Turnkey Innovative Engineering Pty Ltd v Witron Australia Pty Ltd

Link copied
Case Copied 13 min read

Supreme Court


New South Wales

Medium Neutral Citation: Turnkey Innovative Engineering Pty Ltd v Witron Australia Pty Ltd [2023] NSWSC 981
Hearing dates: 16 August 2023
Date of orders: 18 August 2023
Decision date: 18 August 2023
Jurisdiction:Equity - Technology and Construction List
Before: Stevenson J
Decision:

The purported payment schedule is not a valid payment schedule for the purpose of s 14 of the Building and Construction Industry Security of Payment Act 1999 (NSW)

Catchwords:

BUILDING AND CONSTRUCTION – contract – whether email constitutes a valid payment schedule for purpose of s 14 of the Building and Construction Industry Security of Payment Act 1999 (NSW) – whether email indicated the amount the respondent to the payment claim proposed to pay – whether email indicated the reasons the respondent to the payment claim withheld payment

Legislation Cited:

Building and Construction Industry Security of Payment Act 1999 (NSW)

Cases Cited:

Barclay Mowlem v Tesrol Walsh Bay [2004] NSWSC 1232

Clarence Street Pty Ltd v Isis Projects Pty Ltd (2005) 64 NSWLR 448; [2005] NSWCA 391

Façade Treatment Engineering Pty Ltd (in liq) v Brookfield Multiplex Constructions Pty Ltd [2016] VSCA 247

Joye Group Pty Ltd v Cemco Projects Pty Ltd [2021] NSWCA 211

Minimax Fire Fighting Systems Pty Ltd v Bremore Engineering (WA) Pty Ltd & Ors [2007] QSC 333

Multiplex Constructions Pty Ltd v Luikens and Anor [2003] NSWSC 1140

Style Timber Floor Pty Ltd v Krivosudsky (2019) 100 NSWLR 133; [2019] NSWCA 171

Vannella Pty Limited atf Capitalist Family Trust v TFM Epping Land Pty Ltd; Decon Australia Pty Limited v TFM Epping Land Pty Ltd; Vannella Pty Limited v TFM Epping Land Pty Ltd [2019] NSWSC 1379

Category:Principal judgment
Parties: Turnkey Innovative Engineering Pty Ltd (Plaintiff)
Witron Australia Pty Ltd (Defendant)
Representation:

Counsel:
S Robertson SC and D P Hume (Plaintiff)
D S Weinberger and J Y Li (Defendant)

Solicitors:
Thomson Geer Lawyers (Plaintiff)
Lander & Rogers (Defendant)
File Number(s): 2023/213782

JUDGMENT

  1. The sole question in this case is whether an email sent by the defendant, Witron Australia Pty Ltd (“the Principal”), to the plaintiff, Turnkey Innovative Engineering Pty Ltd (“the Contractor”), is a valid payment schedule for the purpose of s 14 of the Building and Construction Industry Security of Payment Act 1999 (NSW) (“the Act”).

  2. For the reasons that follow, my opinion is that it was not.

  3. On 8 September 2022, the Principal and the Contractor entered into a contract (“the Contract”) to carry out electrical installation works at an automated distribution centre to be constructed for Coles Group Limited at Kemps Creek.

  4. The Contract provided for a “flat rate fixed price” of $11.4 million “subject to any increase or decrease arising from variations as mutually agreed by the parties”.

  5. The works were delayed, and on 22 March 2023, the Principal sent the Contractor an email removing from the scope of works under the Contract a number of “Group Control” areas.

  6. Thereafter, the Contractor sought to re-price the works at $14,141,951.32 on…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Turnkey Innovative Engineering Pty Ltd v Witron Australia Pt... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2023] NSWSC 981
Decision Date

CaseChat Overview and Summary

Turnkey Innovative Engineering Pty Ltd sought a declaration that a payment schedule issued by Witron Australia Pty Ltd was invalid, as it did not comply with section 14 of the Building and Construction Industry Security of Payment Act 1999 (NSW). The dispute arose from a building and construction contract, and the core issue was whether the email issued by Witron constituted a valid payment schedule under the Act. Specifically, the court had to determine if the email indicated the amount Witron proposed to pay and the reasons for withholding payment.

The court examined the statutory provisions and previous case law to assess whether the email met the requirements of section 14. It found that for a payment schedule to be valid, it must clearly state the amount the respondent proposes to pay and the reasons for withholding payment. The court scrutinised the content of the email and concluded that it did not sufficiently indicate the amount Witron proposed to pay, nor did it provide adequate reasons for withholding payment. As a result, the court found the email to be an invalid payment schedule.

Given the invalidity of the payment schedule, the court granted Turnkey's application for a declaration that the payment schedule was invalid. The court also ordered Witron to pay Turnkey's costs of the proceeding. This decision reinforces the importance of compliance with the statutory requirements for payment schedules under the Act, highlighting the necessity for clarity and specificity in the communication of payment details and withholding reasons.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.