Chubb Insurance Company of Australia Ltd v Robinson

Link copied
Case Copied 76 min read

FEDERAL COURT OF AUSTRALIA

Chubb Insurance Company of Australia Limited v Robinson [2016] FCAFC 17

Appeal from: 470 St Kilda Road Pty Ltd v Robinson (2013) 308 ALR 411; [2013] FCA 1420
File number VID 40 of 2014
Judges: FOSTER, ROBERTSON AND DAVIES JJ
Date of judgment: 26 February 2016
Catchwords: INSURANCE – whether, by making a statutory declaration in support of a progress claim for payment under a design and construct contract and by providing that claim and statutory declaration to the proprietor, an executive of the building contractor which made the claim did so “… in rendering … professional services to a third party” (being project management services rendered by the contractor to the proprietor) within the meaning of a professional services exclusion clause in a Directors and Officers insurance policy taken out by the contractor  
Legislation:

Building and Construction Industry Security of Payment Act 2002 (Vic)

Corporations Act 2001 (Cth), s 9

Domestic Building Contracts Act 1995 (Vic), s 8

Evidence Act 1995 (Cth), s 144

Federal Court Rules 2011, rr 15.13(a), 30.01, 30.02

Cases cited:

470 St Kilda Road Pty Ltd v Robinson (2013) 308 ALR 411; [2013] FCA 1420

Australian Casualty Co Ltd v Federico (1986) 160 CLR 513

Bradfield v Federal Commissioner of Taxation (1924) 34 CLR 1

Carr v Inland Revenue Commissioners [1944] 2 All ER 163

CGU Insurance Ltd v Porthouse (2008) 235 CLR 103

Chemetics International Ltd v Commercial Union Assurance Company of Canada (1984) 55 BCLR 60

Darlington Futures Ltd v Delco Australia Pty Ltd (1986) 161 CLR 500

Decor Corporation Pty Ltd v Dart Industries Inc (1991) 33 FCR 397

Ex parte Bucknell (1936) 56 CLR 221

FAI General Insurance Co Ltd v Gold Coast City Council [1995] 2 Qd R 341

Fitzpatrick v Job (2007) 14 ANZ Insurance Cases ¶61-731

GIO General Ltd (t/a GIO Australia) v Newcastle City Council (1996) 38 NSWLR 558

Johnson v American Home Assurance Co (1998) 192 CLR 266

Legal & General Insurance Australia Ltd v Eather (1986) 6 NSWLR 390

Major Engineering Pty Ltd v CGU Insurance Ltd (2011) 282 ALR 363

McCann v Switzerland Insurance Australia Ltd (2000) 203 CLR 579

Samsung Electronics Co Limited v Apple Inc (2011) 217 FCR 238

Selected Seeds Pty Ltd v QBEMM Pty Ltd (2010) 242 CLR 336

Suncorp Metway Insurance Ltd v Landridge Pty Ltd (2005) 12 VR 290

Todd v Alterra at Lloyds Ltd (on behalf of the underwriting members of Syndicate 1400) [2016] FCAFC 15

Vero Insurance Ltd v Power Technologies Pty Ltd (2007) 14 ANZ Insurance Cases ¶61-745

Date of hearing: 8 May 2014
Registry: Victoria
Division: General Division
National Practice Area: Commercial and Corporations
Sub-area: Commercial Contracts, Banking, Finance and Insurance
Category: Catchwords
Number of paragraphs: 168
Counsel for the Appellant: Mr NJ Young QC and Mr PD Herzfeld
Solicitor for the Appellant: Clyde & Co
Counsel for the Respondent: Mr IM Neil SC and Mr AC Harding
Solicitor for the Respondent: Pikes & Verekers Lawyers

ORDERS

VID…
CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Chubb Insurance Company of Australia Ltd v Robinson and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details

Case
[2016] FCAFC 17
Decision Date

CaseChat Overview and Summary

Chubb Insurance Company of Australia Ltd appealed against the decision of the primary judge in the Supreme Court of Victoria, which held that a professional services exclusion clause in a Directors and Officers insurance policy did not apply to a claim for indemnity made by an executive of a building contractor. The central issue was whether the making of a statutory declaration in support of a progress claim for payment under a design and construct contract and the provision of that claim and statutory declaration to the proprietor constituted "rendering professional services to a third party" within the meaning of the exclusion clause. The appeal raised questions about the nature of project management services, the admissibility of expert evidence, and the interpretation of the exclusion clause.

