SUPREME COURT OF VICTORIA
COURT OF APPEAL
No 3852 of 2008
No 3853 of 2008
| A J LUCAS DRILLING PTY LTD (ACN 087 777 455) | Appellant/Plaintiff |
| v | |
| MCCONNELL DOWELL CONSTRUCTORS (AUST) PTY LTD (ACN 002 929 017) | Respondent/Defendant/Cross-Appellant |
---
| JUDGES | REDLICH and DODDS-STREETON JJA and BEACH AJA |
| WHERE HELD | MELBOURNE |
| DATE OF HEARING | 27 and 28 July 2009 |
| DATE OF JUDGMENT | 18 December 2009 |
| MEDIUM NEUTRAL CITATION | [2009] VSCA 310 |
| JUDGMENTS APPEALED FROM | A J Lucas Drilling v McConnell Dowell Constructors (Aust) Pty Ltd (No 1) [2007] VSC 500 (Byrne J) A J Lucas Drilling v McConnell Dowell Constructors (Aust) Pty Ltd (No 2) [2008] VSC 275 (Byrne J) A J Lucas Drilling v McConnell Dowell Constructors (Aust) Pty Ltd (No 3) [2008] VSC 315 (Byrne J) |
---
BUILDING CONTRACTS – Sub-contract determined prior to completion without fault by sub-contractor – Valuation works completed – Pro-rata assessment of contract lump sum to reflect percentage completion of original work scope – Whether trial judge’s valuation was precluded by the construction of relevant clauses in the sub-contract – Variations valued on a cost plus margin basis – Changes to work scope and new methodology – Whether variations under sub-contract – Whether error in not allowing full risk component in pro-rata value – Whether sub-contractor accepted the risks associated with changed methodology and the cost of the re-engineering and its implementation – Valuation of variations to the work scope by the changed methodology – Whether the sub-contractor was entitled to compensation for delay.
PRACTICE AND PROCEDURE – Interest at penalty interest rates pursuant to s 58 Supreme Court Act 1986 – Whether the appellant’s claim was for a sum certain – Whether appellant’s letter constituted a demand – Whether good cause was shown to the contrary.
---
| Appearances: | Counsel | Solicitors |
| For the Appellant | Mr M H Whitten Mr B B Carr | Corrs Chambers Westgarth |
| For the Respondent | Mr D S Levin QC Mr J R Gurr | Deacons |
REDLICH JA
DODDS-STREETON JA
BEACH AJA:
Introduction
This appeal and cross-appeal arise from a dispute over the payment due under a sub-contract between the parties, McConnell Dowell Constructors (Australia) Pty Ltd (‘McDow’) and A J Lucas Drilling Pty Ltd (‘Lucas’). McDow was party to a head contract with BHP Billiton Petroleum Pty Ltd (‘BHPB’) to design and construct certain facilities at the Minerva Gas Field near Port Campbell in Victoria.
The principal issue on appeal is whether, in circumstances where the sub-contract determined prior to completion without fault by Lucas, the trial judge erred in valuing its work done up to that date by applying the sub-contract lump sum of $5 million pro-rata to reflect the percentage completion of the original work scope and adjusting it for variations valued on a costs plus margin basis, which produced a total award of $3,672,925 plus GST. His Honour also awarded Lucas interest running from 23 September 2003 pursuant to s 58 of the Supreme Court Act 1986.
The appellant contended that the trial judge’s valuation methodology was…
Keep reading for free
Create a free CaseChat account to read AJ Lucas Drilling Pty Ltd v McConnell Dowell Constructors (A... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2009] VSCA 310
- Decision Date
CaseChat Overview and Summary
The court examined whether the trial judge's valuation method was consistent with the terms of the sub-contract, particularly in relation to the assessment of variations that were valued on a cost plus margin basis. The court also considered whether the changes to the work scope and the new methodology adopted by the sub-contractor constituted variations under the sub-contract. Additionally, the court deliberated on whether there was an error in the valuation that failed to include the full risk component, and whether the sub-contractor had accepted the risks associated with the changed methodology and the costs involved in re-engineering and its implementation. The court further assessed the valuation of variations to the work scope resulting from the changed methodology and whether the sub-contractor was entitled to compensation for delays.
The court concluded that the trial judge's valuation was correct, and the sub-contract did not preclude a pro-rata assessment of the contract lump sum. The court found that the variations and changes in methodology were not properly categorised as variations under the sub-contract and that the sub-contractor had indeed accepted the risks associated with the new methodology. Therefore, the sub-contractor was not entitled to compensation for delays. In relation to interest, the court determined that the appellant's claim was for a sum certain, and the appellant's letter constituted a demand. The court ruled that no good cause was shown to depart from the penalty interest rates as per section 58 of the Supreme Court Act 1986. The final orders of the court reflected the outcomes of these determinations.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.