[2024] UKSC 40
On appeal from: [2022] EWCA Civ 1422
JUDGMENT
R (on the application of Cobalt Data Centre 2 LLP and another) (Appellants) v Commissioners for His Majesty’s Revenue and Customs (Respondent)
before
Lord Briggs
Lord Sales
Lord Burrows
Lady Rose
Lord Richards
20 November 2024
Heard on 24 and 25 January 2024
Appellants
Laurence Rabinowitz KC
Niranjan Venkatesan
(Instructed by Macfarlanes LLP)
Respondent
David Ewart KC
Stephen Kosmin
Edward Waldegrave
Laura Ruxandu
(Instructed by HMRC Solicitor’s Office and Legal Services (Stratford))
LORD BRIGGS AND LORD SALES (with whom Lord Burrows, Lady Rose and Lord Richards agree):
Introduction – the Issues
This appeal concerns the conditions for the availability of the initial 100% capital allowances (“EZA”) regime arising from expenditure incurred in the construction of buildings in an enterprise zone under the Capital Allowances Act 2001 (“the 2001 Act”). Section 298 of the 2001 Act provides that:
For the purposes of sections 299 to 304, the time limit for expenditure on the construction of a building on a site in an enterprise zone is-
10 years after the site was first included in the zone, or
If the expenditure is incurred under a contract entered into within those 10 years, 20 years after the site was first included in the zone.”
In the present case the relevant expenditure was incurred more than 10 years but less than 20 years after the site was first included in the zone, so that the taxpayer was required to show that the expenditure was incurred “under a contract entered into within those 10 years” within the meaning of section 298(1)(b). We will refer to years 1 to 10 as the first period and to years 11 to 20 as the second period.
The contract upon which the taxpayers rely for this purpose in the present case is a type of building contract which has come to be known as a golden contract, and it has been labelled “the Golden Contract” in these proceedings. The distinguishing feature of a golden contract in this context is that, rather than prescribe one or more construction projects which the contractor undertakes to carry out, it sets out a range of alternative construction projects, each described in detail, between which the developer is entitled to (and must) choose, by service of a specified notice upon the contractor. The contract consists of more than a series of mere options (although that is how the specified alternatives were labelled in this Golden Contract), because the developer is required to choose one within a specified time frame, so that the contractor has a contractual right from the outset that one of the specified building projects will be commissioned. A golden contract creates a regime according to which the developer’s obligation to proceed with a development is matched by the developer’s right to select between specified projects, rather than granting an option or set of options leaving the developer free to do nothing. There is therefore a commitment from the outset to the carrying out of a building project on a site within the enterprise zone, but the developer retains the right to decide which one.
The Golden Contract in the present case specified six alternative projects, each for different buildings on different sites (although many of the sites overlapped) within the same enterprise zone, each identified by a description of the type of building, the site on which it was to be constructed, and by reference to an appendix setting out the agreed specification in great detail. It is common ground that the Golden Contract, as originally made and as it remained at the end of the first period, required the developer to select one of the alternative projects. For ease of reference, whilst it should be emphasised that it imposed an obligation on the developer to make a selection, we will call it the developer’s right to select.
Building contracts commonly contain a right for the developer to insist on changes to be made in the specification of the project as it goes along, usually with a right conferred on the building contractor to refuse to accept unreasonable changes, and provision for payment of the resulting extra cost (if any). The Golden Contract included such provision. We will call it the developer’s right to change.
The combination of the developer’s right to select and the developer’s right to change provided the developer under the Golden Contract with valuable flexibility to make significant choices and adjustments to the projects and therefore to the expenditure to be incurred during the second period (ie between the tenth and twentieth anniversaries of the relevant site being included in the enterprise zone), without losing the benefit of the EZA regime. This is because both the right to select and the right to change are unilateral rights conferred on the developer by the Golden Contract in its original form. Expenditure incurred by reason of the exercise of either of those rights is, as the respondents (“HMRC”) accept, expenditure incurred “under” the Golden Contract. Because the Golden Contract was made during the first period, any expenditure incurred in the second period as a result of the exercise of those rights would satisfy the composite time limit in section 298(1)(b).
