IN THE COURT OF APPEAL OF NEW ZEALAND
CA44/04
BETWEENPRIMARY HEALTH REMUERA LIMITED
Appellant
ANDAVOCA RESIDENTIAL CONSTRUCTION LIMITED
Respondent
Hearing:2 June 2004
Coram:Anderson P
Chambers J
O'Regan JAppearances: H P Holland for Appellant
N J Carter for Respondent
Judgment:10 September 2004
JUDGMENT OF THE COURT DELIVERED BY O’REGAN J
[1] This is an appeal against a decision of Associate Judge Lang in which he dismissed an application by the appellant, Primary Health Remuera Limited, for an order setting aside a statutory demand served on Primary Health by the respondent, Avoca Residential Construction Limited, under s290(4) Companies Act 1993. The Judge also made an order under s291(1)(a) Companies Act requiring Primary Health to pay to Avoca the sum of $215,158.75 within 14 days.
Facts
[2] Primary Health is a property developer. Avoca is a construction company. Primary Health is the developer of a substantial town house complex in Remuera Road, Auckland. It called for tenders for the construction of the town houses on the basis of specifications produced by its architects, Archimedia Limited. The specifications incorporated the New Zealand Institute of Architects (NZIA) Standard Conditions of Contract SCC1 2000. Avoca provided an initial tender on 12 November 2001. After correspondence between Avoca and Archimedia, Avoca then submitted a revised tender on 5 December 2001, which was accepted by Primary Health. However, a formal contract for the construction of the town houses was never signed.
[3] The Judge found that the revised tender, the specifications, incorporating the NZIA conditions and the relevant correspondence between Avoca, Archimedia and Primary Health together provided the basis of the contractual relationship between Primary Health and Avoca. (We will refer to this arrangement as the Contract.) There was, however, a dispute as to whether Avoca agreed that liquidated damages for delayed completion would be in the amount of $2,500 per day. We will revert to this later.
[4] As is customary in building contracts of this kind, there was provision for progress payments to be made during the construction period. The provisions governing such payments were rr 73-85 of the NZIA conditions. The text of the relevant rules is set out in an appendix to this judgment. In summary, these provisions provide for the following regime:
(a) Under r 73, the Contractor (Avoca) is entitled to apply to the Architect (for the purposes of this aspect of the contract the Architect was Rider Hunt Auckland Limited) for a progress payment certificate;
(b) The Architect must assess the Contractor’s claim according to certain requirements set out in r 74. In particular, the Architect must deduct from the amount it assesses any retentions allowed under r 79 and any liquidated damages that have become payable under r 72;
(c) Under r 75, the Architect is required to certify the amount it assesses as the Contractor’s claim, less the deductions referred to above, and give a copy of the progress payment certificate to the Principal (Primary Health);
(d) Under r 76, the Principal must pay the amount certified by…
Keep reading for free
Create a free CaseChat account to read Primary Health Remuera Ltd v Avoca Residential Construction... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2004] NZCA 220
- Decision Date
CaseChat Overview and Summary
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi