Gallo v Chief Executive, Department of Environment and Resource Management

Link copied
Case Copied 82 min read

LAND APPEAL COURT OF QUEENSLAND

CITATION:  Gallo v Chief Executive, Department of Environment & Resource Management  [2013] QLAC 6
PARTIES: Filomena, Francesco Ralph and John Peter Gallo
(appellants)
v.

Chief Executive, Department of Environment & Resource Management
(respondent)

FILE NO:

Appeal No. LAC005-12
Land Court No. WAA021-07

DIVISION: Land Appeal Court of Queensland
PROCEEDING: Appeal
ORIGINATING COURT: Land Court of Queensland
DELIVERED ON: 6 December 2013
DELIVERED AT: Cairns

HEARD AT:

DATE OF HEARING:

Cairns

21 March 2013

THE COURT

Henry J
CAC MacDonald, President of the Land Court  
MD Evans, Member of the Land Court

Joint reasons for judgment of Henry J and MacDonald P.  Separate reasons of Mr Evans, concurring as to the orders made.

ORDER:

1.     The appeal is allowed.

2.     The respondent is ordered to grant a licence to take 267 megalitres of water per water year, such licence to be for a stated term and subject to the imposition of appropriate conditions as to the monitoring and management of the licence, the term and conditions to be agreed, or failing agreement to be determined by the Land Court. 

3.     The parties are to meet and seek to negotiate an agreed term and conditions as to the monitoring and management of the licence, within 42 days of the date of this decision.

4.     The parties are to jointly advise this Court of the outcome of these negotiations by no later than 4.00 pm on Friday, 17 January 2014.

5.     In the event that the parties are not able to reach agreement as to the term of the licence and its conditions, the matter is remitted to the Land Court for determination of the term and conditions. 

6.     Any submissions seeking costs are to be filed and served by 4.00pm on Friday, 20 December 2013.

7.     Any submissions in response to such application are to be filed and served by 4.00pm on Friday, 17 January 2014.

CATCHWORDS:

WATER - water licences - three-way regulatory scheme : Water Act 2000, Water Resources Plan, resources operations plan - statutory criteria for deciding applications - relevant date to apply criteria - need to consider existing entitlements.

PRACTICE AND PROCEDURE - appeal to Land Appeal Court - nature of appeal, rehearing - need to prove factual, legal or discretionary error - decision governed by law and facts at date of decision.

STATUTORY INTERPRETATION - Acts Interpretation Act s 20 - accrued rights - presumption displaced by contrary statutory intent - such present here - resources plan pre 2009 amendment to apply.

WORDS AND PHRASES - "additional information" - not a technical phrase - context and Act as a whole suggests ordinary meaning to apply. 

PRACTICE AND PROCEDURE - appeal to Land Court (under Water Act) - nature of appeal - appeal de novo - to hear matter afresh - can admit fresh evidence.

EVIDENCE - direct evidence - inferences - Court not limited to consider "direct" evidence only - inferences permissible from evidence of expert witness - equity and…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Gallo v Chief Executive, Department of Environment and Resou... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details

Case
[2013] QLAC 6
Decision Date

CaseChat Overview and Summary

The case of Gallo v Chief Executive, Department of Environment and Resource Management involves a dispute over the granting of a water licence for the Barron River. The applicants, Gallo and Williams, sought a licence to take water from the Barron River, which was opposed by the Chief Executive. The case was initially heard by the Land Court, which rejected the applicants' application, and the applicants appealed to the Land Appeal Court. The applicants argued that the Land Court erred in its assessment of the proposed use of the water and in its consideration of the relevant conversion rate. The Chief Executive, on the other hand, argued that the Land Court's decision should be upheld and that the applicants had not provided sufficient evidence of the proposed use of the water.

The court had to decide several legal issues, including whether the Land Court erred in its assessment of the proposed use of the water, whether the Land Court erred in its consideration of the relevant conversion rate, and whether the applicants had provided sufficient evidence of the proposed use of the water. The court also had to consider the nature of the appeal and the evidence that could be admitted. The court found that the Land Court had erred in its assessment of the proposed use of the water and in its consideration of the relevant conversion rate. The court also found that the applicants had provided sufficient evidence of the proposed use of the water, and that the Land Court had erred in law by not considering that evidence.

The court's reasoning was based on a purposive interpretation of the relevant statutory provisions, which required the court to consider the statutory criteria for deciding applications at the relevant date. The court found that the relevant date was the date of the decision, rather than the date of the hearing or the application. The court also found that the applicants had a right to a decision on their application, but that this did not entitle them to the continued application of the same procedural provisions that would or should have informed the calculation of volumetric conditions which could have been imposed as part of the making of the initial decision. The court also found that the evidence from the expert witness was properly admitted, even though it may have been considered hearsay.

