He v Earthquake Commission

Case [2019] NZCA 373


IN THE COURT OF APPEAL OF NEW ZEALAND

I TE KŌTI PĪRA O AOTEAROA

 CA567/2017
 [2019] NZCA 373

BETWEEN

XIAOMING HE
Appellant

AND

EARTHQUAKE COMMISSION
First Respondent

AND

CERTAIN SYNDICATES OF LLOYD’S OF LONDON SEVERALLY SUBSCRIBED TO COVERHOLDER CONTRACT B0429CNG90466 AND CERTAIN SYNDICATES OF LLOYD’S OF LONDON SEVERALLY SUBSCRIBED TO COVERHOLDER CONTRACT B0429CNG110466
Second Respondents

Hearing:

30 July 2019

Court:

Brown, Collins and Goddard JJ

Counsel:

P A Cowey and A J Summerlee for Appellant
M R Crotty and N L Walker for First Respondent
R M Flinn and A R Moore for Second Respondents

Judgment:

20 August 2019 at 10.00 am

JUDGMENT OF THE COURT

A      The appeal is dismissed.

BThe appellant must pay one set of costs to the first respondent and one set of costs to the second respondents, in each case for a standard appeal on a band A basis together with usual disbursements.  We certify for second counsel.

____________________________________________________________________

REASONS OF THE COURT

(Given by Goddard J)

Introduction

  1. The appellant, Mr He, owns a property at 377 Selwyn Street in Christchurch.  The principal building on the property (the house) is a house with a shop attached to it.  There are also two freestanding garages.  At the time of the Canterbury earthquakes in 2010 and 2011 the house was covered for natural disaster damage under the Earthquake Commission Act 1993 (EQC Act).  The property was also insured with the second respondents (whom we refer to collectively as OMPL)[1] in respect of certain earthquake damage not covered by the Earthquake Commission (EQC), on the basis set out in the relevant insurance policies. 

    [1]Offshore Market Placements Ltd (OMPL) is a company that acts as agent for the underwriters of the relevant insurance policies. 

  2. The house suffered damage caused by the Canterbury earthquakes.  Mr He made claims to EQC in respect of that damage.  EQC paid approximately $16,000 for repairs to the house.  Mr He considered that EQC’s liability under the EQC Act substantially exceeded this sum.  Mr He also made claims to OMPL in respect of damage to the property, which OMPL did not accept.  Mr He brought proceedings against EQC and OMPL in the High Court.  The claim was largely unsuccessful, apart from a minor claim against EQC for repairs to plaster damage on a section of the perimeter foundation of the house.[2]

  3. In the High Court Mr He advanced a number of claims in respect of damage to the property which he said had been caused by the September 2010, February 2011 and June 2011 Canterbury earthquakes.  Mr He’s appeal to this Court is confined to two of the issues that were determined by the High Court:

    (a)The High Court dismissed Mr He’s claims in relation to damage caused by the February 2011 earthquake, other than the minor damage to the perimeter foundation mentioned above.[3]  The High Court held that Mr He had not established that there was any other damage to the house caused…

Continue reading He v Earthquake Commission

Sign in free to access the full text

Details
AGLC
He v Earthquake Commission [2019] NZCA 373
Case
[2019] NZCA 373
Decision Date

CaseChat Overview and Summary

The appeal was brought by Mr He against the decision of the High Court dismissing his claims for earthquake damage to his property. The first respondent, the Earthquake Commission (EQC), was responsible for compensating Mr He for damage caused by the Canterbury earthquakes. The second respondents were insurance companies that had insured Mr He's property against earthquake damage not covered by EQC. The central issues on appeal were whether the February 2011 earthquake caused damage to the floors of the house, and whether EQC had met its obligations in relation to damage to one of the house's chimneys. The Court of Appeal held that Mr He had not established that the February 2011 earthquake caused material damage to the floors of the house. The Court found that there was no evidence of material changes in floor levels as a result of the earthquake, and that any observed damage was consistent with pre-existing static settlement. The Court also held that EQC had met its obligations in relation to the damaged chimney by paying for its removal and the cost of rebuilding it. The appeal was dismissed and Mr He was ordered to pay costs to the respondents.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.