Warburton v County Construction (NSW) Pty Ltd

Link copied
Case Copied 21 min read

Supreme Court


New South Wales

Medium Neutral Citation: Warburton v County Construction (NSW) Pty Ltd [2022] NSWSC 1281
Hearing dates: Last written submissions 8 September 2022, 21 September 2022
Date of orders: 21 September 2022
Decision date: 21 September 2022
Jurisdiction:Equity - Technology and Construction List
Before: Black J
Decision:

Judgment for the plaintiffs in the amount of $224,727.34. Parties to serve and send to the Associate to Black J their respective submissions as to interest and costs by 4pm on 21 October 2022 and their reply submissions by 4pm on 28 October 2022. Reserve liberty to apply on 3 days’ notice.

Catchwords:

BUILDING AND CONSTRUCTION — Contract — Damages — Quantification — Quantification of damages for the rectification of defects — Where there is disagreement between expert witnesses as to quantification

Cases Cited:

- Builders Insurers Guarantee Corporation v The Owners – Strata Plan No 57504 [2010] NSWCA 23

- Commonwealth v Amann Aviation Pty Ltd (1991) 174 CLR 64

- Dean v Ainley [1987] 1 WLR 1729

- JLW (Vic) Pty Ltd v Tsiloglou [1994] 1 VR 237

- Lichaa v Boutros [2021] NSWCA 322

- McCrohan v Harith [2010] NSWCA 67

- New South Wales v Moss (2000) 54 NSWLR 536; [2000] NSWCA 133

- Placer (Granny Smith) Pty Ltd v Thiess Contractors Pty Ltd (2003) 77 ALJR 768

- Re Hair Industrie Penrith Pty Ltd, Hair Industrie Merrylands Pty Ltd [2015] NSWSC 1578

- Schindler Lifts Australia Pty Ltd v Debelak (1989) 89 ALR 275

- Troulis v Vamvoukakis [1998] NSWCA 237

- Uszok v Henley Properties (NSW) Pty Ltd [2007] NSWCA 31

- Warburton v County Construction (NSW) Pty Ltd [2022] NSWSC 941

- Yates v Mobile Marine Repairs Pty Ltd [2007] NSWSC 1463

Category:Principal judgment
Parties: Mark Warburton (First Plaintiff/First Cross-Defendant)
Jacqueline Warburton (Second Plaintiff/Second Cross-Defendant)
County Construction (NSW) Pty Ltd (First Defendant/Cross-Claimant)
Robert Daryl Hart (Second Defendant)
Representation:

Counsel:
F Hicks SC (Plaintiffs/Cross-Defendants)
M Klooster (Defendants/Cross-Claimant)

Solicitors:
William Cotsis & Associates (Plaintiffs/Cross-Defendants)
Somerville Legal (Defendants/Cross-Claimant)
File Number(s): 2019/191970

Judgment

Background

  1. By my judgment delivered on 15 July 2022 (Warburton v County Construction (NSW) Pty Ltd [2022] NSWSC 941) I found (at [224]) that:

“… County is liable in respect of several aspects of the work done before the Second Agreement took effect (items H2, H3, H13 and G34, in respect of the dividing wall only) as to which it had assumed the wider obligations under the Contract, and the statutory warranties had wider effect, and that liability is not released by the release in the Second Agreement. I will allow the parties an opportunity to reach agreement as to the quantification or works relating to those items, or make further submissions, given the difficulties as to the expert quantification evidence, to which I refer below. Mr and Mrs Warburton have otherwise not established their claims for breach of the Contract, the Second Agreement or the statutory warranties against County.”

  1. I also noted several difficulties which had arisen in…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Warburton v County Construction (NSW) Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Find similar cases

Other decisions on the same topics. Each opens in a new tab.

Details

Case
[2022] NSWSC 1281
Decision Date

CaseChat Overview and Summary

The case of Warburton v County Construction (NSW) Pty Ltd was heard in the Supreme Court of New South Wales, where the plaintiff sought to recover damages from the defendant for defects in the construction of a residential property. The defendant, County Construction (NSW) Pty Ltd, had undertaken the construction work and was found to be in breach of the contractual terms regarding the quality of workmanship. The plaintiff, Warburton, alleged that the defects resulted in significant financial loss and sought compensation for the rectification of these defects. The court was tasked with determining the appropriate quantum of damages that should be awarded to the plaintiff.

The primary legal issue before the court was the quantification of damages for the rectification of defects in the construction. The court had to assess the evidence presented by both parties, including expert witness reports, to determine the extent of the defects, the cost of rectification, and whether any of the claimed damages were excessive or not adequately substantiated. A further issue was the credibility and weight to be given to the expert witnesses' opinions, as they were in disagreement regarding the total cost of rectification.

The court examined the evidence in detail, weighing the differing expert opinions on the cost of rectifying the defects. The court concluded that while both experts were qualified, their methodologies and assumptions led to significant variances in their estimates. The court preferred the opinion of the plaintiff's expert, finding it to be more reliable and better supported by the evidence presented. The court awarded damages to the plaintiff based on the preferred expert's report, after making adjustments for any perceived overestimation. The court found that the defendant was liable for the costs of rectifying the defects, but not for all the additional expenses claimed by the plaintiff.

In summary, the court awarded damages to the plaintiff for the rectification of defects in the construction of the residential property. The quantum of damages was determined based on the preferred expert's report, adjusted for any overestimation. The court's decision provided clarity on the appropriate method for quantifying such damages, taking into account the disagreement between the expert witnesses.

Background

Background to the litigation

Decision

Reasons for decision

Ratio Decidendi

Legal principle established