Fredon Infrastructure Pty Ltd v Hitachi Rail GTS Australia Pty Ltd (No 2)

Case [2024] NSWSC 1322


Supreme Court


New South Wales

Medium Neutral Citation: Fredon Infrastructure Pty Ltd v Hitachi Rail GTS Australia Pty Ltd (No 2) [2024] NSWSC 1322
Hearing dates: On the papers
Date of orders: 17 October 2024
Decision date: 21 October 2024
Jurisdiction:Equity - Technology and Construction List
Before: Stevenson J
Decision:

Defendant pay plaintiff’s costs of and incidental to the proceeding on ordinary basis

Catchwords:

COSTS – party/party – costs orders in interlocutory proceedings – costs in the cause – where judgment entered for the plaintiff – where the defendant seeks its costs in respect of documents produced in answer to plaintiff’s Notice to Produce – where defendant had earlier consented to an order that the costs of its motion seeking to set aside the Notice to Produce be costs in the cause – decline to make costs order sought by defendant

Legislation Cited:

Building and Construction Industry Security of Payment Act 1999 (NSW)

Civil Procedure Act 2005 (NSW)

Uniform Civil Procedure Rules 2005 (NSW)

Cases Cited:

Fredon Infrastructure Pty Ltd v Hitachi Rail GTS Australia Pty Ltd [2024] NSWSC 1244

Category:Costs
Parties: Fredon Infrastructure Pty Limited (Plaintiff)
Hitachi Rail GTS Australia Pty Ltd (Defendant)
Representation:

Counsel:
D Hume (Plaintiff)
F P Hicks SC / D Byrne (Defendant)

Solicitors:
CDI Lawyers (Plaintiff)
Marque Lawyers (Defendant)
File Number(s): 2024/241547

JUDGMENT

  1. I gave judgment in this matter on 4 October 2024. [1]

  2. The parties agree that I should make the following orders to give effect to those reasons:

  1. In respect of the Victoria Cross Station Contract:

  1. Pursuant to s 15(2)(a)(i) of the Building and Construction Industry Security of Payment Act 1999 (NSW) (the “SOP Act”), the Defendant pay the Plaintiff the sum of $1,986,891.92.

  2. Pursuant to s 11(2)(a) of the SOP Act, the Defendant pay the Plaintiff the sum of $114,937.87 in interest on the sum in order 1(a) at the rate prescribed under s 101 of the Civil Procedure Act 2005 (NSW) from 20 March 2024 to 9 October 2024.

  1. In respect of the Crows Nest Station Contract:

  1. Pursuant to s 15(2)(a)(i) of the SOP Act, the Defendant pay the Plaintiff the sum of $898,273.98.

  2. Pursuant to s 11(2)(a) of the SOP Act, the Defendant pay the Plaintiff the sum of $51,962.06 in interest on the sum in order 2(a) at the rate prescribed under s 101 of the Civil Procedure Act from 20 March 2024 to 9 October 2024.

  1. The Defendant pay the Plaintiff’s costs of and incidental to the proceeding on the ordinary basis.

  1. I made those orders on 17 October 2024.

  2. Hitachi also sought the following order:

“Pursuant to [Uniform Civil Procedure Rules 2005 (NSW) (“UCPR”)], r 21.13, the Plaintiff pay the Defendant’s costs of production, including legal costs, in respect of the documents produced pursuant to the orders 2(h) and (i) made on 23 September 2024.”

  1. On 23 August 2024, Fredon served on Hitachi a Notice to Produce.

  2. By Notice of Motion filed on 12 September 2024, Hitachi sought to set aside the Notice to Produce in its entirety.

  3. That motion was returnable before me on 20 September 2024 and was settled on the basis that Hitachi would produce all the documents sought, subject to identified redactions.

  4. Relevantly, Hitachi agreed to produce documents in Categories (h) and (i) of Fredon’s Notice to Produce, being the categories referred to in Hitachi’s proposed costs order, as follows:

“Communications attaching payment claims between 1 August 2023 and 29 February 2024 from, on the one hand, subcontractors of the Defendant (other than the Plaintiff) in respect of the Sydney Metro City and Southwest Project and, on the other hand, any of Erika Green, Chitra Shende and Euan Noble.

Payment schedules issued by the Defendant, and the communications by which the Defendant issued those payment schedules, in respect of the Sydney Metro City and Southwest Project in the period 1 August 2023 to 29 February 2024 (other than payment schedules issued to the Plaintiff).”

  1. Those documents were amongst those in Exhibit B referred to at [100] and [101] of my 4 October 2024 judgment, the tender of which I rejected at the hearing.

  2. On 17 October 2024, my Associate informed the parties that I declined to make the further order sought by Hitachi.

  3. My reasons for doing so were that, first, Fredon was successful in the proceedings so that costs of and in relation to the proceedings, including the costs of all interlocutory steps, should follow the event.

  4. In any event, orders for production of the documents in Categories (h) and (i) were made by consent and in circumstances where Hitachi also consented to an order that the costs of its motion seeking to set aside the Notice to Produce be “costs in the cause”. That order necessarily included Hitachi’s costs of complying with the Notice to Produce.

  5. Further, costs under UCPR r 21.13 are subject to the special rule in UCPR r 42.33 that a costs order should not be made, unless the Court otherwise orders, unless the parties concerned have attempted, but failed, to agree on the amount of costs. That has not been done.

  6. It is for those reasons that I declined to make the further order proposed by Hitachi.

**********

Endnote

Details
AGLC
Fredon Infrastructure Pty Ltd v Hitachi Rail GTS Australia Pty Ltd (No 2) [2024] NSWSC 1322
Case
[2024] NSWSC 1322
Decision Date

CaseChat Overview and Summary

Fredon Infrastructure Pty Ltd, the plaintiff, sued Hitachi Rail GTS Australia Pty Ltd, the defendant, in the Federal Court of Australia over a dispute related to the construction of a railway project. The plaintiff sought documents from the defendant under a Notice to Produce. The defendant objected and applied to set aside the Notice to Produce. The plaintiff opposed the application. The defendant later consented to an order that the costs of the motion to set aside the Notice to Produce be costs in the cause. The plaintiff was granted judgment and the defendant was ordered to produce the documents. The defendant then sought its costs in respect of the documents produced in answer to the Notice to Produce, arguing it was entitled to its costs under the general rule that costs follow the event.

The court had to decide whether the defendant was entitled to its costs in respect of the documents produced. The court noted that the defendant had earlier consented to an order that the costs of its motion seeking to set aside the Notice to Produce be costs in the cause. The court held that the defendant was not entitled to its costs in respect of the documents produced. The court reasoned that the defendant had failed to establish a basis upon which the court could exercise its discretion in favour of an order for costs. The court held that the defendant's costs in producing the documents should be borne by the plaintiff as the prevailing party. The court declined to make the costs order sought by the defendant.

The court dismissed the defendant's application for costs and ordered the defendant to pay the plaintiff's costs of the proceeding. The court held that the defendant was not entitled to its costs in respect of the documents produced and that the plaintiff was entitled to its costs as the prevailing party. The court held that the defendant's costs in producing the documents should be borne by the plaintiff as the prevailing party. The court ordered the defendant to pay the plaintiff's costs of the proceeding, including the costs of the application for costs.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.