SUPREME COURT OF QUEENSLAND

CITATION:

Breakwater Pacific Pty Ltd v Chief Executive, Department of Resources [2024] QSC 107

PARTIES:

BREAKWATER PACIFIC PTY LTD

(applicant)

v
CHIEF EXECUTIVE, DEPARTMENT OF RESOURCES

(respondent)

FILE NO/S:

BS 1465 of 2022

DIVISION:

Trial Division

PROCEEDING:

Application

ORIGINATING COURT:

Supreme Court at Townsville

DELIVERED ON:

31 May 2024

DELIVERED AT:

Brisbane

HEARING DATE:

7 and 8 November 2023

Respondent’s supplementary submissions 12 March 2024

Applicant’s final submissions 19 March 2024

Respondent’s submissions in reply 27 March 2024

JUDGE:

Muir J

ORDER:

1.   The Application for judicial review is dismissed.

2.   I will hear the parties as to costs.

CATCHWORDS:

ADMINISTRATIVE LAW – JUDICIAL REVIEW – REVIEWABLE DECISION – UNDER AN ENACTMENT – where the applicant applied to surrender a lease – where the respondent made a decision refusing the application – where the applicant seeks judicial review of the decision – whether the decision made by the respondent was made under an enactment for the purpose of the Judicial Review Act 1991 (Qld)

ADMINISTRATIVE LAW – JUDICIAL REVIEW – REVIEWABLE DECISION – STANDING – where the respondent claims that the applicant has no standing to bring a claim – whether the applicant has standing to seek judicial review of the decision

ADMINISTRATIVE LAW – JUDICIAL REVIEW – GROUNDS OF REVIEW – ERROR OF LAW – where the applicant claims that there was an error of law in the respondent’s decision – whether s16 of the Land Act is applicable to an applicant to surrender a lease.

ADMINISTRATIVE LAW – JUDICIAL REVIEW – GROUNDS OF REVIEW – IRRELEVANT CONSIDERATIONS – RELEVANT CONSIDERATIONS – where the applicant claims that the decision was premised on irrelevant considerations – where the applicant claims that there was a failure to account for relevant considerations – whether s61(2) of the BICA Amendment Act was relevant to the refusal of a surrender application.

ADMINISTRATIVE LAW – JUDICIAL REVIEW – GROUNDS OF REVIEW – NATURAL JUSTICE – where the applicant alleges that the failure to put the views of interested parties before the decision maker constitutes a failure of natural justice.

ADMINISTRATIVE LAW – JUDICIAL REVIEW – GROUNDS OF REVIEW – NO EVIDENCE – where the applicant claims that the decision was based upon the existence of a fact that does not exist – where the applicant claims that the fact was critical to the reasons of the respondent – whether the fact was incorrectly considered.

Acts Interpretation Act 1954 (Qld)

Administrative Decisions (Judicial Review) Act 1977 (Cth), s 5

Coastal Protection and Management Act1995 (Qld), s 3(c), s 4(e), s 124(4)

Judicial Review Act 1991 (Qld), s 20, s 23, s 24, s 30

Land Act1994 (Qld), s 4, s 16, s 327, s 327A, s 327C, s 329
Land Title Act 1994 (Qld), s 27, s 30
Mineral Resources Act 1989 s 318AAV

Ainsworth v Criminal Justice Commission (1992) 175 CLR 564
Argos Pty Ltd v Corbell (2014) 254 CLR 394
Australia Pacific LNG Pty Ltd v The Treasurer,…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Breakwater Pacific Pty Ltd v Chief Executive, Department of... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2024] QSC 107
Decision Date

CaseChat Overview and Summary

The case of Breakwater Pacific Pty Ltd v Chief Executive, Department of Resources involved Breakwater Pacific Pty Ltd applying for judicial review of a decision by the Chief Executive of the Department of Resources to refuse Breakwater's application to surrender its 2012 leases. The court was required to determine whether the Chief Executive's decision was made under an enactment, whether Breakwater had standing to bring the claim, and whether the decision was legally erroneous. The court also considered whether the decision was based on irrelevant considerations, failed to account for relevant considerations, breached natural justice, or was based on no evidence.

The court held that the Chief Executive's decision to refuse the surrender application was not made under an enactment for the purposes of the Judicial Review Act 1991 (Qld). The court found that the decision was merely an anterior decision to refuse to enter into negotiations about the terms of a possible agreement to surrender the leases, and therefore did not affect Breakwater's rights. The court further held that s 16 of the Land Act did not apply to Breakwater's application to surrender the leases, and that the decision was not based on irrelevant considerations or failed to account for relevant considerations. The court also found that the decision did not breach natural justice or was based on no evidence.

The court dismissed the application for judicial review and ordered that the parties would be heard as to costs.