The Court addressed the appeal by first examining the nature of project management services. While the Court accepted that project management could be a recognised discipline, it found that the making of a statutory declaration in support of a progress claim was not inherently a professional service. The Court also considered the admissibility of expert evidence on the nature of project management and found that the evidence provided by Mr Bell, the expert witness, was largely inadmissible as it did not relate to the relevant time period of 2010 or 2011. The Court concluded that the primary judge was correct in holding that the making of the statutory declaration by Mr Robinson was not an act that occurred "in the rendering of services" to St Kilda and that the professional services exclusion did not apply to his claim for indemnity.

The Court further held that the construction of the exclusion clause should be guided by the ordinary and fair meaning of the words used, taking into account the commercial and social purposes of the insurance policy. The Court rejected Chubb's argument that the exclusion clause should be interpreted narrowly and found that the contra proferentem principle did not result in the exclusion being inapplicable. The Court concluded that the primary judge's interpretation of the exclusion clause was correct.

In conclusion, the Court dismissed the appeal and ordered that Chubb pay the respondent's costs of and incidental to the appeal. The Court upheld the primary judge's decision that the professional services exclusion clause did not apply to Mr Robinson's claim for indemnity.

Orders

Orders of the court

1. The appeal be dismissed.

2. The appellant pay the respondent’s costs of and incidental to the appeal.

Background

Background to the litigation

The critical question on appeal, therefore, is whether the professional services exclusion applies to Mr Robinson’s claim for indemnity. THE FACTSThe Design & Construct Contract The Design & Construct Contract (the D&C Contract) is dated 25 October 2010. The contracting parties were St Kilda, as principal, and Reed, as contractor. The Contract Sum provided for in that contract was $39,210,587 (excluding GST). The contract comprised:(a)Formal Instrument of Agreement;(b)General Conditions of Contract and Annexures Part A, B, C, D, E and H;(c)Schedule 1 – Principal’s Project Requirements; (d)Annexures Part F-1 and F-2; and(e)Annexure Part G. The Recitals contained in the Formal Instrument of Agreement provided:A.The Principal is seeking a builder to undertake the redevelopment of the existing 7 storey office building on the Site into a 14 storey residential apartment building, consisting of 173 one and two bedroom apartments and 3 small office suites. The proposed redevelopment fully utilises the existing structure and façade of the building at 470 St. Kilda Road, Melbourne with the additional floors added proposed as steel construction (“the Project”), such work being domestic building work for the purposes of the DBC Act.B.The Contractor has agreed to enter into this Contract with the Principal whereby the Contractor is agreeing to accept full responsibility for the design documents and undertake the performance of WUC in accordance with the Contract. C.The Contractor represents to the Principal that it is experienced in the performance of works similar to the WUC and that it will provide the necessary resources, personnel, skill and expertise required in order to comply with all its obligations in accordance with the Contract. D.The Contractor acknowledges that the Principal has relied upon the representation in Recital C in entering into the Contract and agrees to its engagement on the terms of the Contract.E.The Contractor acknowledges that the provisions to be incorporated in this Contract as a requirement of the DBC Act are so incorporated and the Contractor acknowledges and warrants to the Principal that the Contractor has carefully examined the provisions of that Act. The acronym DBC Act which appeared in Recitals A and E and elsewhere in the D&C Contract was a reference to the Domestic Building Contracts Act 1995 (Vic). The acronym “WUC” which appeared in Recitals B and C is a reference to the work which Reed was obliged to carry out under the D&C Contract. Clauses 1, 2 and 3 of the Operative Provisions of the Formal Instrument of Agreement were in the following terms:OPERATIVE PROVISIONSWhereas:Performance1.The Contractor shall assume full responsibility for the design documents and perform the WUC in accordance with the terms and conditions of this Contract.2.The date that the work is to be completed is defined as the Date for Practical Completion and is 9 December 2011.3.In consideration for the Contractor performing the WUC by the Date for Practical Completion, the Principal shall pay the Contractor the Contract Sum at the times and in the manner set out in the Contract.

