) 251 CLR 533:[77]However, if parties do go to arbitration and the arbitrator makes an award, the making of the award has legal significance in respect of the parties' dispute and their rights and liabilities. As the plurality in Dobbs said: "if, before the institution of an action, an award was made, it [the award] governed the rights of the parties and precluded them from asserting in the Courts the claims which the award determined" (emphasis added). In such a case, the arbitrator's award governs the rights of the parties because "[b]y submitting the claims to arbitration, the parties confer upon the arbitrator an authority conclusively to determine them".[78]This gives rise to the general rule that an award made by an arbitrator pursuant to such authority is final and conclusive. Further, the arbitrator's making of an award in exercise of such authority both extinguishes the original cause of action and imposes new obligations on the parties in substitution for the rights and liabilities which were the subject of the dispute referred to arbitration. The former rights of the parties are discharged by an accord and satisfaction. The accord is the agreement to submit disputes to arbitration; the satisfaction is the making of an award in fulfilment of the agreement to arbitrate.[79]It follows that when an arbitral award is enforced by curial process, the obligations sought to be enforced are those which are created by the award in substitution for the rights and liabilities which were the subject of the dispute referred to arbitration. A party may sue on an award as a cause of action or, in some cases, as in this case, seek enforcement of the award pursuant to the IA Act.(Emphasis added and citations omitted)

Ratio Decidendi

Legal Principle Established

The CFMMEU supported the Judge’s approach. In particular, it contended that:(a)it had not been open to the parties to resolve the steward claim in a way which conflicted with the manner in which crewing levels are to be determined under the EA;(b)the requirements of the EA with respect to crewing continued to apply after the July 2018 agreement was made;(c)the reliance of Maersk upon the decision in Energy Australia FCA was misplaced as that case had involved the effect of an arbitral determination with binding effect, and the July Agreement did not have that status; and(d)the steps in the EA dispute resolution procedure had been followed before it made its application to the FWC.Consideration of Ground 1 It is convenient to address first some aspects of s 186(6) and the dispute resolution procedure in cl 10 of the EA.Section 186(6) The evident intention of s 186(6) of the FW Act is to require the persons negotiating enterprise agreements to address the means, suitable to the enterprise in question, by which the FWC or an independent third party can settle disputes about matters arising under the agreement itself or in relation to the NES. It is a recognition that, despite the negotiation of the matters recorded in the enterprise agreement, disputes may arise from time to time which will not be resolved consensually and, in respect of which, it is in the interests of those covered by the agreement, and the public interest, that there be a means of settlement by an independent body. By this means the orderly conduct of industrial relations or, using the expression of Rares and Barker JJ in Energy Australia Full Court at [30], the “restoration and maintenance of industrial harmony” is facilitated. Subject to those negotiating an enterprise agreement providing as a minimum for the matters to which s 186(6) refers, they have considerable flexibility in the procedure which they adopt for themselves for the resolution of disputes. The particular disputes for which s 186(6) requires provision are disputes about “any matter” arising under the enterprise agreement itself or relating to the NES. However, the dispute resolution procedure in an enterprise agreement need not be confined to disputes about matters of this kind. Nor are the disputes to which ss 738 and 739 refer so confined. This is made evident by s 738(b) which indicates, in effect, that s 739 has application if an enterprise agreement includes a term providing a procedure for dealing with disputes, including a term referred to in s 186(6). See also United Firefighters’ Union of Australia v Country Fire Authority [2015] FCAFC 1; (2015) 228 FCR 497 at [247]‑[248]. Thus, depending upon the terms of the enterprise agreement, the matters which may be the subject of disputes may be diverse, although probably subject to the qualification that they pertain to the relationship between the employer(s) and employee(s) covered by the agreement or the relationship between employer(s) and union(s) covered by the agreement – see s 172(1) of the FW Act.