Vendor and Purchaser—Contract of sale—Time—Stipulation—Time not of the essence—Failure of purchaser to tender transfer to purchaser by specified date—Whether vendor thereby entitled to give notice to complete—Whether vendor may give notice when purchaser in breach though not guilty of unreasonable delay.
Decisions
May 11. The following written judgments were delivered: - GIBBS C.J. The facts of this case are set out in the judgment of Mason J. which I have had the advantage of reading. I agree with the conclusion reached by Mason J., and in general with his reasoning, but would state for myself briefly why I consider that the appeal should be dismissed. (at p511)
2. The contract for the sale of the land in question from the appellant to the respondent did not fix any date for completion, and did not contain any stipulation that time should be of the essence of the contract. However, by cl. 4, it was provided that within twenty-eight days from the delivery of the vendor's statement of title the purchaser should at his own expense tender to the vendor for execution the appropriate assurance of the property. The statement of title was delivered on 2 November 1979, but, on 8 February 1980, when the appellant gave to the respondent a notice to complete the contract, the respondent had not tendered a transfer for execution. However, at the hearing at first instance no reliance was placed on the failure of the respondent to tender a transfer. Before the Court of Appeal, the appellant sought to argue that the failure of the respondent to tender a transfer within the time allowed by the contract was a breach of contract which provided sufficient justification for the giving of the notice to complete. Since the facts concerning the failure to comply with cl. 4 were not examined at first instance, and since evidence could possibly have been given that the appellant had waived the non-compliance (as indeed the evidence suggests), thus preventing the appellant's argument from succeeding, the Court of Appeal was correct in holding that it was not open to the appellant to take this point for the first time on appeal. (at p512)
3. It is common ground that if it was not open to the appellant to rely on a breach by the respondent of cl. 4, the appellant was not entitled to give the notice requiring completion of the contract unless the respondent had been guilty of unreasonable delay. In the circumstances of the case, which Mason J. has set out, it is impossible to conclude that the delay on the part of the respondent was unreasonable. (at p512)
4. What I have said is enough to dispose of the case, but the parties have directed argument to the question whether, if the appellant had been able to establish that the respondent was in breach of…
Grounds of appeal
[14] The appellant contends that the primary judge erred in finding that the respondent had discharged the onus of establishing the matters required under the relevant provision.
[15] It was submitted that his Honour failed to give adequate weight to the evidence of the second witness, and that the findings of fact were not reasonably open on the material before the Court.
[16] The respondent, for its part, submits that no error is disclosed, and that the conclusions reached were well within the range of outcomes available to the primary judge.
Consideration
[17] It is convenient to deal first with the question of construction, as the resolution of that issue informs the remaining grounds advanced by the appellant.
[18] For the reasons that follow, we are of the view that the appeal should be allowed in part and the matter remitted for further determination.
Continue reading Louinder v Leis
Sign in free to access the full text
Details
AGLC
Louinder v Leis [1982] HCA 28
Case
[1982] HCA 28
Decision Date
CaseChat Overview and Summary
The High Court of Australia considered a dispute between a vendor and a purchaser concerning a contract for the sale of land. The purchaser failed to tender a transfer to the vendor by a specified date, a date which was not stipulated as being of the essence of the contract. The vendor sought to rely on this failure to issue a notice to complete.
The central legal issue before the Court was whether a vendor is entitled to issue a notice to complete when the purchaser has failed to comply with a contractual stipulation, even if that stipulation is not of the essence and the purchaser has not been guilty of unreasonable delay. The Court also had to determine the circumstances under which a vendor may validly serve a notice to complete on a purchaser.
The Court held that a vendor is not entitled to serve a notice to complete on a purchaser merely because the purchaser has failed to meet a date for performance which is not of the essence. A notice to complete can only be validly served when the time for performance has passed and the party serving the notice is not itself in breach of the contract, and where the other party has failed to perform within a reasonable time or has committed a breach that would justify rescission. The Court reasoned that the right to serve a notice to complete is a mechanism to expedite performance when there has been an unreasonable delay, not a penalty for a minor or non-essential breach.
The appeal was allowed, and the notice to complete was held to be invalid.