Evidence

Evidence before the court

At the time when the primary judge answered the separate question, there had been no adjudication by the Court on the principal claim brought by St Kilda against Mr Robinson. It was not known at that time whether Mr Robinson would be held liable to St Kilda. The Evidence of Mr Bell At the hearing before the primary judge, Chubb called expert evidence from Geoffrey Bell who is an engineer and a director of a construction and engineering consulting firm. Her Honour considered that most of Mr Bell’s report was inadmissible. Her Honour also held that so much of Mr Bell’s report as might be admissible was the subject of oral evidence-in-chief from him. At 424–425 [60]–[61] of the judgment, her Honour said:60In his evidence in chief, Mr Bell, who was subject to some cross-examination, gave evidence that project management involved organising a project so that it was delivered “on time, on budget and in accordance with the specification”. I accept that he was qualified to give expert evidence on this and associated matters. Mr Bell gave evidence that the Project Management Institute, which was based in the United States, had chapters all over the world. His evidence was to the effect that project management related to matters such as time, costs, safety, quality and personnel. His evidence was that a project manager “bring[s] together a range of other people who have responsibility for particular elements of the job [and has] ultimate responsibility for delivery of a project”. It is usual, he said, for project managers to be technically qualified and common for them to seek post-graduate project management qualifications through institutions of higher learning. In re-examination, Mr Bell said that a project manager had usually worked up from “a task like a project engineer” and might have spent “time working in programming or contract administration”. 61 I generally accept the evidence of Mr Bell as set out above. These findings were ultimately not challenged on appeal. However, they are expressed in very general terms and are not related to any particular period of time. They are of only marginal assistance in the resolution of the issue to be determined by this Court. Another Evidentiary Issue At the hearing before the primary judge, Chubb endeavoured to tender a bundle of documents in order to demonstrate that project management is a recognised discipline that should properly be characterised as professional. Chubb placed reliance upon s 144 of the Evidence Act 1995 (Cth). Ultimately, her Honour accepted that particular proof is not required in order to establish knowledge that, in 2013 [our emphasis], the relevant institutions of higher learning offered courses of the kind described in the documents sought to be tendered by Chubb and that the Project Management Institute maintained requirements about the professional competency of its members and advertised through their website a certification program. We consider this material to be of no assistance in resolving the issues raised in this appeal. The evidence was confined to 2013 and did not speak at all to the position in 2010 or 2011. THE CHUBB POLICY

Decision

Reasons for decision

Mr Robinson filed a Notice of Contention on 14 February 2014 upon which he intended to rely in the event that leave to appeal was granted by the Court. That Notice of Contention contained four grounds. By grounds 1 and 2 of his Notice of Contention, Mr Robinson claimed that the primary judge had erred in admitting into evidence the affidavit of Mr Bell, an engineer, and in allowing Mr Bell to give oral evidence at the hearing before her Honour. Both of those grounds were abandoned before the appeal hearing. Thereafter, no issue concerning the admissibility of Mr Bell’s evidence remained. The weight to be given to that evidence continued to be a matter of contest. By grounds 3 and 4 of his Notice of Contention, Mr Robinson sought to argue that the primary judge erred at 427–428 [74] of her Reasons for Judgment (judgment) when she held that the making of the relevant statutory declaration by Mr Robinson was an act that occurred “in the rendering of services” to St Kilda and should have held that it was not such an act at all. This contention raises the true construction of the professional services exclusion clause and can be conveniently addressed when we deal with Chubb’s grounds of appeal. The critical question on appeal, therefore, is whether the professional services exclusion applies to Mr Robinson’s claim for indemnity. THE FACTSThe Design & Construct Contract The Design & Construct Contract (the D&C Contract) is dated 25 October 2010. The contracting parties were St Kilda, as principal, and Reed, as contractor. The Contract Sum provided for in that contract was $39,210,587 (excluding GST). The contract comprised:(a)Formal Instrument of Agreement;(b)General Conditions of Contract and Annexures Part A, B, C, D, E and H;(c)Schedule 1 – Principal’s Project Requirements; (d)Annexures Part F-1 and F-2; and(e)Annexure Part G. The Recitals contained in the Formal Instrument of Agreement provided:A.The Principal is seeking a builder to undertake the redevelopment of the existing 7 storey office building on the Site into a 14 storey residential apartment building, consisting of 173 one and two bedroom apartments and 3 small office suites. The proposed redevelopment fully utilises the existing structure and façade of the building at 470 St. Kilda Road, Melbourne with the additional floors added proposed as steel construction (“the Project”), such work being domestic building work for the purposes of the DBC Act.B.The Contractor has agreed to enter into this Contract with the Principal whereby the Contractor is agreeing to accept full responsibility for the design documents and undertake the performance of WUC in accordance with the Contract. C.The Contractor represents to the Principal that it is experienced in the performance of works similar to the WUC and that it will provide the necessary resources, personnel, skill and expertise required in order to comply with all its obligations in accordance with the Contract. D.The Contractor acknowledges that the Principal has relied upon the representation in Recital C in entering into the Contract and agrees to its engagement on the terms of the Contract.E.The Contractor acknowledges that the provisions to be incorporated in this Contract as a requirement of the DBC Act are so incorporated and the Contractor acknowledges and warrants to the Principal that the Contractor has carefully examined the provisions of that Act. The acronym DBC Act which appeared in Recitals A and E and elsewhere in the D&C Contract was a reference to the Domestic Building Contracts Act 1995 (Vic). The acronym “WUC” which appeared in Recitals B and C is a reference to the work which Reed was obliged to carry out under the D&C Contract.

