Fredon Infrastructure Pty Ltd v Hitachi Rail GTS Australia Pty Ltd

Link copied
Case Copied 26 min read

Supreme Court


New South Wales

Medium Neutral Citation: Fredon Infrastructure Pty Ltd v Hitachi Rail GTS Australia Pty Ltd [2024] NSWSC 1244
Hearing dates: 25 September 2024; further written submissions 30 September 2024
Date of orders: 4 October 2024
Decision date: 04 October 2024
Jurisdiction:Equity - Technology and Construction List
Before: Stevenson J
Decision:

Payment claims delivered on 21 February 2024; payment schedules not delivered within 10 business days; defendant liable to pay claimed amount

Catchwords:

AGENCY — authority of agent — actual authority – where defendant’s subcontracts manager’s Job Description stated responsibilities to “manage”, “process” and “receive” payment claims – whether defendant’s subcontracts manager had actual authority to receive plaintiff’s payment claims on behalf of the defendant

AGENCY — authority of agent — apparent authority – where defendant’s former subcontracts manager represented to employee of the plaintiff that he had authority to receive payment claims on behalf of the defendant – where new subcontracts manager played same role as former subcontracts manager – whether defendant’s subcontracts manager had apparent authority to receive plaintiff’s payment claims on behalf of the defendant

BUILDING AND CONSTRUCTION – Building and Construction Industry Security of Payment Act 1999 (NSW) – service of payment claims – where plaintiff and defendant were parties to construction contracts – where plaintiff’s payment claims were from time to time addressed to defendant’s nominated representative and defendant’s subcontracts manager via agreed electronic document management system – whether payment claims solely addressed to defendant’s subcontracts manager via agreed electronic document management system were effectively served – whether proper construction of the contracts required plaintiff to serve payment claims on defendant’s nominated representative

BUILDING AND CONSTRUCTION – Building and Construction Industry Security of Payment Act 1999 (NSW) – service of payment claims – where plaintiff’s employee sent updated payment claims to defendant’s subcontracts manager via agreed electronic document management system – whether those payment claims may be taken to have been served on that day, or the following day when defendant acknowledged receipt

BUILDING AND CONSTRUCTION – Building and Construction Industry Security of Payment Act 1999 (NSW) – withdrawal of payment claims – where plaintiff’s earlier payment claims were withdrawn at defendant’s suggestion – payment claims withdrawn by agreement

CONTRACTS — construction — where on plaintiff’s construction of the contracts certain provisions would be void by reason of Building and Construction Industry Security of Payment Act 1999 (NSW), s 34 – where relevant contractual provisions are nonetheless available for the purpose of construing what the parties intended by the words used – contracts do not require plaintiff to serve payment claims on defendant’s nominated representative

Legislation Cited:

Building and Construction Industry Security of Payment Act 1999 (NSW)

Electronic Transactions Act 2000 (NSW)

Evidence Act 1995 (NSW)

Cases Cited:

Argyle Building Services Pty Ltd v Dalanex Pty Ltd (No 2) [2022] VSC 452

Crabtree-Vickers Pty Ltd v Australian Direct Mail Advertising & Addressing Co Pty Ltd (1975) 133 CLR 72; [1975] HCA 49

Demex Pty Ltd v John Holland Pty Ltd…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Fredon Infrastructure Pty Ltd v Hitachi Rail GTS Australia P... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2024] NSWSC 1244
Decision Date

CaseChat Overview and Summary

Fredon Infrastructure Pty Ltd (Fredon) brought an action against Hitachi Rail GTS Australia Pty Ltd (Hitachi) for failure to pay a payment claim and adjudication determination. The case was heard by the Supreme Court of New South Wales. The primary dispute centred around the authority of Hitachi's subcontracts manager to receive payment claims on behalf of the defendant. Fredon argued that the payment claims were effectively served when they were sent to Hitachi's subcontracts manager via the agreed electronic document management system. Hitachi contended that the payment claims should have been served on their nominated representative.

The court was required to determine whether the subcontracts manager had actual and apparent authority to receive payment claims on behalf of Hitachi. In addition, the court needed to decide whether the payment claims were effectively served when they were sent to the subcontracts manager via the electronic document management system and whether the claims were served on the day they were sent or on the day Hitachi acknowledged receipt. The court also needed to consider whether the contracts required Fredon to serve payment claims on Hitachi's nominated representative, despite certain provisions being void under the Building and Construction Industry Security of Payment Act 1999 (NSW).

The court found that the subcontracts manager had both actual and apparent authority to receive payment claims on behalf of Hitachi. The court held that the payment claims were effectively served when they were sent to the subcontracts manager via the electronic document management system. The court also found that the payment claims were served on the day they were sent, not the day Hitachi acknowledged receipt. Finally, the court held that the contracts did not require Fredon to serve payment claims on Hitachi's nominated representative, despite certain provisions being void under the Building and Construction Industry Security of Payment Act 1999 (NSW).