The court allowed the appeal and ordered the Chief Executive to grant a licence to take 267 megalitres of water per water year, subject to the imposition of appropriate conditions as to the monitoring and management of the licence. The term and conditions of the licence were to be agreed upon by the parties, or failing agreement, to be determined by the Land Court. Any submissions seeking costs were to be filed and served by a specified date, and any submissions in response to such application were to be filed and served by another specified date.

Orders

Orders of the court

1. The appeal is allowed.

2. The respondent is ordered to grant a licence to take 267 megalitres of water per water year, such licence to be for a stated term and subject to the imposition of appropriate conditions as to the monitoring and management of the licence, the term and conditions to be agreed, or failing agreement to be determined by the Land Court.

3. The parties are to meet and seek to negotiate an agreed term and conditions as to the monitoring and management of the licence, within 42 days of the date of this decision.

4. The parties are to jointly advise this Court of the outcome of these negotiations by no later than 4.00 pm on Friday, 17 January 2014.

5. In the event that the parties are not able to reach agreement as to the term of the licence and its conditions, the matter is remitted to the Land Court for determination of the term and conditions.

6. Any submissions seeking costs are to be filed and served by 4.00pm on Friday, 20 December 2013.

7. Any submissions in response to such application are to be filed and served by 4.00pm on Friday, 17 January 2014.

Background

Background to the litigation

Evidence

Evidence before the court

We also note that in De Tournouer, the Land Court[21] the Land Appeal Court[22] and the Court of Appeal[23] all took into account the additional evidence given on behalf of the appellant before the Land Court as to the proposed use of the water applied for. Admittedly, this particular submission does not appear to have been raised in that case, but, if it is correct, it is surprising that it was not raised before any of the Courts given the course of that litigation. In any event, it is clear that the Court of Appeal considered both the application and the evidence given before the Land Court. For example, Fraser JA said:[24]"None of that justified an inference that the water allocation would be efficiently used. As I have mentioned, that topic was simply not addressed in any meaningful way in the application or in the evidence." (emphasis added)[21] De Tournouer v Chief Executive, Department of Natural Resources and Water (2008) QLC 15. [22] De Tournouer v Department of Natural Resources and Water (2009) 30 QLCR 150. [23] De Tournouer v Department of Environment and Resource Management [2011] 1 QdR 200. [24] De Tournouer v Department of Environment and Resource Management [2011] 1 QdR 200 at 210 [26]. It follows that we consider that the whole of the evidence before the Land Court is available for consideration by this Court in this appeal. In support of his submission that the Land Court had erred in law in determining that there was no statement by the appellants of the proposed use of any allocated water, counsel for the appellant submitted that:· Part E (not Part F) of the appellants' application form did identify the purpose for which the water is to be used. Part E had been completed by Mr Gallo by ticking the boxes, "domestic", "stock watering" and "irrigation" as proposed uses. The licence issued by the chief executive similarly identified the "authorised purpose" as irrigation, stock, domestic supply.· Further, Exhibit 21 (Mr Sutherland's report) provided comprehensive evidence, by way of additional information, as to the proposed use of the water. Counsel pointed to numerous examples, in Exhibit 21, of Mr Sutherland's use of the word "proposed" in relation to the use of the water. He also pointed to such examples in the joint experts’ statement (appended to the report) and in Appendix 4 to Mr Sutherland's report - Crop Water Resource Plan ("CWRP").Counsel for the respondent submitted that:· The information required by Part F of the application form, which had largely been left blank by the appellants, was connected with the requirement in s 57(2)(b) of the Barron Plan to address the efficiency of the proposed water use practices. Mr Sutherland's evidence did not assist because, as correctly characterised by the Land Court, Mr Sutherland's evidence was as to what could hypothetically or theoretically be produced. It did not show the appellants' proposals as to the efficient water use at the time they made the application.· The appellants' failure to give evidence before the Land Court, in the face of the Court of Appeal decision in De Tournouer, allowed an inference to be drawn that - (a)the appellants had not developed proposed water use practices, as required by s 51(2)(b) of the Barron Plan; and/or (b)the purpose of the application was to obtain close to the legally maximum use possible allocation of water, regardless of the efficiency of that use.· The appellants' focus on the "proposed" use of the water was incorrect. The statutory test includes and requires an assessment of the efficiency of the proposed water use practices.

