FEDERAL COURT OF AUSTRALIA
Auguste v Nikolyn Pty Ltd [2016] FCA 1579
Appeal from: File number: WAD 205 of 2016 Judge: MCKERRACHER J Date of judgment: 23 December 2016 Catchwords: HIGH COURT AND FEDERAL COURT – where significant delay in the delivery of judgment following trial – whether delay had an operative effect on the conclusion
CONSUMER LAW – misleading and deceptive conduct – whether representation made – operation of deeming provision in s 51A of the Trade Practices Act 1974 (Cth)
CONTRACTS – building contract – whether implied term of reasonable time – whether work completed within a reasonable time
COSTS – indemnity costs – ulterior motive – groundless contentions – whether award of indemnity costs justified in the circumstances – payment of interest where significant delay in the delivery of judgment
Legislation: Federal Circuit Court Rules 2001 (Cth) r 25
Trade Practices Act 1974 (Cth) ss 51A, 52
Cases cited: Auguste v Nikolyn Pty Ltd [2013] FCCA 1630
Australian Competition and Consumer Commission v Dateline Imports Pty Ltd [2015] FCAFC 114
Caffey v Leatt-Hayter (No 3) [2013] WASC 348
Colgate Palmolive Co v Cussons Pty Ltd (1993) 46 FCR 225
D & Z Constructions Pty Ltd v IHI Corporation [2013] WASC 265
DM Drainage & Constructions Pty Ltd v Karara Mining Ltd [2014] WASC 170
Expectation Pty Ltd v PRD Realty Pty Ltd (2004) (2004) 140 FCR 17
Finishing Services Pty Ltd v Lactos Fresh Pty Ltd [2007] FCAFC 15
Fountain Selected Meats (Sales) Pty Ltd v International Produce Merchants Pty Ltd (1988) 81 ALR 397
Fox v Percy [2003] HCA 22; [2013] 214 CLR 118
Huntley v Department of Police and Justice (NSW) (No 2) [2016] FCCA 146
Laminex (Australia) Pty Ltd v Smeeth [1999] NSWCA 462
Marks v GIO Australia Holdings Ltd (1998) 196 CLR 494
Monie v Commonwealth (2005) 63 NSWLR 729
Mount Lawley Pty Ltd v Planning Commission (WA) (2004) 29 WAR 273
Tattsbet Ltd v Morrow (2015) 233 FCR 46
Date of hearing: 3 October 2016 Registry: Western Australia Division: General Division National Practice Area: Commercial and Corporations Sub-area: Regulator and Consumer Protection Category: Catchwords Number of paragraphs: 145 Counsel for the Appellant: Mr A Rumsley Solicitor for the Appellant: Alan Rumsley Counsel for the Respondents: Ms N Breach Solicitor for the Respondents: D’Angelo Legal ORDERS
WAD 205 of 2016 BETWEEN: ROBERT STEPHEN AUGUSTE
Appellant
AND: NIKOLYN PTY LTD (ACN 078 833 977)
First Respondent
DONATO COLASANTE
Second Respondent
JUDGE:
MCKERRACHER J
DATE OF ORDER:
23 DECEMBER 2016
THE COURT ORDERS THAT:
1.The appeal be dismissed.
2.The appellant pay the costs of the respondents, to be assessed if not agreed.
Note: Entry of orders is dealt with in Rule 39.32 of the Federal Court Rules 2011.
REASONS FOR JUDGMENT
TABLE OF CONTENTS
BACKGROUND
[4]
PRIMARY JUDGMENT
[12]
Reasoning of the primary judge
[27]
GROUNDS OF APPEAL AND NOTICE OF…
Continue reading Auguste v Nikolyn Pty Ltd
Sign in free to access the full text
- AGLC
- Auguste v Nikolyn Pty Ltd [2016] FCA 1579
- Case
- [2016] FCA 1579
- Decision Date
CaseChat Overview and Summary
The legal issues that the court was required to decide were whether there was a delay in the delivery of judgment that had an operative effect on the conclusion, whether there was misleading and deceptive conduct under s 51A of the Trade Practices Act 1974 (Cth), whether there was an implied term of reasonable time in the building contract, and whether the award of indemnity costs was justified in the circumstances. The court found that there was no delay in the delivery of judgment that had an operative effect on the conclusion, and that there was no misleading and deceptive conduct under s 51A of the Trade Practices Act 1974 (Cth). The court also found that there was an implied term of reasonable time in the building contract, and that the award of indemnity costs was justified in the circumstances.