Orders

Orders of the court

1. The Application for judicial review is dismissed.

2. I will hear the parties as to costs.

Background

Background to the litigation

In order to answer these questions, it is first necessary to say more about the 2012 leases and the statutory regimes under which the Refusal Decision and this application for review were made.More about the facts and the relevant statutory provisions The 2006 Agreement Act did a number of things, including relevantly, the following: (a)First: It acknowledged the “very large capital expenditure” and that it was “necessary” to provide “security and assurances” to enable such expenditure (paragraph E), such “titles, rights and privileges” not to be “derogated from by the State in any manner whatsoever except as hereinafter provided” (paragraph G); (b)Second: It confirmed that if the Special Lease was divided into two new leases as anticipated by s 60(1) (essentially for the western and northern revetment rock walls in Lots 796 and 795 respectively) they: A. would “have terms equal to the remaining term of the Special Lease” – so only to 24 March 2015 (s 60(2)(b)); and B. could be transferred to the Lessee’s own nominee, and the State was deemed to approve such transfer (s 60(3)), and the “nominee must be the registered owner of a freehold lot” (s 60(4)).(c)Third: It included s 61 (which related to the Marina Entrance Channel and Marina Basin and not the 2012 Leases) which stated relevantly as follows: “61 Term lease for the Marina Entrance Channel and Marina Basin;(1) If the Special Lease is subdivided and the new lease over new lot 795 and existing lots 676 … and 796 … and leases … are transferred as mentioned in clause 60, the Trustee’s nominee shall be entitled to apply to the State for the grant of a term lease under the Land Act on similar terms in respect of the Marina Basin and Marina Entrance …(2) The term lease for which an application may be made under clause 61(1) is the most appropriate tenure and use of the Marina Basin and Marina Entrance Channel including for the purpose of – (a)section 16 (Deciding appropriate tenure) of the Land Act; and(b)the coastal management plan under the Coastal Protection and Management Act 1995.” The Coastal Protection and Management Act1995 (Qld) has, as one of its four main objects to “ensure decisions about land use and development safeguard life and property from the threat of coastal hazards” (s 3(c)). It achieves its objects by “coordinated and integrated planning and decision-making involving … using other relevant legislation wherever practicable to achieve the objects of this Act” (s 4(e)). Section 124(4) of the Coastal Protection and Management Act provides that the owner of freehold land above the high-water mark and connected to or receiving the benefit of a structure on tidal lands, has a statutory obligation to maintain the structure. The 2012 leases The western revetment wall was subdivided in 2012, with two parts surrendered to the State to become “reserve” and the other two parts (Lots 1 and 2) leased to Breakwater for 10 years under the 2012 leases, with the existing conditions for Breakwater to maintain the wall. At the time, it was expected that Breakwater would transfer the 2012 leases to the adjoining land owners.[6] But as things transpired, this transfer did not happen. Breakwater made the following two points about this fact:(a)First: The rent increased from $8,204 in 2013/2014 to $80,075 in 2021/2022 and, faced with such exorbitant increases, the adjoining land owners refused to agree to the transfer;[7] and(b)Second: Requisition by the “Department” could have properly tethered (by covenant) the title held by the adjoining land owners to the western revetment wall Lots 1 and 2. [6]Apparently in line with the intention in the BIC legislation, the adjoining land owners’ extant obligations under coastal protection legislation, and the obligation to maintain the western revetment walls already included in the Community Management Scheme filed in the Land Registry for Lot 1.[7]In August 2022, with 10 weeks remaining on the term (and 10 weeks prior to the Decision), Breakwater was notified by the respondent that the valuation had reduced by 80% from $901,666 (2021/2022) to $175,833 (2022/2023). But given rent is averaged over three years, Breakwater contended that reduction made no real difference.

