IN THE HIGH COURT OF NEW ZEALAND INVERCARGILL REGISTRY
I TE KŌTI MATUA O AOTEAROA WAIHŌPAI ROHE
CIV-2022-425-79
[2023] NZHC 2715
BETWEEN NORTHLAKE INVESTMENTS LIMITED
Plaintiff
AND
CIVIL CONSTRUCTION LIMITED
Defendant
Hearing: 28 August 2023 Appearances:
J D McBride and A W McDonald for Plaintiff B M Cash and V Bortsova for Defendant
Judgment:
28 September 2023
JUDGMENT OF ASSOCIATE JUDGE PAULSEN
This judgment was delivered by me on 28 September 2023 at 3.00 pm pursuant to Rule 11.5 of the High Court Rules
Registrar/Deputy Registrar Date:
NORTHLAKE INVESTMENTS LTD v CIVIL CONSTRUCTION LTD [2023] NZHC 2715 [28 September 2023]
Table of Contents
Para No
Introduction [1] What happened
The contracts [7] The Covid Claim [11] The Stage 12 Claim [19] The adjudication [25] The final payment claim [32] Summary judgment principles – Northlake
[33]
Northlake’s pleading
[36]
Issue one – Was Civil required to dispute the engineer’s decisions under the dispute resolution provisions of NZS 3910:2013?
[38]
The Stage 12 Claim [40] The Covid Claim [44] Conclusion on issue one [47] Issue two – If Civil was required to dispute the engineer’s decisions, did it do so in the manner required?
Northlake’s position [48] Civil’s position [52] My analysis [62] Conclusion on issue two [69] Issue three – Was the adjudicator’s determination binding?
[70]
The Act [71] Northlake’s alternative positions [93] Conclusion of issue three [95] Issue four – Does Northlake have a claim for money had and received?
[96]
Conclusion on issue four [103] Summary judgment application and strike out principles – Civil
[104]
Issue five – Can the adjudicator’s determination now be challenged by Northlake?
[110]
Result
[114]
Introduction
[1] Northlake Investments Ltd (Northlake) and Civil Construction Ltd (Civil) entered into construction contracts for the performance of works by Civil at Northlake’s development at Wanaka. The engineer to the contracts disallowed certain payment claims by Civil, which Civil referred to adjudication under the Construction Contracts Act 2002 (the Act). An adjudicator issued a determination requiring Northlake to make payments to Civil in respect of the disputed claims. Northlake made payment whilst disputing its liability to do so.
[2] Northlake now seeks summary judgment against Civil to recover, as money had and received, the $591,040 it paid to Civil in respect to two of the disputed claims. It argues the adjudicator’s determination had “no effect” upon decisions made by the engineer disallowing Civil’s claims, and the decisions are “final and binding” because Civil did not refer them to the engineer or to adjudication as required by the conditions of contract within three months of the decisions being given.
[3] Civil resists summary judgment and makes its own application for summary judgment and to strike out Northlake’s claim. Civil argues the engineer’s decisions never became final and binding because it was not required to dispute them, but that it did so in time in any event. Even if that was not the case, Civil says it was entitled to refer the disputes to adjudication, the adjudication determination was binding…
Keep reading for free
Create a free CaseChat account to read Northlake Investments Limited v Civil Construction Limited and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2023] NZHC 2715
- Decision Date
CaseChat Overview and Summary
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi