| CITATION: | Doolan v Queensland Building and Construction Commission [2017] QCAT 58 |
| PARTIES: | Sharon Maree Doolan (Applicant) |
| v | |
| Queensland Building and Construction Commission (Respondent) |
| APPLICATION NUMBER: | GAR023-16 |
| MATTER TYPE: | General administrative review matters |
| HEARING DATE: | 6 February 2017 |
| HEARD AT: | Brisbane |
| DECISION OF: | Member Hughes |
| DELIVERED ON: | 28 February 2017 |
| DELIVERED AT: | Brisbane |
| ORDERS MADE: | 1. The Decision of the Queensland Building and Construction Commission dated 16 December 2015 not to issue a Direction To Rectify is confirmed; and 2. The Decision of the Queensland Building and Construction Commission dated 15 July 2016 to decline the claim under the statutory insurance scheme is confirmed. |
| CATCHWORDS: | PROFESSIONS AND TRADES – BUILDERS – STATUTORY POWER TO REQUIRE RECTIFICATION OF DEFECTIVE OR INCOMPLETE BUILDING WORK – HOME WARRANTY INSURANCE STATUTORY TIME LIMIT - where statutory time limit expired – whether Tribunal can extend time – where provision has mandatory precondition to exercise of discretion – where precondition not satisfied – where Tribunal cannot extend time and application must therefore be dismissed CAUSE OF DEFECT - where homeowner did not provide independent expert evidence to support claims – where one Commission expert did not attend for cross-examination – where relying upon evidence of what a party claims an expert said would be contrary to procedural fairness – where weight of evidence did not suggest that builder caused problems BLAMEWORTHINESS – where Commission cannot give ‘Direction To Rectify’ where homeowner has not obtained relevant permission to enable compliance - where not fair to give ‘Direction To Rectify’ where homeowner did not mitigate loss - where evidence suggested homeowner at least contributed to drainage issue by not obtaining neighbour’s permission and not maintaining rubble pit to prevent it being clogged – HOME WARRANTY INSURANCE – where claim outside time limit – whether Tribunal should extend time – where no reasonable explanation for delay Queensland Building and Construction Commission Act 1991 (Qld), s 3, s 72, s 72A | |
Keep reading for free
Create a free CaseChat account to read Doolan v Queensland Building and Construction Commission and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2017] QCAT 58
- Decision Date
CaseChat Overview and Summary
The legal issues before the Court included whether the QBCC could extend the statutory time limit for issuing a 'Direction To Rectify', whether it was fair to issue the direction given the circumstances, and whether the QBCC should have accepted Mr. Doolan’s claim under the statutory insurance scheme. The Court had to consider the statutory preconditions, principles of fairness, and the evidence regarding the cause of the defect and the homeowner's blameworthiness.
The Court held that the QBCC could not extend the statutory time limit as there was a mandatory precondition that was not satisfied. Furthermore, the Court found that it was not fair to issue a 'Direction To Rectify' as Mr. Doolan did not provide independent expert evidence to support his claims, and the evidence did not suggest that the builder caused the problems. The Court also found that Mr. Doolan had not obtained the necessary permissions, had not mitigated his loss, and was aware or should have been aware of the QBCC and its powers. The Court concluded that issuing the direction after such delay would be contrary to the interests of the building industry and consumers. Finally, the Court upheld the QBCC’s decision to decline Mr. Doolan’s claim under the statutory insurance scheme due to the absence of a reasonable explanation for the delay.
The final orders of the Court were to confirm the QBCC's decision not to issue a 'Direction To Rectify' and to decline Mr. Doolan’s claim under the statutory insurance scheme.
Orders
Orders of the court
1. The Decision of the Queensland Building and Construction Commission dated 16 December 2015 not to issue a Direction To Rectify is confirmed; and
2. The Decision of the Queensland Building and Construction Commission dated 15 July 2016 to decline the claim under the statutory insurance scheme is confirmed.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.