PLANNING AND ENVIRONMENT COURT OF QUEENSLAND
CITATION:
Charters Towers Operations Pty Ltd v Charters Towers Regional Council [2025] QPEC 12.
PARTIES:
Charters Towers Operations Pty Ltd
ACN 655 026 305(Appellant)
v
Charters Towers Regional Council
(Respondent)
FILE NO:
2544 of 2023
DIVISION:
Planning and Environment
PROCEEDING:
Appeal against refusal.
ORIGINATING COURT:
Planning and Environment Court, Brisbane.
DELIVERED ON:
11 June 2025
DELIVERED AT:
Brisbane.
HEARING DATE:
18 – 21 June 2024. Written submissions received 9 July 2024 and 17 March 2025.
JUDGE:
Byrne KC DCJ
ORDER:
The appeal is adjourned to a date to be determined on the delivery of these reasons, for further review, in light of these reasons.
CATCHWORDS:
ENVIRONMENT AND PLANNING – PLANNING – PLANNING CONTROLS – QUEENSLAND – LOCAL PLANNNG INSTRUMENT – where an appeal lies against the refusal by the respondent of an application for a material change of use – where the application sought approval to construct and operate a non-resident workforce accommodation facility in the rural residential zone as designated in the Charter Towers Town Plan, version 2 – where the application is impact assessable.
ENVIRONMENT AND PLANNING – PLANNING – PLANNING CONTROLS – QUEENSLAND – LOCAL PLANNNG INSTRUMENT – where the planning instrument requires that non-resident workforce accommodation be a temporary use strictly limited to the construction phases of the major project – meaning of temporary - whether the planning instrument requires that the applicant can establish that the facility will supply accommodation to one or more specific projects.
ENVIRONMENT AND PLANNING – PLANNING – PLANNING CONTROLS – QUEENSLAND – LOCAL PLANNNG INSTRUMENT – whether the planning instrument allows a non-resident workforce accommodation facility in the rural residential zone – where issues of social planning, economic need and character and visual amenity are raised by the issues in dispute where some aspects of the application are in conflict with provisions in the planning instrument - whether the application warrants acceptance, in whole or in part and with or without conditions, as an exercise of discretion.
LEGISLATION:
Acts Interpretation Act 1954, ss. 7, 32C.
Planning Act, ss. 45, 60, 65.
Planning and Environment Court Act 2016, ss. 43, 45, 46, 47.
Planning and Environment Court Rules 2018, r. 34.
Planning Regulations 2017, rr. 30, 31.
CASES:
AB v Independent Broad-based Anti-Corruption Commission (2024) 278 CLR 300.
Abeleda v Brisbane City Council and Anor (2020) 6 QR 441.
Acland Pastoral Co Pty Ltd v Rosalie Shire Council [2008] QPELR 342.
Arksmead Pty Ltd v Council of the City of Gold Coast [2001] 1 Qd R 285.
Ausco Modular Pty Ltd v Western Downs Regional Council and Anor [2018] QPELR 80.
Bell v Brisbane City Council & Ors [2022] QPELR 289.
Broad v Brisbane City Council & the Baptist Union of Queensland [1986] 2 Qd R 317.
Clarry & Anor v Brisbane City Council [2024] QCA 39.
Development Watch Inc v Sunshine Coast Regional Council & Anor [2022] QCA 6.
Keep reading for free
Create a free CaseChat account to read Charters Towers Operations Pty Ltd v Charters Towers Regiona... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2025] QPEC 12
- Decision Date
CaseChat Overview and Summary
The central legal issue in this appeal was whether the planning instrument required that non-resident workforce accommodation be a temporary use strictly limited to the construction phases of a major project. The court had to determine the meaning of "temporary" in the context of the planning instrument. Another significant issue was whether the planning instrument allowed a non-resident workforce accommodation facility in the rural residential zone, considering the social planning, economic need, and character and visual amenity issues raised by the application. The court also had to determine if the application warranted acceptance, in whole or in part and with or without conditions, as an exercise of discretion.
The appeal was adjourned to a date to be determined upon the delivery of these reasons. The court provided detailed reasons for the adjournment, indicating that the appeal would be reviewed in light of the reasoning provided. The court considered the planning instrument's requirements, the nature of the proposed accommodation facility, and the relevant social, economic, and visual amenity issues. The outcome of the review will depend on how these factors align with the provisions of the planning instrument and the council's discretion in accepting or rejecting the application.
Orders
Orders of the court
The appeal is adjourned to a date to be determined on the delivery of these reasons, for further review, in light of these reasons.