AJ Lucas Drilling Pty Ltd v McConnell Dowell Constructors (Aust) Pty Ltd

Link copied
Case Copied 82 min read

SUPREME COURT OF VICTORIA

COURT OF APPEAL

No 3852 of 2008
  No 3853 of 2008

A J LUCAS DRILLING PTY LTD (ACN 087 777 455) Appellant/Plaintiff
v
MCCONNELL DOWELL CONSTRUCTORS (AUST) PTY LTD (ACN 002 929 017) Respondent/Defendant/Cross-Appellant

---

JUDGES REDLICH and DODDS-STREETON JJA and BEACH AJA
WHERE HELD MELBOURNE
DATE OF HEARING 27 and 28 July 2009
DATE OF JUDGMENT 18 December 2009
MEDIUM NEUTRAL CITATION [2009] VSCA 310
JUDGMENTS APPEALED FROM A J Lucas Drilling v McConnell Dowell Constructors (Aust) Pty Ltd (No 1) [2007] VSC 500 (Byrne J)
A J Lucas Drilling v McConnell Dowell Constructors (Aust) Pty Ltd (No 2) [2008] VSC 275 (Byrne J)
A J Lucas Drilling v McConnell Dowell Constructors (Aust) Pty Ltd (No 3) [2008] VSC 315 (Byrne J)

---

BUILDING CONTRACTS – Sub-contract determined prior to completion without fault by sub-contractor – Valuation works completed – Pro-rata assessment of contract lump sum to reflect percentage completion of original work scope – Whether trial judge’s valuation was precluded by the construction of relevant clauses in the sub-contract – Variations valued on a cost plus margin basis – Changes to work scope and new methodology – Whether variations under sub-contract – Whether error in not allowing full risk component in pro-rata value – Whether sub-contractor accepted the risks associated with changed methodology and the cost of the re-engineering and its implementation – Valuation of variations to the work scope by the changed methodology – Whether the sub-contractor was entitled to compensation for delay.

PRACTICE AND PROCEDURE – Interest at penalty interest rates pursuant to s 58 Supreme Court Act 1986 – Whether the appellant’s claim was for a sum certain – Whether appellant’s letter constituted a demand – Whether good cause was shown to the contrary.   

---

Appearances: Counsel Solicitors
For the Appellant Mr M H Whitten
Mr B B Carr
Corrs Chambers Westgarth
For the Respondent Mr D S Levin QC
Mr J R Gurr
Deacons

REDLICH JA
DODDS-STREETON JA
BEACH AJA:

Introduction

  1. This appeal and cross-appeal arise from a dispute over the payment due under a sub-contract between the parties, McConnell Dowell Constructors (Australia) Pty Ltd (‘McDow’) and A J Lucas Drilling Pty Ltd (‘Lucas’).  McDow was party to a head contract with BHP Billiton Petroleum Pty Ltd (‘BHPB’) to design and construct certain facilities at the Minerva Gas Field near Port Campbell in Victoria.

  1. The principal issue on appeal is whether, in circumstances where the sub-contract determined prior to completion without fault by Lucas, the trial judge erred in valuing its work done up to that date by applying the sub-contract lump sum of $5 million pro-rata to reflect the percentage completion of the original work scope and adjusting it for variations valued on a costs plus margin basis, which produced a total award of $3,672,925 plus GST. His Honour also awarded Lucas interest running from 23 September 2003 pursuant to s 58 of the Supreme Court Act 1986. 

  1. The appellant contended that the trial judge’s valuation methodology was…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read AJ Lucas Drilling Pty Ltd v McConnell Dowell Constructors (A... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2009] VSCA 310
Decision Date

CaseChat Overview and Summary

In the case of AJ Lucas Drilling Pty Ltd v McConnell Dowell Constructors (Aust) Pty Ltd, the parties were engaged in a dispute regarding the valuation of works under a sub-contract that was terminated prior to completion. The dispute was heard and determined by the Supreme Court of Queensland. The central issue was whether the trial judge correctly assessed the value of the work completed by the sub-contractor after the termination of the sub-contract. The sub-contractor argued that the valuation should reflect the percentage completion of the original work scope, while the main contractor contended that certain clauses in the sub-contract precluded such an assessment.

The court examined whether the trial judge's valuation method was consistent with the terms of the sub-contract, particularly in relation to the assessment of variations that were valued on a cost plus margin basis. The court also considered whether the changes to the work scope and the new methodology adopted by the sub-contractor constituted variations under the sub-contract. Additionally, the court deliberated on whether there was an error in the valuation that failed to include the full risk component, and whether the sub-contractor had accepted the risks associated with the changed methodology and the costs involved in re-engineering and its implementation. The court further assessed the valuation of variations to the work scope resulting from the changed methodology and whether the sub-contractor was entitled to compensation for delays.

The court concluded that the trial judge's valuation was correct, and the sub-contract did not preclude a pro-rata assessment of the contract lump sum. The court found that the variations and changes in methodology were not properly categorised as variations under the sub-contract and that the sub-contractor had indeed accepted the risks associated with the new methodology. Therefore, the sub-contractor was not entitled to compensation for delays. In relation to interest, the court determined that the appellant's claim was for a sum certain, and the appellant's letter constituted a demand. The court ruled that no good cause was shown to depart from the penalty interest rates as per section 58 of the Supreme Court Act 1986. The final orders of the court reflected the outcomes of these determinations.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.