Energex Limited v Alstom Australia Limited

Link copied
Case Copied 76 min read

FEDERAL COURT OF AUSTRALIA

Energex Limited v Alstom Australia Limited [2004] FCA 575

PRACTICE AND PROCEDURE – pleadings – application for summary judgment or strike out of statement of claim – whether allegations under s 82(1) of Trade Practices Act 1974 (Cth) statute barred under s 82(2) – whether cause of action accrues at time agreement to purchase goods entered into, or when loss and damage discovered – whether limitation defence should be dealt with at interlocutory stage – whether allegations under ss 80 and 87 included in order to circumvent limitation period – whether those allegations fail to disclose cause of action, are frivolous or vexatious, or abuse of process – whether failure to plead essential elements of tort of deceit

WORDS & PHRASES – “in trade or commerce” – s 51AC of Trade Practices Act 1974 (Cth) – whether reliance upon limitation defence constitutes conduct in trade or commerce

Trade Practices Act 1974 (Cth) Pt IV and ss 45, 51AC, 80, 82, and 87

ACCC v ABB Transmission and Distribution Limited (2001) ATPR 41-815 referred to
ACCC v ABB Transmission and Distribution Limited (2001) ATPR 41-839 referred to
Gould v Vaggelas (1985) 157 CLR 215 referred to
State of Queensland v Pioneer Concrete (Qld) Pty Ltd (1999) ATPR 41-691 referred to
Wardley Australia Limited v Western Australia (1992) 175 CLR 514 applied
Arcadi v Colonial Mutual Life Assurance Society Ltd (1984) ATPR 40-473 referred to
Sellars v Adelaide Petroleum NL (1994) 179 CLR 332 referred to
Torrens Aloha Pty Ltd v Citibank NA (1997) 72 FCR 581 referred to
Keen Mar Corporation Pty Ltd v Labrador Park Shopping Centre Pty Ltd (1988) ATPR 
40-853 referred to
Australian Iron & Steel Ltd v Hoogland (1962) 108 CLR 471 referred to
Mayne Nickless Ltd v Multigroup Distribution Services Pty Ltd (2001) 114 FCR 108 discussed
Williams v Spautz (1992) 174 CLR 509 referred to
Walton v Gardiner (1993) 177 CLR 378 referred to
James v ANZ Banking Group Ltd (1986) 64 ALR 347 referred to
Karedis Enterprises Pty Ltd v Antoniou (1995) 59 FCR 35 applied
Potts v Miller (1940) 64 CLR 282 referred to
Jobbins v Capel Court Corporation Ltd (1989) 25 FCR 226 referred to
ACCC v CG Verbatis Holdings Pty Ltd (2001) ATPR 41-802 referred to
Multigroup Distribution Services Pty Ltd v TNT Australia Pty Ltd (1996) ATPR 41-522 referred to
Sammy Russo Supplies Pty Ltd v Australian Safeway Stores Pty Ltd (1998) ATPR 41-641 referred to
Western Australia v Wardley Australia Ltd (1991) 30 FCR 245 applied
Marks v GIO Australia Holdings Ltd (1998) 196 CLR 494 referred to
I & L Securities Pty Ltd v HTW Valuers (Brisbane) Pty Ltd (2002) 210 CLR 109 referred to
Cartledge v E Jopling & Sons Ltd [1963] AC 758 discussed
Blacker v National Australia Bank Ltd (2001) ATPR 41-817 referred to
Troulis v Vamvoukakis (unreported, NSW Court of Appeal, 27 February 1998) referred to
Williams v Commonwealth Bank of Australia

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Energex Limited v Alstom Australia Limited and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2004] FCA 575
Decision Date

CaseChat Overview and Summary

Energex Limited has filed a claim against Alstom Australia Limited and other corporate respondents, collectively referred to as the Schneider respondents, alleging a series of unlawful agreements and arrangements, known as the Transformer Arrangement, in the supply of power and distribution transformers. Energex claims that the corporate respondents, under the auspices of the Australian Electrical and Electronic Manufacturers Association Limited, engaged in collusive tendering from 1980 onwards to maintain their market shares. The Schneider respondents have moved to dismiss Energex's claims.

