| IN THE SUPREME COURT OF VICTORIA | Not Restricted | |
AT MELBOURNE
COMMERCIAL AND EQUITY DIVISION
BUILDING CASES LIST
No. 4466 of 2007
| AJ LUCAS DRILLING PTY LTD (ACN 087 777 455) | Plaintiff |
| v | |
| McCONNELL DOWELL CONSTRUCTORS (AUST) PTY LTD (ACN 002 929 017) | Defendant |
---
JUDGE: | BYRNE J | |
WHERE HELD: | Melbourne | |
DATES OF HEARING: | 30 June, 1, 2, 3, 4 July 2008 | |
DATE OF JUDGMENT: | 1 August 2008 | |
CASE MAY BE CITED AS: | Lucas Drilling v McConnell Dowell Constructors (No. 2) | |
MEDIUM NEUTRAL CITATION: | [2008] VSC 275 | |
---
Building Contracts – quantification of claims – assessment of pro-rata completion of contract works – assessment of extra work as a consequence of variation.
Practice and Procedure – preliminary trial of questions – fidelity to litigation process – amendment of pleading – amendment to raise issue which might have been dealt with at preliminary trial – amendment refused.
---
APPEARANCES: | Counsel | Solicitors |
| For the Plaintiff | Mr EN Magee QC, Mr Michael Whitten and Mr Bernard Carr | Corrs Chambers Westgarth |
| For the Defendant | Mr David Levin QC, and Mr JR Gurr | Deacons |
HIS HONOUR:
The parties agreed to structure this proceeding in two trials. The first trial, dealing with all questions other than those as to quantum, was conducted over 16 days in October and November 2007 and I published my judgment in December.[1] The parties have presented further evidence and submissions on the deferred questions and this is my judgment on those questions. In this judgment I adopt the terminology and conclusions of the first judgment.
[1][2007] VSC 500.
Procedural matters
I have expressed criticisms of the pleadings in this case.[2] The deficiencies return to plague this second trial. The claim of Lucas Drilling, as pleaded, included claims for four variations: a variation affecting the drilling work[3]; a variation affecting the diving and associated marine work[4]; the provision of thinsulators to the product line[5]; and additional hydrostatic testing[6]. The last two items, which were for modest sums, were not in issue. There were also claims for delays in paragraph 36 and following but these were deleted, leaving, however, in Schedule D detail of 168.5 days of delay. But these claims for delay were never pursued. Indeed, given that the claim of Lucas Drilling for payment under clause 24 of the sub-contract, was for the value on a cost-plus basis of all its work on the project up to the suspension and termination of its sub‑contract in September 2003, it is difficult to see why or how it made claims for variations at all. Its abandoned claims for delay were not translated into money claims.
[2][2007] VSC 500 at [14], [55].
[3]Statement of Claim paras 22 ff.
[4]Statement of Claim paras 42 ff.
[5]Statement of Claim paras 50 ff.
[6]Statement of Claim paras 55ff.
I return to the two disputed variations. The first arose from the change in the diameter of the casing for the first line from 10 inches to 12 inches to accommodate a larger umbilical bundle that was…
Keep reading for free
Create a free CaseChat account to read A J Lucas Drilling Pty Ltd v McConnell Dowell Constructors (... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2008] VSC 275
- Decision Date
CaseChat Overview and Summary
The legal issues before the court included the assessment of the pro-rata completion of the contract works and the evaluation of the extra work that arose as a consequence of variations. Additionally, the court had to consider whether an amendment to the pleadings was appropriate, given that the issue could have been raised during a preliminary trial. The court was tasked with determining the appropriate quantum of damages owed by the appellant to the respondent.
In its reasoning, the court emphasised the importance of fidelity to the litigation process and the need to adhere to the preliminary trial. The court found that the respondent's proposed amendment to the pleadings, which aimed to raise an issue that could have been dealt with at the preliminary trial, was not permissible. Consequently, the court refused the amendment. The court then proceeded to assess the pro-rata completion of the contract works and the extra work resulting from the variations. Ultimately, the court determined that the respondent was entitled to compensation for the additional work performed.
The court ordered the appellant to compensate the respondent for the extra work performed as a consequence of variations to the contract. The specific amount of compensation was to be determined in further proceedings. The court's decision underscored the importance of adhering to the litigation process and the need for parties to raise all relevant issues at the appropriate time.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.