Wellington and others v Huaxin Energy (Aust) Pty Ltd

Link copied
Case Copied 62 min read

SUPREME COURT OF QUEENSLAND

CITATION:

Wellington & Ors v Huaxin Energy (Aust) Pty Ltd (formerly Cuesta Coal Limited) & Anor [2020] QCA 114

PARTIES:

OWEN REGINALD WELLINGTON AND ROXANNE WELLINGTON AS TRUSTEES FOR THE OR & R WELLINGTON SUPERFUND
ABN 81 576 722 911
(first appellant)
OWEN REGINALD WELLINGTON AS TRUSTEE FOR OR & R PARTNERSHIP
ABN 84 165 075 135
(second appellant)
FOX INVESTMENTS (QLD) PTY LTD ACN 159 501 845 AS TRUSTEE FOR THE FOX FAMILY TRUST
(third appellant)
v
HUAXIN ENERGY (AUST) PTY LTD (FORMERLY CUESTA COAL LIMITED)
ACN 153 351 994
(first respondent)
BLACKWOOD EXPLORATION PTY LTD
ACN 142 208 982
(second respondent)

FILE NO/S:

Appeal No 2611 of 2019
SC No 5591 of 2016

DIVISION:

Court of Appeal

PROCEEDING:

General Civil Appeal

ORIGINATING COURT:


Supreme Court at Brisbane – [2019] QSC 18 (Jackson J)

DELIVERED ON:

29 May 2020

DELIVERED AT:

Brisbane

HEARING DATE:

13 June 2019

JUDGES:

Morrison and Philippides JJA and Ryan J

ORDERS:

1.   The appeal is dismissed.

2.   The appellants pay the respondents’ costs of the appeal.

CATCHWORDS:

CONTRACTS – GENERAL CONTRACTUAL PRINCIPLES – CONSTRUCTION AND INTERPRETATION OF CONTRACTS – IMPLIED TERMS – TERMS ESSENTIAL TO ENABLE PERFORMANCE – where the parties entered into a contract for the sale of an exploration permit for coal (EPC) and the related environmental authority and mining information as property (the Assets) – where there were various iterations of the contract for the sale of the Assets, culminating in the “final contract” between the appellants and respondents – where the respondents made three payments pursuant to the relevant iteration of the agreement and the EPC was transferred to the second respondent – where the consideration for the purchase of the assets also included the issue of Third Tranche Shares and Third Tranche Options (as those terms were defined in the final contract), conditional on a Competent Person estimating the existence of a Measured Mineral Resource within the EPC area of 100 million tonnes (Mt), or if not, an amount of 40 Mt or greater (as those terms are defined in the final contract and an industry code called the “JORC Code”) – where, on 28 November 2013, the first respondent made an announcement to the ASX that a Competent Person estimated the existence of an Inferred Mineral Resource (as that term is defined in the JORC Code) of 364.1 Mt – where, following that announcement, the second respondent did not carry out further exploratory work that would be necessary to further upgrade the mineral resource – where the appellants contended at trial that there was an implied duty on the first respondent to cooperate by causing to be obtained “detailed and reliable exploration, sampling and testing information” so that the appellants could have the benefit comprised in the Third Tranche Shares and Options consequent on the existence of the existence of a Measured Mineral Resource in the contemplated quantity – whether there was an implied duty to cooperate as alleged by the appellants as a…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Wellington and others v Huaxin Energy (Aust) Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2020] QCA 114
Decision Date

CaseChat Overview and Summary

Wellington and others v Huaxin Energy (Aust) Pty Ltd was an appeal against a decision of Jackson J, who had dismissed claims for breach of implied contractual duties and for damages. The appellants (the Wellingtons) sought to establish the existence of implied terms in a contract for the sale of an exploration permit for coal (EPC). The respondents (Huaxin) argued that the trial judge’s decision was correct in rejecting the existence of an implied duty to cooperate and an implied term to undertake particular exploration work. The Wellingtons appealed the trial judge’s decision on the basis that he had erred in rejecting the existence of an implied duty to cooperate, an implied term to undertake particular exploration work, and in his quantification of damages for loss of opportunity arising from a breach of the implied terms. The appeal was dismissed, and the Wellingtons were ordered to pay the respondents’ costs of the appeal.

The central issues in the appeal concerned the implication of terms in the contract for the sale of the EPC and related assets. The Wellingtons argued that there was an implied duty on Huaxin to cooperate by causing to be obtained "detailed and reliable exploration, sampling and testing information" so that the Wellingtons could benefit from the Third Tranche Shares and Options contingent on the existence of a Measured Mineral Resource in the contemplated quantity. They also argued that there was an implied term in the contract that Huaxin would obtain "detailed and reliable exploration, sampling and testing information" through appropriate techniques to enable a Competent Person to calculate the level of Measured Mineral Resource in the EPC area. The trial judge had rejected both claims, and the Wellingtons sought to overturn this decision on appeal. Additionally, the Wellingtons appealed the trial judge’s assessment of damages for loss of opportunity, claiming that he had erred in his global assessment of damages.

The court considered the evidence and arguments presented by both parties and ultimately upheld the trial judge’s decision. The court found that the trial judge was correct in rejecting the existence of an implied duty to cooperate and an implied term to undertake particular exploration work. The court also found that the trial judge’s assessment of damages for loss of opportunity was not erroneous. Consequently, the appeal was dismissed, and the Wellingtons were ordered to pay the respondents’ costs of the appeal.

Orders

Orders of the court

1. The appeal is dismissed.

2. The appellants pay the respondents’ costs of the appeal.

Background

Background to the litigation

The three issues that arise in the appeal are whether the trial judge was correct:(a)in rejecting the appellants’ contention that an implied term to cooperate arose (the implied duty to cooperate);(b)in rejecting that an implied term to undertake particular exploration work arose (the implied exploration term); and(c)in his Honour’s quantification of damages for loss of opportunity arising from a breach of the implied terms.Factual background The factual background is set out concisely by Jackson J in his reasons as follows. On or around 1 July 2009, Mr Owen Reginald Wellington (Mr Wellington) applied for an EPC over an area comprising 130 sub-blocks (45,000 hectares) of land that is located approximately 150 km south of Charters Towers, which is part of an of area in Queensland known as the Galilee Basin.[1][1]Wellington v Huaxin Energy (Aust) Pty Ltd (formerly Cuesta Coal Limited) [2019] QSC 18 (Reasons) at [2]. On 6 July 2010, the original Vendors entered into a heads of agreement for the sale with the Purchaser and Blackwood Coal Pty Ltd (Heads of Agreement).[2] On 29 October 2010, EPC 1802 was granted to Mr Wellington.[3] On 17 November 2010, the Vendors, the Purchaser and Blackwood Coal Pty Ltd entered into a contract styled the Tenement Sale Agreement, in substitution for the Heads of Agreement (Tenement Sale Agreement).[4] On 13 December 2010, the cash component of the consideration payable under the Tenement Sale Agreement was paid.[5] [2]Reasons at [3].[3]AB1 at 52. [4]Reasons at [5].[5]Reasons at [6]. On 9 May 2011, the parties varied the terms of the Tenement Sale Agreement by a contract styled the “Amended and Restated Tenement Sale Agreement” (Amended and Restated Tenement Sale Agreement).[6] On 28 October 2011, the parties to the Amended and Restated Tenement Sale Agreement and the first respondent, then named Cuesta Coal Ltd, entered into a contract that was called the “Cuesta Deed” in evidence and submissions, varying the parties to the contract up to that time by substituting the first respondent for Blackwood Coal Pty Ltd, and varying the consideration payable to the Vendors for purchase of the Assets.[7] On 8 December 2011 and 3 January 2012, that part of the consideration payable under the Amended and Restated Tenement Sale Agreement defined as the “First Tranche Payment” was paid.[8] On 18 January 2012, EPC 1802 was transferred to the second respondent.[9][6]Reasons at [7].[7]Reasons at [8].[8]Reasons at [9].[9]Reasons at [10]. On 10 December 2012, the parties to the contract at that point and the third appellant entered into a contract styled a Deed of Assignment under which the third appellant became a party to the Amended and Restated Tenement Sale Agreement, as varied by the Cuesta Deed, in replacement for Mr Fox.[10][10]Reasons at [11]. On 18 October 2013, the parties to the contract varied the consideration payable under the Amended and Restated Tenement Sale Agreement to the Vendors (final contract).[11] On 21 October 2013, 21 January 2014 and 17 April 2014, the part of the consideration payable to the Vendors under the final contract styled the “Second Tranche Payment” was paid.[12] Soon after the first of those payments, on 29 October 2013, the first respondent made an ASX announcement that a Competent Person had estimated an “Inferred Mineral Resource” (a defined term to which reference will be made later) upon EPC 1802 of 364.1 million tonnes (Mt).[13][11]Reasons at [12].[12]Reasons at [13].[13]Reasons at [14].

Evidence

Evidence Before The Court

His Honour stated further:[42]“As defined, the crux of the distinction between an indicated mineral resource and a measured mineral resource lies in the degree of confidence. Thus, for an indicated mineral resource, the data must be such ‘as to allow confident interpretation of the geological framework and assume continuity of mineralisation’, whereas for a measured mineral resource, the data must be such as ‘to leave no reasonable doubt, in the opinion of the Competent Person determining the mineral resource, that the tonnage and grade of the mineralisation can be estimated to within close limits, and that any variation from the estimate would be unlikely to significantly affect potential economic viability’. The measured mineral resource category requires ‘a high level of confidence in, and understanding of, the geological properties and controls of the mineral deposit’.Clauses 42 to 44 of the 2012 edition JORC Code relate specifically to the public reporting of coal resources. They provide that for guidance on the estimation of coal resources, readers are referred to the “Australian Guidelines for Estimating and Reporting of Inventory Coal, Coal Resources and Coal Reserves” as published from time to time by the Coalfields Geology Council of New South Wales and the Queensland Resources Council. The 2003 edition of those guidelines deals with the estimation of coal resources from points of observation or “POB”. Paragraph 4.5.3 provides that measured coal resources may be estimated using data obtained from POBs normally less than 500 metres apart, but the distance may be extended if there is sufficient technical justification to do so; for example, if supported by geostatistical analysis.”[42]Reasons at [36].Evidence as to the 21 hole exploration program His Honour observed that it was not in dispute at trial that the exploration and drilling program carried out by the first respondent in the relevant areas of EPC 1802 constituted a total of up to 45 drill holes of which six were POB quality. The POBs were spaced between 3,000 and 4,000 metres apart, which exceeded the maximum spacing that is permissible to estimate or determine a Measured Mineral Resource.[43][43]Reasons at [38]. The trial judge referred to the expert evidence concerning a 21 hole exploration program for upgrading to a Measured Mineral Resource:[44]“The [appellants’] expert, Troy Turner, proposes that a drilling program of 21 x 63 millimetre dome and core holes and 21 pilot open chip holes would be required to ‘convert’ (upgrade) the most prospective zone of the current 364.1 Mt Inferred Mineral Resource area on EPC 1802, in the Yellow Jacket area of the EPC, to approximately 100 Mt of Measured Mineral Resource. The proposed area was described in the evidence of the case as the ‘100 Mt polygon’. I will describe this proposed drilling program as the ‘21 hole exploration program’. The [respondents’] experts agreed that the 21 hole exploration program is a reasonable approach to a first stage of drilling with the intention to define a Measured Mineral Resource, but reserved whether further in-fill drilling or possibly step-out drilling and drilling into adjacent areas may be required. However, the [appellants] contend, for the purposes of their case, that it was the 21 hole exploration program that the first [respondent] failed to carry out, in breach of the implied duty to cooperate or the detailed and reliable exploration implied term.Mr Turner opined that the 21 hole exploration program would have cost in the range between $0.73 million and $1.1 million and would have taken 70 days to complete the exploration work and a further 90 days to carry out the associated laboratory and assessment work, in accordance with the proposed exploration budget attached as Appendix D to his first report.”[44]Reasons at [39].The trial judge’s decision as to the implied duty to cooperate

Decision

Reasons for decision

The trial judge referred to the expert evidence concerning a 21 hole exploration program for upgrading to a Measured Mineral Resource:[44]“The [appellants’] expert, Troy Turner, proposes that a drilling program of 21 x 63 millimetre dome and core holes and 21 pilot open chip holes would be required to ‘convert’ (upgrade) the most prospective zone of the current 364.1 Mt Inferred Mineral Resource area on EPC 1802, in the Yellow Jacket area of the EPC, to approximately 100 Mt of Measured Mineral Resource. The proposed area was described in the evidence of the case as the ‘100 Mt polygon’. I will describe this proposed drilling program as the ‘21 hole exploration program’. The [respondents’] experts agreed that the 21 hole exploration program is a reasonable approach to a first stage of drilling with the intention to define a Measured Mineral Resource, but reserved whether further in-fill drilling or possibly step-out drilling and drilling into adjacent areas may be required. However, the [appellants] contend, for the purposes of their case, that it was the 21 hole exploration program that the first [respondent] failed to carry out, in breach of the implied duty to cooperate or the detailed and reliable exploration implied term.Mr Turner opined that the 21 hole exploration program would have cost in the range between $0.73 million and $1.1 million and would have taken 70 days to complete the exploration work and a further 90 days to carry out the associated laboratory and assessment work, in accordance with the proposed exploration budget attached as Appendix D to his first report.”[44]Reasons at [39].The trial judge’s decision as to the implied duty to cooperate His Honour observed[45] that the common starting point for the parties’ submissions on the implied duty to cooperate was the following passage of Mason J in Secured Income Real Estate (Australia) Ltd v St Martins Investments Pty Ltd:[46][45]Reasons at [41].[46](1979) 144 CLR 596 at 607.“But it is common ground that the contract imposed an implied obligation on each party to do all that was reasonably necessary to secure performance of the contract. As Lord Blackburn said in Mackay v Dick…:‘as a general rule … where in a written contract it appears that both parties have agreed that something shall be done, which cannot effectually be done unless both concur in doing it, the construction of the contract is that each agrees to do all that is necessary to be done on his part for the carrying out of that thing, though there may be no express words to that effect.’It is not to be thought that this rule of construction is confined to the imposition of an obligation on one contracting party to co-operate in doing all that is necessary to be done for the performance by the other party of his obligations under the contract. As Griffith CJ said in Butt v M’Donald…:‘It is a general rule applicable to every contract that each party agrees, by implication, to do all such things as are necessary on his part to enable the other party to have the benefit of the contract.’It is easy to imply a duty to co-operate in the doing of acts which are necessary to the performance by the parties or by one of the parties of fundamental obligations under the contract. It is not quite so easy to make the implication when the acts in question are necessary to entitle the other contracting party to a benefit under the contract but are not essential to the performance of that party's obligations and are not fundamental to the contract. Then the question arises whether the contract imposes a duty to co-operate on the first party or whether it leaves him at liberty to decide for himself whether the acts shall be done, even if the consequence of his decision is to disentitle the other party to a benefit. In such a case, the correct interpretation of the contract depends, as it seems to me, not so much on the application of the general rule of construction as on the intention of the parties as manifested by the contract itself.”

Ratio Decidendi

Legal Principle Established

The central issues as to the implication of terms centre on cl 4.1(1)(b)(iii) and cl 4.2(2) of the final contract which relevantly provide:“4.1 Consideration(1)The consideration for the purchase of the Assets is:…(b) Subject to Completion occurring, any necessary shareholder approvals being obtained (including approvals required under the ASX Listing Rules), the Vendors entering into any restriction agreement required by the ASX under the ASX Listing Rules and doing anything else required in accordance with the ASX Listing Rules:…(iii)the issue of the Third Tranche Shares and Third Tranche Options by Cuesta to the Vendors on the date that is:(A)10 Business Days after the Third Milestone occurred if Cuesta is listed on the ASX as at the date the Third Milestone occurred; or(B)10 Business Days after the Third Milestone occurred and the Purchaser receives a valuation from an Independent Expert which is carried out in accordance with clause 4.1(2) if Cuesta is not listed on the ASX as at the date the Third Milestone occurred…4.2 Failure to Meet Second Milestone and Third Milestone[19](1)…(2)If the Purchaser fails to meet the Third Milestone by the 5th anniversary of the grant of the Tenement (Third Milestone Date) but a Competent Person infers the existence of a Measured Mineral Resource with an estimated tonnage of at least 40,000,000 but less than 100,000,000 tonnes of coal in the Tenement Area as at the Third Milestone Date, then Cuesta must issue the Third Tranche Shares and the Third Tranche Options[20] to the Vendors (adjusted on a pro rate basis) on the date that is(a) 10 Business Days after the Third Milestone Date if Cuesta is listed on the ASX at the time; or(b) 10 Business Days after the Third Milestone Date and the Purchaser receives a valuation from an Independent Expert which is carried out in accordance with clause 4.1(2) if Cuesta is not listed on the ASX at the time.” (emphasis added)[19]Third Milestone Date had the meaning given to it in cl 4.2(2): cl 1.1(5).[20]“Third Tranche Options” was defined to mean “that number of Cuesta Options equal to the number to Third Tranche Shares” (as that term was in turn defined in the final contract): cl 1.1(55).Other provisions The three milestones were defined as follows:“First Milestone means the earlier to occur of:(a)the first anniversary of the grant of the Application; and(b)the date that coal is intersected on the Purchaser’s initial drill program on the Tenement.”[21]“Second Milestone means the date a Competent Person[22] infers the existence of an Inferred Mineral Resource with an estimated tonnage of 100,000,000 tonnes or more of coal in the Tenement Area.”[23]“Third Milestone means the date a Competent Person infers the existence of a Measured Mineral Resource with an estimated tonnage of 100,000,000 tonnes or more of coal in the Tenement Area.”[24][21]Clause 1.1 (24).[22]“Competent Person” is defined by reference to the “JORC Code” (cl 1.1 (12)), as a person who is a Member or Fellow of The Australasian Institute of Mining and Metallurgy, or of the Australian Institute of Geoscientists, or of a “Recognised Overseas Professional Organisation” (ROPO) included in a list promulgated from time to time, having a minimum of five years’ experience which is relevant to the style of mineralisation and type of deposit under consideration and to the activity which that person is undertaking.[23]Clause 1.1 (46).[24]Clause 1.1 (53).