SUPREME COURT OF SOUTH AUSTRALIA
(Magistrates Appeal: Civil)
WANG v GELNAR P/L
[2023] SASC 43
Judgment of the Honourable Justice Stanley
31 March 2023
CONTRACTS - BUILDING, ENGINEERING AND RELATED CONTRACTS - PERFORMANCE OF WORK - REMEDIES FOR BREACH OF CONTRACT - DAMAGES
CONTRACTS - BUILDING, ENGINEERING AND RELATED CONTRACTS - REMUNERATION - EXTRAS AND ALTERATIONS
APPEAL AND NEW TRIAL - APPEAL - GENERAL PRINCIPLES - ADMISSION OF FURTHER EVIDENCE - EVIDENCE NOT AVAILABLE AT HEARING
APPEAL AND NEW TRIAL - APPEAL - GENERAL PRINCIPLES - EXCESSIVE OR INADEQUATE DAMAGES - DAMAGES INADEQUATE
APPEAL AND NEW TRIAL - APPEAL - GENERAL PRINCIPLES - POINTS AND OBJECTIONS NOT TAKEN BELOW
This is an appeal from the judgment of a magistrate who allowed a claim for the cost of unpaid work done pursuant to a building contract and awarded the respondent the sum of $21,581.82 together with interest in an amount of $3,000. The magistrate also dismissed a counterclaim by the appellant for the sum of $70,702.66 for damages for defective works negligently performed.
The appellant alleges that the works were defective due to the provision of understrength concrete in the foundations, resulting in a loss of rental income for a period of 34 weeks.
The trial magistrate found that the use of understrength concrete was a breach of contract, but the weaker concrete was nonetheless fit for purpose and did not cause any defect in the structural integrity of the foundation. Accordingly, the magistrate found that there was no loss suffered as a result of the breach of contract.
The trial magistrate also allowed a claim for $2,700, being the costs of what she found to be variation works which the appellant claimed were rectification works.
The grounds of appeal raised by the appellant are:
1. That the learned magistrate erred in finding that all of the costs associated with the delay to building works were not “costs that can be directly attributed” to the breach of contract; and
2. That the learned magistrate erred in accepting a variation claim in the amount of $2,700 because the relevant works formed part of the contractor’s obligations under the contract.
Held:
1. The magistrate did not err in finding that all of the costs associated with the delay to building works were not “costs that can be directly attributed” to the breach of the contract.
2. The magistrate did not err in accepting the variation claim.
3. The appeal is dismissed.
4. The question of costs is reserved.
Pitt v Commissioner for Consumer Affairs [2021] SASCA 24; Sunlight Nominees Pty Ltd v Zotti & Zotti [2019] SASCFC 11; Taylor v Hayes (1990) 53 SASR 282; University of Wollongong v Metwally (No 2) (1985) 59 ALJR 481; Viscariello v Livesey & Anor [2013] SASC 99; Wade v Australian Railway Historical Society (2000) 77 SASR 221; Warren v Coombes (1979) 142 CLR 531; Water Board v Moustakas (1988) 180 CLR 491, considered.
WANG v GELNAR P/L
[2023]…
Continue reading Wang v Gelnar P/L
Sign in free to access the full text
- AGLC
- Wang v Gelnar P/L [2023] SASC 43
- Case
- [2023] SASC 43
- Decision Date
CaseChat Overview and Summary
The court was required to decide whether the magistrate correctly assessed the costs related to the delay in building works and whether the variation claim was appropriately accepted. Specifically, the court needed to consider whether the costs attributed to the delay were directly linked to the breach of contract, as well as whether the variation claim was justified given the contractor's contractual obligations.
In rejecting the appeal, the court held that the magistrate's findings were not in error. The court emphasised the importance of the ability of the appellant to have obtained the evidence at first instance and noted that the public interest in the finality of litigation is a crucial consideration. The detailed testimony and documentary evidence presented by the appellant were deemed not to have a material bearing on the question of error in the magistrate's decision. The court also highlighted that the appellant's failure to present this evidence at the initial trial could not be justified by ordinary diligence.
The appeal was dismissed, and the parties were directed to address the matter of costs. This decision reinforces the principles governing the admission of further evidence on appeal and the importance of the finality of litigation.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.