Evidence

Evidence Before The Court

Decision

Reasons for decision

In Griffith v Tang, Gummow, Callinan and Heydon JJ relevantly observed as follows:“The determination of whether a decision is ‘made…under an enactment’ involves two criteria: first, the decision must be expressly or impliedly required or authorised by the enactment; and, secondly, the decision must itself confer, alter or otherwise affect legal rights or obligations, and in that sense the decision must derive from the enactment. A decision will only be ‘made… under an enactment’ if both these criteria are met.”[Emphasis added] Their Honours went on to say that “a statutory grant of a bare capacity to contract does not suffice to endow subsequent contracts with the character of having been made under that enactment”; [12] and that “[t]he power to affect the other party’s rights and obligations will be derived not from the enactment but from such agreement as has been made between the parties.”[13] In Griffith v Tang, the High Court also made the following two important points about the enunciated two-limb test:(a)First: it is sufficient that the enactment required or authorises decision from which new rights or obligations arise;[14] and(b)Second: the relevantly affected legal rights do not necessarily have to “owe their existence to the enactment in question” instead “[a]ffected rights or obligations derived from the general law or statute will suffice.”[15] [12]Tang at [82]. See also King v Director of Housing (2013) 23 Tas R 353 at [64].[13]Ibid at [82].[14]Ibid at [89]. [15]Ibid. Limb 1 of Tang As to the first limb of Tang, Breakwater submitted that the application to surrender and the decision to refuse it were both made under the enactment because the surrender of the 2012 leases was statutorily confined to ss 327 and 329 of the Land Act. With the offer of the surrender requiring one-year’s notice. The respondent submitted that the Refusal Decision is no more than an anterior decision to refuse to enter into a negotiation to agree on terms of surrender that might be approved by the chief executive; and therefore, it does not affect the applicant’s rights.[16] This submission was underpinned by the following three propositions: (a)First: The words “affect rights” in the second limb of the Tang test referred to a power to unilaterally affect rights, in contradistinction to a power to enter into some kind of an agreement;[17] and a decision to enter into such an agreement has no effect at all without the agreement of the other party, and it is in fact the agreement of the other party that triggers the effect on rights;[18](b)Second: Section 327A(b) of the Land Act refers to the chief executive’s written approval, and that must mean written approval of what is described in the preceding words of the section - that is, surrender on the terms agreed between the chief executive and the lessee.”; and [19](c)Third: No rights can be affected until the conditions in s 327A of the Land Act are met. One of those conditions is the agreement of terms of surrender between the chief executive and the lessee (Breakwater). And it is that agreement, which is capable of affecting rights, not an anterior decision to not enter into a negotiation about the terms of a possible agreement. [16]Respondent’s written submissions at [20] and [25]. [17]Tang at [80]: “A legislative grant of capacity to contract to a statutory body will not, without more, be sufficient to empower that body to unilaterally to affect the rights or liabilities.”[18]T2-10 ll 1-2.[19]T2-10 l 8.

Ratio Decidendi

Legal Principle Established

Judicial reviews are not concerned with the merits of the determination. The court will not disturb a decision reached “after a careful consideration of the merits of the particular matter and a review of all of the multiplicity of competing submissions advanced.”[52] [52]Save Bell Park Group v Kennedy [2002] QSC 174 per Dutney J at [23], [24] and [26].Relevant mandatory consideration In the present case, the parties could not agree on the relevant considerations the Delegate was required by law to take into account. Breakwater’s primary submission was that the respondent was required to evaluate the most appropriate use and tenure under s16 of the Land Act but instead of doing this, the respondent wrongly:[53](a)premised its decision upon a non-existent and erroneous legislative requirement for a lease to be in place over the land; and (b)failed to identify relevant considerations in favour of the surrender (including who the lessee should be), in order to move to the next evaluative step and balance those considerations against correct countervailing considerations. [53]Applicant’s outline at [2]. On the other hand, the respondent submitted that s 16(1) of the Land Act only contained mandatory considerations for decisions to “allocate land” and not to a case such as the present which involved an application to surrender a lease under s 327C(1). The determination of what considerations a decision‐maker must and, conversely, must not take into account in the exercise of a statutory power is a question of the construction of the statute which created the power, including, if necessary, by implication from the subject matter, scope and purpose of the statute.[54] A consideration will be “relevant” if the decision-maker is required by law to take it into account.[55] A consideration will be “irrelevant” if the decision-maker is prohibited by law from taking the consideration into account.[56] [54]Minister for Aboriginal Affairs v Peko‐Wallsend Ltd (1986) 162 CLR 24 per Mason J at 39–40; Underwood v Queensland Dept of Communities[2013] 1 Qd R 252 per Muir JA, with Dalton J agreeing, at 258–9 [32].[55]Ibid.[56]Ibid. I prefer the respondent’s construction and submissions on this issue. I find that the express terms of s 16(1) of the Land Act could only be mandatory considerations for decisions to allocate land and do not apply as such in this case for the following four reasons: (a)First: Chapter 2 of the Land Act is headed “Land Allocation” and Part 1 of that Chapter provides for “allocation powers”. One of those powers is the power conferred on the Governor-in-Council to grant land in fee simple under s 14. Section 15 provides the power for the Minister to lease unallocated State land. Section 16, also found within Part 1 of Chapter 2 of the Land Act, is headed “deciding appropriate tenure”; (b)Second: The subject of s 16 is made clear by the introductory words of s 16(1), which states: “before land is allocated under this Act”. It follows that this provision is concerned with providing considerations bearing upon decisions as to the allocation of land; (c)Third: Section 16(1) then provides that “the chief executive must evaluate the land to assess the most appropriate tenure and use for the land”. Subsection (2) then provides for a number of considerations that the chief executive must take into account when “conducting the evaluation”; and(d)Fourth: The Refusal Decision was not a decision allocating land but rather is a decision on Breakwater’s application made under s 327C(1) of the Land Act to surrender the leases. The land the subject of the leases had already been allocated. It is only the surrender of the leases that would render that land unallocated.[57] [57]Land Act s 327G.