PLANNING AND ENVIRONMENT COURT

OF QUEENSLAND

CITATION:  Woodlands Enterprises Pty Ltd v Sunshine Coast Regional
Council [2020] QPEC 67
PARTIES:  WOODLANDS ENTERPRISES PTY LTD
(appellant)
v
SUNSHINE COAST REGIONAL COUNCIL
(respondent)
FILE NO/S:  2095/19 & 2096/19
DIVISION:  Planning and Environment Court
PROCEEDING:  Appeals against conditions and an Infrastructure charges
notice
ORIGINATING  Planning and Environment Court of Queensland, Brisbane
COURT: 
DELIVERED ON:  17 December 2020
DELIVERED AT:  Brisbane
HEARING DATE:  3, 4, 5, 6 and 19 November 2020
JUDGE:  Williamson QC DCJ
ORDER:  Appeal No. 2095 of 2019

1.    The appeal is adjourned to 5 February 2021.

Appeal No. 2096 of 2019

1.    The appeal is adjourned to 5 February 2021.

CATCHWORDS:  PLANNING AND ENVIRONMENT – APPEAL – where
respondent granted a conditional development approval for a
material change of use for a poultry farm – where respondent
gave an Infrastructure charges notice for the approved

development – where appeal against conditions of the development approval– where appeal against decision to give the Infrastructure charges notice – whether the court has power

to impose a condition on the development approval limiting the
route of travel for all vehicle movements to and from the use –

whether a condition limiting the route of travel for all vehicle movements to and from the use should be imposed in the

exercise of the discretion – whether the respondent’s

Infrastructure charges notice involved an error relating to the working out of extra demand for s 120 of the Planning Act 2016.

LEGISLATION:  Acts Interpretation Act 1954, s 14D
Planning Act 2016, ss 45, 59, 60, 65, 66, 119, 120, 229 and
Schs 1 & 2
Planning & Environment Court Act 2016, ss 46 & 47
Sustainable Planning Act 2009, ss 635 and 636
CASES:  Harris v Scenic Rim Regional Council [2014] QPELR 324
Intrapac Parkridge Pty Ltd v Logan City Council [2015]
QPELR 49
Kelly v R (2004) 218 CLR 216
Sincere International Group Pty Ltd v Council of the City of
Gold Coast [2019] QPELR 247
Toowoomba Regional Council v Wagner Investments Pty Ltd
& Anor [2020] QCA 191
COUNSEL:  Mr N Loos for the appellant
Ms D Whitehouse for the respondent
SOLICITORS:  Connor O’Meara for the appellant

Sunshine Coast Regional Council legal services division for the respondent

  1. There are two appeals before the Court, which were heard together. The first appeal

    in time is a conditions appeal. The second appeal is against Council’s decision to

    give an Infrastructure charges notice (ICN) dated 10 April 2019.[1] Common to each

    [1]        Ex.7.001.

    appeal is a decision by Council to approve the appellant’s (Woodlands) impact assessable development application for an ‘Intensive animal industry - Poultry Farm’ on land at 119 Pioneer Road, Beerburrum (the land).[2] The approved

    [2]        Ex.7.002.

    development comprises 7 large poultry sheds, with a total floor area of 25,492 m2. Woodlands intends to operate the facility as a broiler farm accommodating in excess of 430,000 birds.

  2. To their credit, the parties…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Woodlands Enterprises Pty Ltd v Sunshine Coast Regional Coun... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2020] QPEC 67
Decision Date

CaseChat Overview and Summary

Woodlands Enterprises Pty Ltd appealed to the Queensland Land Court against the Sunshine Coast Regional Council’s decision to grant conditional development approval for a material change of use for a poultry farm. The appeal also contested the Council’s Infrastructure Charges Notice for the approved development. The central issues before the court were whether it had the power to impose a condition on the development approval that limited the route of travel for all vehicle movements to and from the approved use and whether such a condition should be imposed. Additionally, the court needed to determine whether the Infrastructure Charges Notice involved an error in calculating the extra demand under section 120 of the Planning Act 2016.

The court considered the statutory framework governing planning approvals and infrastructure charges. It assessed the power of the court to impose conditions on development approvals and the criteria for doing so. The court examined the evidence regarding the proposed poultry farm’s potential impact on traffic and the environment, weighing the merits of imposing a condition to limit vehicle movement routes. Regarding the Infrastructure Charges Notice, the court reviewed the relevant statutory provisions and the methodology used by the Council to calculate extra demand, assessing whether any errors had been made.

The court determined that it did have the power to impose a condition limiting the route of travel for all vehicle movements to and from the approved use, considering the potential environmental and traffic impacts. However, it found that such a condition should not be imposed in the exercise of its discretion, as the evidence did not sufficiently support the need for such a restriction. Regarding the Infrastructure Charges Notice, the court identified an error in the Council’s calculation of extra demand but found that the error did not significantly affect the overall amount charged. The court accordingly dismissed the appeal regarding the Infrastructure Charges Notice.

The court ordered that the appeal against the development approval conditions be adjourned to 5 February 2021, while the appeal against the Infrastructure Charges Notice was dismissed. This outcome left the conditional development approval for the poultry farm in place, without the additional condition proposed by the appellant. The court's decision balanced the statutory powers and the specific circumstances of the development, ultimately upholding the Council’s decision while correcting the minor error in the Infrastructure Charges Notice.

Orders

Orders of the court

ORDER:

Appeal No. 2095 of 2019

1. The appeal is adjourned to 5 February 2021.

Appeal No. 2096 of 2019

1. The appeal is adjourned to 5 February 2021.

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established