Supreme Court
New South Wales
Medium Neutral Citation: G&S Engineering Services Pty Ltd v MACH Energy Australia Pty Ltd [2019] NSWSC 407 Hearing dates: 2 & 3 April 2019; further written submissions 5 and 9 April 2019 Decision date: 11 April 2019 Jurisdiction: Equity - Technology and Construction List Before: Stevenson J Decision: Interlocutory injunction to be granted
Catchwords: EQUITY – equitable remedies – injunctions – interlocutory injunction – whether defendant should be restrained from calling on security surety bonds – whether serious question to be tried that bonds should be returned – whether serious question to be tried that neither first nor second defendants entitled to have recourse to surety bond
CONTRACTS – construction – purpose of security bonds – whether a risk allocation device – whether recourse to security bonds available before dispute under contract determinedCases Cited: Anaconda Operations Pty Ltd v Fluor Daniel Pty Ltd [1999] VSCA 214
Barclay Mowlem Construction Ltd v Simon Engineering (Aust) Pty Ltd (1991) 23 NSWLR 451
Birstar Pty Ltd v Proprietors “Ocean Breeze” Building Units Plan No 4745 [1997] 1 Qd R 117
BP Refinery (Westernport) Pty Ltd v Hastings Shire Council (1977) 180 CLR 266
Clough Engineering Ltd v Oil & Natural Gas Corporation Ltd [2008] FCAFC 136; (2008) 249 ALR 458
CPB Contractors Pty Ltd v JKC Australia Lng Pty Ltd (No 2) [2017] WASCA 123
Eddy Lau Constructions Pty Ltd v Transdevelopment Enterprise Pty Ltd [2004] NSWSC 273
Farleigh Investments Pty Ltd v Reefking Pty Ltd [2002] WASC 115
Fletcher Construction Australia Ltd v Varnsdorf Pty Ltd [1998] 3 VR 812
Life Insurance Co of Australia Ltd v Phillips (1925) 36 CLR 60; [1925] HCA 18
Lucas Stuart Pty Ltd v Hemmes Hermitage Pty Ltd [2010] NSWCA 283
Reed Construction Services Pty Ltd v Kheng Seng (Australia) Pty Ltd (1999) 15 BCL 158
Saipem Australia Pty Ltd v GLNG Operations Pty Ltd (No 2) [2016] 1 Qd R 254; [2015] QSC 173
SMA Solar Technology AG v Beyond Building Systems Pty Ltd (No 5) [2012] FCA 1483Texts Cited: Practice Note SC Eq 3 Category: Principal judgment Parties: G&S Engineering Services Pty Ltd (First Plaintiff)
DRA Pacific Pty Ltd (Second Plaintiff)
MACH Energy Australia Pty Ltd (First Defendant)
MACH Mount Pleasant Operations Pty Ltd (Second Defendant)
JCD Australia Pty Ltd (Third Defendant)Representation: Counsel:
Solicitors:
M Christie SC with D Hume and B Wacker (Plaintiffs)
D T Miller SC with N Simpson (Defendants)
Jones Day (Plaintiffs)
Corrs Chambers Westgarth (Defendants)
File Number(s): SC 2019/71358
Judgment
-
On 10 March 2017 the plaintiffs, G&S Engineering Services Pty Ltd and DRA Pacific Pty Ltd (“the Contractors”) entered a contract entitled “Mount Pleasant Project Design and Construct Contract” with the first defendant, MACH Energy Australia Pty Ltd to carry out “Works” relating to a coal handling and preparation plant and train load out facility for a coal mine in the Hunter Valley. In the Contract, MACH Energy was named as “the Company”.
-
On 14 August 2018, the second defendant,…
Keep reading for free
Create a free CaseChat account to read G&S Engineering Services Pty Ltd v MACH Energy Australia Pty... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Find similar cases
Other decisions on the same topics. Each opens in a new tab.
Details
- Case
- [2019] NSWSC 407
- Decision Date
CaseChat Overview and Summary
The primary legal issues revolved around the construction of the security bonds and the allocation of risks between the parties. G&S Engineering Services argued that the surety bonds were intended as a risk allocation device, and that recourse to them was not available until the dispute under the contract was determined. The defendants contended that the bonds were available for recourse regardless of the outcome of the underlying dispute.
The court found that the purpose of the surety bonds was to provide a measure of security in case of default, and not solely as a risk allocation device. The court also determined that recourse to the surety bonds could be available before the dispute under the contract was finally determined. Given these findings, the court held that there was no serious question to be tried that the surety bonds should be returned, nor that neither of the other defendants were entitled to have recourse to them. Consequently, the application for an interlocutory injunction was dismissed.
The final orders of the court were that G&S Engineering Services' application for an interlocutory injunction was dismissed, with no orders as to costs.
Background
Background to the litigation
Decision
Reasons for decision
Ratio Decidendi