Decision

Reasons for decision

However, the application of s 53 to pre-existing appeals is qualified by s 66 of the Barron Plan[9] which provides that:[9]Section 66 was inserted as a transitional provision by s 20 of Water Resources (Barron) Amendment Plan (No 1) 2009. "66 Appeals against particular decisions(1)Subsection (2) applies if - (a) before the commencement, an interested person has appealed under chapter 6 of the Act against a review decision to grant in part an application for or about a water licence that had the effect of increasing the volume of water taken in subartesian management area B; and (b) the appeal has not been decided before the commencement.(2)For deciding the appeal, part 6 as in force immediately before the commencement continues to apply.(3)In this section - The law to be applied by an appeal court depends on the nature of the appeal proceedings, which in turn depends on the statutory provisions which establish the right of appeal. The right to appeal to this Court is conferred by s 64 of the Land Court Act 2000 which provides that a party to a proceeding may appeal to the Land Appeal Court against all or part of the decision of the Land Court. Section 56 of the Land Court Act provides that an appeal to the Land Appeal Court must be decided on the evidence on the record of the proceeding in which the decision appealed against was made, although the Land Appeal Court may admit new evidence in limited circumstances. Section 57 of the Land Court Act empowers the Land Appeal Court to do one more of the following: "(a) suspend the operation of the Land Court's decision and remit the matter, with or without directions, to the court or tribunal that made the decision to act according to law; (b) affirm, amend, or revoke and substitute another order or decision for the order or decision appealed against; (c) make an order the Land Appeal Court considers appropriate." The effect of these provisions is that an appeal to this Court is by way of re-hearing which, as there was no application to adduce new evidence in this case, is to be decided on the record of the proceedings in the Land Court.[10] [10]De Tournouer v Chief Executive, Department of Environment and Resource Management [2011] 1 QdR 200 [20], 206 207 [22]. Although the Land Appeal Court may, by s 57(c) make an order it "considers appropriate", to succeed in an appeal of this nature, the appellants must ordinarily establish that the lower Court's decision resulted from factual, legal or discretionary error.[11] In Coal and Allied Operations Pty Limited v Australia Industrial Relations Commission[12], the majority said - "Ordinarily, if there has been no further evidence admitted and if there has been no relevant change in the law, a court or tribunal entertaining an appeal by way of rehearing can exercise its appellate powers only if satisfied that there was an error on the part of the primary decision maker. That is because statutory provisions conferring appellate powers, even in the case of an appeal by way of rehearing, are construed on the basis that, unless there is something to indicate otherwise, the power is to be exercised for the correction of error."[11]De Tournouer v Chief Executive, Department of Environment and Resource Management [2011] 1 QdR 200, 207 [22]; comp Re Coldham & Others; Ex Parte Brideson [No.2] (1990) 170 CLR 267 (where the Commission was empowered "to take further evidence" and had power to "make such order as it thinks fit") distinguished in Coal and Allied Operations Pty Limited v Australian Industrial Relations Commission (2000) 203 CLR 194, 204 [16].[12] (2000) 203 CLR 194, 203, 204 [14].

Ratio Decidendi

Legal principle established

The argument in support of such a departure is "rights" based. In effect it is that if an application for a water licence is successful the applicant has a right to a water licence conditioned according to the system in place at the time the licence was applied for. Such an argument relies upon the application of s 20 of the Acts Interpretation Act 1954 (Qld) which relevantly provides:"20 Saving of operation of repealed Act etc. … (2) The repeal or amendment of an Act does not - …(c) affect a right, privilege or liability acquired, accrued or incurred under the Act; or …(e) affect an investigation, proceeding or remedy in relation to a right, privilege, liability or penalty mentioned in paragraph (c) or (d).(3) The investigation, proceeding or remedy may be started, continued or completed, and the right, privilege or liability may be enforced and the penalty imposed, as if the repeal or amendment had not happened." That provision applies to the ROP.[55] If an applicant for a licence has any arguable entitlement in the context of s 20 it would likely be characterised as a right rather than a privilege. What though is the “right” relied upon? It may be accepted for present purposes that an applicant for a licence has a right to a decision on the application, a right to review of it and a right to appeal to the Land Court about it.[56] These processes of decision, review and appeal are all accorded to applicants under the Act. But it does not follow that in the exercise of a "right" of appeal a disappointed applicant can be said to have a "right" to the continued application of the same procedural provisions that would or should have informed the calculation of volumetric conditions which could have been imposed as part of the making of the initial decision. [55] Section 14(1) and Schedule 1, Statutory Instruments Act 1992. [56] See Esber v The Commonwealth (1992) 174 CLR 430, 440. The consideration of an application for a water licence involves the application of a variety of discretionary considerations pursuant to s 210 of the Act. However, an obligation upon the decision-maker to have regard to those considerations does not confer a right in the applicant to have those considerations remain static, to be assessed as they stood at the moment of the application. The fact that a decision maker is entitled to seek further information after the making of the application is inconsistent with the applicant having such a right. The language of s 210 of the Act is also inconsistent with such a right. The change of conversion rate occurred between the hearing in the Land Court and the decision of the Land Court. The learned Member was in effect deciding the matter, for the purposes of s 210, as if he were the chief executive. Section 210 therefore required the Member, "in deciding" whether to grant or refuse the application and in deciding the conditions for the licence, to consider "any water resource plan, [and] resource operations plan that may apply to the licence". On the face of it the water resource plan, which "may apply to the licence" for the purposes of determining the volumetric conditions of the licence, would be that which applied at the time of the making of the decision as to the licence conditions. This is because the time of the decision is the point in time when the licence and the conditions therein would be directed to be granted. That is, it is the conversion rate in the ROP at the time of the making of the decision about the licence conditions rather than at the time of the hearing or earlier that is prima facie relevant.