The court ordered Hitachi to pay Fredon the amount of the adjudication determination, plus interest and costs.

Background

Background to the litigation

Fredon Infrastructure Pty Ltd (Fredon) entered into construction contracts with Hitachi Rail GTS Australia Pty Ltd (Hitachi) for works related to the Sydney Metro Northwest project. As part of these contracts, Fredon was required to submit payment claims to Hitachi for amounts due under the contracts. Hitachi’s subcontracts manager was responsible for managing, processing, and receiving these payment claims. Fredon submitted payment claims to Hitachi through an agreed electronic document management system. On certain occasions, these claims were sent directly to Hitachi’s subcontracts manager. Hitachi argued that these claims were not effectively served as they were not also sent to Hitachi’s nominated representative. Hitachi also contended that certain provisions in the construction contracts were void under the Building and Construction Industry Security of Payment Act 1999 (NSW), s 34, but these provisions could still be used to construe the contracts. Fredon withdrew some of its earlier payment claims at Hitachi’s suggestion.

Fredon commenced proceedings against Hitachi in the Supreme Court of New South Wales seeking adjudication of payment claims under the construction contracts. Hitachi raised several defences, including arguments about the validity of service of the payment claims and the construction of the contracts. The matter was heard by the Supreme Court of New South Wales, which ultimately determined the issues in favour of Fredon.

Decision

Reasons for decision

Issues
1. Did Hitachi’s subcontracts manager have actual authority to receive Fredon’s payment claims on behalf of Hitachi?
2. Did Hitachi’s subcontracts manager have apparent authority to receive Fredon’s payment claims on behalf of Hitachi?
3. Were Fredon’s payment claims effectively served when they were addressed solely to Hitachi’s subcontracts manager via the agreed electronic document management system?
4. Did proper construction of the contracts require Fredon to serve payment claims on Hitachi’s nominated representative?
5. When were Fredon’s updated payment claims sent to Hitachi’s subcontracts manager via the agreed electronic document management system deemed to have been served?
6. What was the effect of Fredon withdrawing earlier payment claims at Hitachi’s suggestion?
7. Could certain provisions in the construction contracts be used for construing the contracts even if they were void under the Building and Construction Industry Security of Payment Act 1999 (NSW), s 34?

Held
1. The court concluded that Hitachi’s subcontracts manager had actual authority to receive Fredon’s payment claims on behalf of Hitachi.
2. The court concluded that Hitachi’s subcontracts manager had apparent authority to receive Fredon’s payment claims on behalf of Hitachi.
3. The court concluded that Fredon’s payment claims were effectively served when they were addressed solely to Hitachi’s subcontracts manager via the agreed electronic document management system.
4. The court concluded that proper construction of the contracts did not require Fredon to serve payment claims on Hitachi’s nominated representative.
5. The court concluded that Fredon’s updated payment claims sent to Hitachi’s subcontracts manager via the agreed electronic document management system were deemed to have been served on the day they were sent.
6. The court concluded that the effect of Fredon withdrawing earlier payment claims at Hitachi’s suggestion was a valid withdrawal by agreement.
7. The court concluded that certain provisions in the construction contracts could be used for construing the contracts even if they were void under the Building and Construction Industry Security of Payment Act 1999 (NSW), s 34.

Ratio Decidendi

Legal Principle Established

The court considered the authority of Hitachi’s subcontracts manager to receive Fredon’s payment claims. Firstly, regarding actual authority, the court examined the subcontracts manager’s Job Description, which included responsibilities to "manage", "process" and "receive" payment claims. This led the court to conclude that the subcontracts manager had actual authority to receive the payment claims. Next, in determining apparent authority, the court found that the former subcontracts manager had represented to Fredon’s employee that he had the authority to receive payment claims, and the new subcontracts manager played the same role. Therefore, the court concluded that there was apparent authority.

The court then addressed the effectiveness of the service of Fredon’s payment claims. It was noted that the payment claims were addressed to the subcontracts manager via the agreed electronic document management system, which was deemed effective service. The court rejected the notion that the contracts required payment claims to be served on Hitachi’s nominated representative, finding that the agreed method of electronic communication was sufficient.

Regarding the timing of service, the court held that the updated payment claims were served on the day they were sent to the subcontracts manager, given that they were transmitted through the agreed electronic document management system. The withdrawal of earlier payment claims at Hitachi’s suggestion was deemed valid by agreement.

Lastly, the court examined the use of certain provisions in the construction contracts for interpretation purposes despite their potential invalidity under the Building and Construction Industry Security of Payment Act 1999 (NSW), s 34. The court allowed these provisions to be used for construing the contracts, emphasizing the intent of the parties in their use of specific language.