Under the common law which regulates the legal relationship between contracting parties, there is of course freedom to make almost any alteration to this relationship by a further agreement. This may be achieved (broadly speaking) by one or other of two mechanisms. The first is to vary the existing contract by altering one or more of its terms. The second is to put an end to the existing contract and replace it with a new one. We will call the first mechanism variation and the second replacement. The second has tended to be called rescission during argument, but this is a word with a variety of meanings, only one of which is to put an end to a contract by a further agreement. Furthermore rescission says nothing about any continuing contractual relationship, whereas replacement does. It is again common ground that both variation and replacement require a further agreement which satisfies the common law requirements of a binding contract, including fresh consideration.
The facts which have given rise to the issues to be determined on this appeal may, in a nutshell, be summarised as follows. The Tyne Riverside Enterprise Zone was established on 19 February 1996. On 17 February 2006 two wholly owned and controlled special purpose subsidiaries of the same corporate parent made the Golden Contract for the construction of a building in that enterprise zone just two days before the expiry of the first 10 year period. The parties were Highbridge North Tyneside Developer One Limited (called the Developer) and Highbridge North Tyneside Contractor One Limited (called the Contractor). The appellant taxpayers are successors in title to the rights of the Developer. The Golden Contract gave the Developer the right of selection of one out of six specified projects, called Works Option 1 to Works Option 6. By clause 12 of the JCT Standard Form as incorporated in and amended by the Golden Contract (“clause 12”), the Developer was given a right to change the design, quality or quantity of “the Works” (as defined) included in the detailed specifications within each Works Option, subject to a requirement that the Contractor consent to a change to design, such consent not to be unreasonably withheld or delayed, and with provision for extra payment to the Contractor where changes necessitated extra work.
At various times during the second period the Developer purported to exercise both the right to select and the right to change. The Developer and the Contractor also purported during the second period to vary the Golden Contract so as, inter alia, to enable the Developer to select more than one of the specified Works Options. Thereafter the Contractor built and the Developer and the taxpayers (the Developer’s successors) paid for three buildings, called DC1, DC2 and DC3. The present appeal is concerned with a claim for EZAs in respect of buildings DC2 and DC3. Those buildings differ in significant respects from the subject matter of any of the Works Options set out in the Golden Contract in its original form. The expenditure incurred by the Developer and the taxpayers on DC2 and DC3 within the second period (“the Relevant Expenditure”) constitutes the basis of the claim to 100% capital allowances in issue on this appeal.
The primary case of the taxpayers is that the Relevant Expenditure was all incurred under the Golden Contract and hence fell within the scope of section 298, because it was all commissioned by the unilateral exercise by the Developer of the right to select and the right to change set out in clause 12 conferred by the Golden Contract in its original form, ie as made during the first period. HMRC say that those rights, on the true construction of the Golden Contract, were insufficiently wide to enable the Developer to require the Contractor to build DC2 or DC3, which could only be contracted for by a new agreement, made after the end of the first period, and therefore falling foul of the time limits in section 298. The taxpayers reply by claiming, in the alternative to their primary case, that if the Relevant Expenditure was incurred as the result of a new agreement enabling the Developer to select additional Works Options, it was one which varied rather than replaced the Golden Contract, so that it was still incurred “under” the Golden Contract as varied. To that alternative case HMRC makes two responses. First (in logic though not in time), section 298 does not on its true construction permit expenditure required or allowed by the content of a variation made during the second period of a contract made during the first period (or at least a variation which changed the type of building or the site on which it was to be built) to be treated as expenditure incurred “under” the earlier contract. Secondly, the alterations (to use a neutral word) necessary to provide for the construction of DC2 and DC3 amounted to a replacement of the Golden Contract rather than a variation of it, so that on no construction of section 298 could the replacement contract be said to have been made during the first period.
