Court of Appeal
Supreme Court
New South Wales
Medium Neutral Citation: Witron Australia Pty Ltd v Turnkey Innovative Engineering Pty Ltd [2023] NSWCA 305 Hearing dates: 6 December 2023 Date of orders: 13 December 2023 Decision date: 13 December 2023 Before: Leeming JA at [1];
Payne JA at [2];
Kirk JA at [3]Decision: (1) Appeal dismissed.
(2) Appellant to pay the respondent’s costs.
Catchwords: BUILDING AND CONSTRUCTION — Payment schedule requirements — Where payment claim had two distinct and substantial components — Where statement for withholding payment failed to provide any reason directed to a distinct and substantial component of a payment claim — Whether statement was sufficient to constitute “reasons” under s 14(3) of the Building and Construction Industry Security of Payment Act 1999 (NSW) — Sufficiency of reasons is to be assessed in a purposive manner
Legislation Cited: Building and Construction Industry Payment Act 2004 (Qld), s 18
Building and Construction Industry Security of Payment Act 1999 (NSW), ss 8(c), 14, 15(2)(b), 17(3)(b), 19, 20(2B), 22(2)(d), 27
Cases Cited: Barclay Mowlem v Tesrol Walsh Bay [2004] NSWSC 1232
Ceerose Pty Ltd v A-Civil Aust Pty Ltd [2023] NSWCA 215
Clarence Street Pty Ltd v Isis Projects Pty Ltd (2005) 64 NSWLR 448; [2005] NSWCA 391
Façade Treatment Engineering Pty Ltd (in liq) v Brookfield Multiplex Constructions Pty Ltd (2016) 337 ALR 452; [2016] VSCA 247
John Holland Pty Ltd v Roads and Traffic Authority of New South Wales (2007) 23 BCL 205; [2007] NSWCA 19
Joye Group Pty Ltd v Cemco Projects Pty Ltd [2021] NSWCA 211
Minimax Fire Fighting Systems Pty Ltd v Bremore Engineering (WA) Pty Ltd [2007] QSC 333
Multiplex Constructions Pty Ltd v Luikens [2003] NSWSC 1140
Project Blue Sky v Australian Broadcasting Authority (1998) 194 CLR 355; [1998] HCA 28
Style Timber Floor Pty Ltd v Krivosudsky (2019) 100 NSWLR 133; [2019] NSWCA 171
Vanella Pty Ltd v TFM Epping Land Pty Ltd [2019] NSWSC 1379
Western Australian Planning Commission v Southregal Pty Ltd (2017) 259 CLR 106; [2017] HCA 7
Category: Principal judgment Parties: Witron Australia Pty Ltd (Appellant)
Turnkey Innovative Engineering Pty Ltd (Respondent)Representation: Counsel:
Solicitors:
D S Weinberger (Appellant)
S Robertson SC / D Hume (Respondent)
Lander & Rogers (Appellant)
Thomson Geer (Respondent)
File Number(s): 2023/275941 Publication restriction: Nil Decision under appeal
- Court or tribunal:
- Supreme Court
- Jurisdiction:
- Equity – Technology and Construction List
- Citation:
Turnkey Innovative Engineering Pty Ltd v Witron Australia Pty Ltd [2023] NSWSC 981
- Date of Decision:
- 16 August 2023
- Before:
- Stevenson J
- File Number(s):
- 2023/213782
HEADNOTE
[This headnote is not to be read as part of the judgment]
The appellant, Witron Australia Pty Ltd, contracted the respondent, Turnkey Innovative Engineering Pty Ltd, to carry out electrical installation works involving a series of “group controls” (GCs). The contract stipulated “a flat fixed price” of $11.4 million (excluding GST) for a defined scope of work, subject to “any increase or decrease arising from variations as mutually agreed by…
Keep reading for free
Create a free CaseChat account to read Witron Australia Pty Ltd v Turnkey Innovative Engineering Pt... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2023] NSWCA 305
- Decision Date
CaseChat Overview and Summary
The central legal issue before the Court of Appeal was whether Witron's statement, which failed to provide reasons specifically directed to one of the distinct and substantial components of Turnkey's payment claim, was sufficient to constitute "reasons" for withholding payment under section 14(3) of the Act. The Court was required to determine the sufficiency of the reasons provided by Witron in light of the statutory requirements.
The Court of Appeal affirmed the lower court's decision, holding that the reasons provided by Witron were insufficient. Applying a purposive approach to the interpretation of section 14(3), the Court reasoned that the purpose of requiring reasons is to enable the claimant to understand the basis of the withholding and to respond accordingly. Where a payment claim has multiple distinct and substantial components, the statement withholding payment must provide reasons that address each of those components. Witron's failure to provide reasons directed to one of the substantial components meant its statement did not satisfy the statutory requirement. Consequently, the appeal was dismissed, and Witron was ordered to pay Turnkey's costs.
Orders
Orders of the court
(1) Appeal dismissed.
(2) Appellant to pay the respondent’s costs.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.