The court's reasoning and outcome were based on the evidence presented and the applicable law. The court found that the primary judge did not deal with material evidence that is directly inconsistent with his findings and relates to issues which go to the very heart of the claim. The court also found that the primary judge's disposition of the respondent's case under s 340(1)(a)(iii) and (b), linked to s 341(1)(b) and (c)(i), of the FW Act cannot stand. The court dismissed the appeal and ordered the appellant to pay the costs of the respondents, to be assessed if not agreed.
In conclusion, the Federal Court of Australia found that there was no delay in the delivery of judgment that had an operative effect on the conclusion, and that there was no misleading and deceptive conduct under s 51A of the Trade Practices Act 1974 (Cth). The court also found that there was an implied term of reasonable time in the building contract, and that the award of indemnity costs was justified in the circumstances. The appeal was dismissed, and the appellant was ordered to pay the costs of the respondents.
Orders
Orders of the court
1. The appeal be dismissed.
2. The appellant pay the costs of the respondents, to be assessed if not agreed.
Note: Entry of orders is dealt with in Rule 39.32 of the Federal Court Rules 2011.
Background
Background to the litigation
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Ratio Decidendi
Legal Principle Established
The purpose of Mr Auguste identifying these matters is to show that the primary judge did not deal with material evidence that is directly inconsistent with his findings and relates to issues which go to the very heart of the claim. Ground 1 – delay – consideration In Tattsbet, the Full Court dealt with a similar complaint about delay in delivery of reasons for judgment. Jessup J, in considering the submission, said the following (Allsop CJ and White J agreeing) (at [131]-[134]):131. The principles which inform the decision of an appellate court to hold that excessive delay in the delivery of judgment at first instance in the case concerned has rendered that judgment unsafe were discussed at length by the Full Court in Expectation Pty Ltd v PRD Realty Pty Ltd [2004] FCAFC 189; (2004) 140 FCR 17, 32-35 [66]-[83]. I would accept that, particularly where a transcript of the evidence at trial exists, mere delay need not justify a conclusion that the fact-finding process has miscarried. There are, however, additional circumstances which give rise to concern in the present case. 132. In Expectation, the Full Court said (at [74]):The problem is not restricted to fading memory. A judge who comes to make an inordinately delayed decision will inevitably be subjected to great pressure to complete and publish the judgment. A conscientious judge could not but feel that pressure. It is almost inevitable that there will also be some form of external pressure - whether from the parties, the management of the Court, the press or parliamentarians. That pressure could well unconsciously affect the process of decision-making and the process of giving reasons for decision. The decision that is easiest to make and express will have great psychological attraction. In the present case, I can see no sign that the primary Judge sought to take the easiest path to the resolution of the disputes that were before him. To the contrary: his Honour gave careful attention to the appellant’s reasons for having taken adverse action against the respondent, notwithstanding that, on his findings, her case failed at an anterior stage. Nonetheless, the pressures to which the Full Court referred in Expectation appear to have been present here. The circumstances which surrounded the delivery of judgment bespeak an environment in which his Honour felt under considerable pressure to complete his reasons at the last minute. 133. Additionally, the omissions to which I have referred above, taken cumulatively, suggest that his Honour may not have given some issues in the case the attention which they deserved, notwithstanding the very long period during which he was reserved. Those arising under s 357 of the FW Act are an instance. His Honour’s failure to make the findings of fact that would be necessary for a proper determination of so much of the respondent’s case as relied on s 340(1)(a)(iii) and (b) of the FW Act are another. On the cross-appeal, our attention was also drawn to a number of minor errors – typographical and proofing errors, for example – in his Honour’s reasons. While nothing would normally turn on such matters, in the circumstances of the present case it must be accepted that they provide some support for the respondent’s second ground. 134. The critical finding with respect to the appellant’s reason or reasons for taking adverse action turned substantially upon the credit which the primary Judge assigned to the evidence of Mr Fletton. Notwithstanding the existence of transcript, that finding was inevitably based upon his Honour’s observation of Mr Fletton as a witness, and upon the advantage which a trial Judge conventionally has in such a setting. In my view, there is a real risk that his Honour compromised his ability to use that advantage in the determination of Mr Fletton’s reasons for acting when he allowed such an inordinate period to elapse between the giving of the evidence and the making of the determination. When considered together with the matters referred to in paras 106-109 above, the result is that his Honour’s disposition of the respondent’s case under s 340(1)(a)(iii) and (b), linked to s 341(1)(b) and (c)(i), of the FW Act cannot stand.(emphasis added)