Thus the issues which emerge for decision by this court may be summarised as follows:
Was the Relevant Expenditure triggered by the exercise of the Developer’s unilateral rights to select and to change conferred by the Golden Contract in its original form? (“The Clause 12 Issue”)
If not, does section 298 on its true construction enable expenditure, incurred by reason of a variation during the second period of a contract originally made in the first period, to be treated as expenditure incurred under the original contract? (“The section 298 Issue”)
If it does, was the Relevant Expenditure triggered by a variation or by a replacement of the Golden Contract? (“The Variation Issue”)
The Clause 12 Issue raises questions of construction of the Golden Contract, mainly in relation to clause 12, and its application to agreed facts, although the issues of construction go a little wider than that. If the question as framed is given an affirmative answer then HMRC accept that the appeal should be allowed. We deal with this issue at paras 108-124 below.
The section 298 Issue raises an important question of construction of section 298, in its statutory context. If it is answered in the negative, then the appeal must fail, and the Variation Issue becomes largely academic. But the taxpayers raise the threshold question whether it is open to HMRC to raise the section 298 Issue at all, having, it is said, declined to do so in the courts below in circumstances where permission to raise it now would cause the taxpayers prejudice. We deal with this issue at paras 58-107 below.
The Variation Issue is said to raise an important unresolved question of pure common law, namely whether and if so to what extent the characterisation of a contractual alteration to a contractual relationship as either a variation or a replacement (or, if one wishes to use the word, rescission) of the original contract depends upon the common intention of the parties, objectively ascertained. We will call it the Variation Issue. This is a point upon which the courts below disagreed, and in relation to which the judgments of the members of the Court of Appeal do not deliver entirely uniform reasoning. But it only arises if this court answers the Clause 12 Issue “no” and either refuses to entertain the section 298 Issue or answers it “yes”. We deal with this issue at paras 125-161 below.
For reasons which will in due course appear, we would answer the Clause 12 Issue in the negative. We consider that the court should entertain the section 298 Issue and we would also answer it in the negative. We would therefore dismiss the appeal, albeit for different reasons than those given by the Court of Appeal for the same outcome. While the Variation Issue is therefore in our view largely academic, it was the basis for the Court of Appeal’s decision and the subject of extensive reasoning in that court. It has been fully argued on this appeal, and we consider it to be of sufficient public importance to address it in any event. It does not in our view admit of a simple yes or no answer. Because the section 298 Issue is also of general importance and because a proper understanding of the time limits in section 298 forms part of the context in which the other issues fall to be decided, we propose to consider it first, after a fuller deployment of the facts, the terms of the Golden Contract and a summary of the decisions of the courts below.
The Facts
In 1996, an Order was made to designate an enterprise zone in North Tyneside to include the Cobalt Business Park (“the Site”) during the period 19 February 1996 to 18 February 2006: the Tyne Riverside Enterprise Zones (North Tyneside) (Designation) (No. 1) Order 1996 (SI 1996/106).
Prior to 2006, part of the Site had been used by Siemens, the well-known manufacturing company, for a facility to make semiconductors. However, following a downturn in the price for computer memory chips, Siemens ceased production and sold the Site to the Atmel group (“Atmel”). In 2006, realising that the enterprise zone would soon be coming to an end, Atmel took steps to preserve the ability to claim EZAs in respect of future construction work at the Site. It incorporated the Developer and the Contractor as special purpose vehicles with a view to achieving this.
On 17 February 2006 – as noted above, two days before the deadline specified in section 298(1) of 10 years after 19 February 1996 - the Developer and the Contractor entered into the Golden Contract for the construction of a building at the Site. In doing this, the intention of both the Developer and the Contractor was that the Developer would have the tax benefit of being able to claim EZAs in relation to the construction costs, pursuant to section 298(1)(b), for whichever building was chosen for construction under the Golden Contract.
The Golden Contract incorporated the conditions of the JCT Standard Form of Building Contract with Contractor’s Design 1998 Edition (“the JCT Standard Form”) with certain specified amendments agreed by the parties. In the JCT Standard Form clauses the Developer is called “the Employer”, and both terms are used in this judgment.