Ratio Decidendi

Legal principle established

Grounds 1 and 4 to 8 are subsidiary to grounds 2 and 3. They constitute specific challenges to a number of steps in her Honour’s reasoning. Those grounds are more appropriately viewed as arguments rather than as grounds of appeal. Those grounds are in the following terms: 1.The primary judge erred in concluding that project management was not an established and well recognised profession. …4.The judge erred in concluding that the compilation of the accounting records relied upon in making the Statutory Declaration was essentially a routine task necessary for the conduct of Reed’s own business.5.The judge erred in characterising the making of the Statutory Declaration as the mere provision of factual information.6.The judge erred in concluding that the construction of the Exclusion advanced by Chubb would inappropriately circumscribe the cover provided by the D&O Policy.7.The judge erred in concluding that the making of the Statutory Declaration was not in the rendering of professional services within the meaning of the Exclusion.8.The judge erred in concluding that application of the contra proferentem principle would result in the Exclusion’s being inapplicable.CONSIDERATION AND DECISIONConstruction of Insurance Contracts and Exclusion Clauses (General Principles) In McCann at 589 [22], Gleeson CJ said:A policy of insurance, even one required by statute, is a commercial contract and should be given a businesslike interpretation. Interpreting a commercial document requires attention to the language used by the parties, the commercial circumstances which the document addresses, and the objects which it is intended to secure. In the same case, at 600–603 [74], Kirby J reiterated some of the principles which govern the resolution of ambiguities in phrases in commercial contracts, including insurance policies. Of present relevance are the following propositions extracted from [74] in his Honour’s judgment:(a)As a species of commercial contract, an insurance policy must be interpreted to give to the words used their ordinary and fair meaning (Australian Casualty Co Ltd v Federico (1986) 160 CLR 513 (Federico) at 520–521 and at 525); (b)The meaning to be given to an insurance policy must take into account the commercial and social purposes for which it was written (Legal & General Insurance Australia Ltd v Eather (1986) 6 NSWLR 390 at 394 and at 405). The Court is not entitled to make a new contract for the parties which is at odds with the contract upon which they have actually agreed (Johnson v American Home Assurance Co (1998) 192 CLR 266 (Johnson v AHA) at 272 [19]). Maxims and rules of construction, developed as tools to aid the task of interpretation, are subordinate to the primary duty which is to uphold the contract between the parties as properly construed;(c)Notwithstanding the primary duty of courts to give meaning to the words in an insurance policy, it has been recognised that, in cases of ambiguity, a “liberal approach” will generally be adopted in the construction of insurance contracts (Johnson v AHA at 274 [19] and Federico at 520); and(d)In relation to principle 4 articulated by Kirby J, his Honour said: Courts now generally regard the contra proferentem rule (as it is called) as one of last resort because it is widely accepted that it is preferable that judges should struggle with the words actually used as applied to the unique circumstances of the case and reach their own conclusions by reference to the logic of the matter, rather than by using mechanical formulae. Nevertheless, dictionaries, facts and logic alone will sometimes not provide an answer to the contest before the court. In those cases:“it is not unreasonable for an insured to contend that, if the insurer proffers a document which is ambiguous, it and not the insured should bear the consequences of the ambiguity because the insurer is usually in the superior position to add a word or a clause clarifying the promise of insurance which it is offering”.