The central legal issues the court had to address were whether the claims were statute-barred under the Limitation Act and whether they disclosed a cause of action. The Schneider respondents argued that the claims were time-barred, while Energex contended that the claims were within the limitation period. The court needed to determine whether the limitation period began to run when the contracts were entered into or when the damages became ascertainable.

The court found that the claims were not statute-barred. It held that the Limitation Act did not commence to run until the damages were ascertainable, which, in this case, was when the successful bids were awarded. The court further found that the claims disclosed a cause of action, as Energex had adequately pleaded the elements of a conspiracy under the Trade Practices Act. The Schneider respondents' motion to dismiss the claims was therefore dismissed. The matter was stood over to determine issues of costs and to give directions for the future conduct of the proceeding.

Orders

Orders of the court

1. The notice of motion filed on behalf of the first, second, third, fourth and fifth respondents on 20 August 2003, and amended on 15 October 2003, be dismissed.

2. The notice of motion filed on behalf of the sixth and seventh respondents, on 20 August 2003, be dismissed.

3. The notice of motion filed on behalf of the sixteenth, seventeenth, eighteenth and nineteenth respondents, on 28 August 2003, be dismissed.

4. The matter be stood over to 16 June 2004 at 9.30 am in order to determine any issue of costs, and to give directions for the future conduct of this proceeding.

Background

Background to the litigation

I shall refer to the sixteenth, seventeenth, eighteenth and nineteenth respondents as “the Schneider respondents”. THE FACTUAL BACKGROUND Energex claims that since about 1980, it, together with others, has engaged in the purchase of electricity transformers from the various corporate respondents. It identifies those from whom it has purchased the transformers as being:·GEC from 1980 to 1989, and Alstom thereafter; ·WTC since 1980; and·ABBPT from 1980 to 1996, and ABBTDL thereafter. In addition, Energex claims that it purchased distribution transformers from ASET from 1980 to 1993, and from Schneider thereafter. Energex claims that there has, at all material times, been a market in Australia for the supply of power and distribution transformers. The purchasers of these transformers have included electricity utilities, and large industrial and mining companies. Energex describes this market as “the transformer market”. Alternatively, it alleges that two separate markets, one for the supply of power transformers, and the other for the supply of distribution transformers, have, at all material times, existed in Australia. Energex claims that there was competition among the corporate respondents in relation to the supply of these transformers. It alleges that, from 1980 onwards, acting under the auspices of Australian Electrical and Electronic Manufacturers Association Limited (“AEEMA”), a company limited by guarantee, and through a Division known as the “Power and Distribution Transformers Division”, the corporate respondents entered into a series of unlawful agreements, arrangements or understandings relating to the supply of transformers. Energex describes these agreements, arrangements or understandings as “the Transformer Arrangement”. The Transformer Arrangement was, in substance, a classic case of collusive tendering. The corporate respondents agreed that they would allocate tenders for the production and supply of transformers among themselves with a view to each of them maintaining their share of sales of power and distribution transformers. They would achieve this object by ensuring that the selected manufacturer submitted a tender at a lower assessed annual value (“AAV”) than the tenders submitted by other manufacturers, or by those manufacturers not submitting a tender. The lower AAV would be achieved by the manufacturers discussing their tenders with each other, thereby ensuring that those tenders yielded a higher AAV than that of the selected manufacturer. Energex sets out in its statement of claim a series of detailed particulars from which the existence of such an agreement, arrangement or understanding is to be inferred. Alternatively, Energex pleads the existence of a “Pre-1993 Power Transformer Arrangement”. The parties to that arrangement are said to have been GEC, WTC and TEC. Energex claims that the arrangement involved those companies agreeing to allocate forthcoming tenders for the production and supply of power transformers amongst themselves with a view to each maintaining its share of sales. The shares of sales to be maintained were 45% to TEC, 32% to GEC, and 23% to WTC. The method by which this would be achieved was essentially the same as for the Transformer Arrangement.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

WEINBERG J

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Established by: WEINBERG J

Full text does not contain this section.