The JCT Standard Form provides that the Employer is entitled (and obliged) to require the Contractor to undertake a single building project. But by amendment of that form, the Golden Contract provided from the outset that the Developer was entitled (and obliged) to require the Contractor to undertake any one (but not more than one) of six specified building projects. The alternative projects were called “Works Option 1” to “Works Option 6” and definitions were provided for each of these terms which referred to very detailed documentation specifying the Developer’s instructions for that option (called “the Works Option 1 Employer’s Requirements”, “the Works Option 2 Employer’s Requirements” and so on, respectively). The six Works Options defined in the Golden Contract differed significantly in size and scope, provided for works to be undertaken on different parts of the Site (on areas described as Sites A, B or C, depending on the Works Option) and provided in each case for a different specified “Contract Sum” payable by the Developer.
Works Option 1 was defined as follows:
“… the design, construction and commissioning work comprising an industrial unit to accommodate the manufacture of an eight inch board on Site C for which works the Employer has issued to the Contractor its requirements (hereinafter referred to as the ‘Works Option 1 Employer’s Requirements’).”
Works Option 3 was defined as follows:
“… the design and construction works comprising an office business park on Site A for which works the Employer has issued to the Contractor its requirements (hereinafter referred to as the ‘Works Option 3 Employer’s Requirements’).”
Clause 23A of the Golden Contract obliged the Developer to serve a Notice to Proceed on the Contractor which was to state “which Works Option the Contractor shall carry out and complete”.
In February 2009 (that is, outside the first 10 year period specified in section 298) the parties agreed to vary the Golden Contract to permit the Developer to submit a Notice to Proceed in respect of a combination of specified Works Options, stating that notwithstanding the giving of a Notice to Proceed in respect of Works Option 2, the Employer could also give a Notice to Proceed in respect of Works Option 3 (“Variation 1”). In April 2009 a further variation was agreed to replace Variation 1 to permit the Developer to choose to proceed with a different combination of Works Options, being Works Option 1 and Works Option 3 (“Variation 2”). Clause 23A was amended accordingly, to say that notwithstanding the giving of a Notice to Proceed as respects Works Option 1 the Developer could also give a Notice to Proceed as respects Works Option 3.As is clear, these variations effected significant substantive alterations in the rights and obligations of the Developer and the Contractor as they had originally been specified in the Golden Contract.
Clause 12 of the JCT Standard Form, as incorporated in and amended by the Golden Contract, headed “Changes in the Employer’s Requirements and provisional sums”, provided in relevant part as follows:
The term ‘Change in the Employer’s Requirements’ or ‘Change’ means:
a change in the Employer’s Requirements which makes necessary the alteration or modification of the design, quality or quantity of the Works, otherwise than such as may be reasonably necessary for the purposes of rectification pursuant to clause 8.4, including
.1.1 the addition, omission or substitution of any work,
.1.2 the alteration of the kind or standard of any of the materials or goods to be used in the Works,
.1.3 the removal from the site of any work executed or materials or goods brought thereon by the Contractor for the purposes of the Works other than work materials or goods which are not in accordance with this Contract;
the imposition by the Employer of any obligations or restrictions in regard to the matters set out in clause 12.1.2.1 to 12.1.2.4 or the addition to or alteration or omission of any such obligations or restrictions so imposed or imposed by the Employer in the Employer’s Requirements in regard to:
.2.1 access to the site or use of any specific parts of the site,
.2.2 limitations of working space,
.2.3. limitations of working hours …,
.2.4 the execution or completion of the work in any specific order.
The Employer may subject to the proviso hereto and to clause 12.2.2 issue instructions effecting a Change in the Employer’s Requirements. No Change effected by the Employer shall vitiate this Contract. Provided that the Employer may not effect a Change which is, or which makes necessary, an alteration or modification in the design of the Works without the consent of the Contract which consent shall not be unreasonably delayed or withheld.”