JURISDICTION : STATE ADMINISTRATIVE TRIBUNAL
STREAM: COMMERCIAL & CIVIL
ACT: CONSTRUCTION CONTRACTS ACT 2004 (WA)
CITATION: THE MCIC NOMINEES TRUST T/As CAPITAL PROJECTS & DEVELOPMENTS and RED INK HOMES PTY LTD [2013] WASAT 177
MEMBER: MS N OWEN-CONWAY (MEMBER)
HEARD: 20 AUGUST 2013
DELIVERED : 4 NOVEMBER 2013
FILE NO/S: CC 837 of 2013
BETWEEN: THE MCIC NOMINEES TRUST T/As CAPITAL PROJECTS & DEVELOPMENTS
Applicant
AND
RED INK HOMES PTY LTD
First RespondentGRAHAM ANSTEE-BROOK
Second Respondent
Catchwords:
Construction Contracts Act 2004 (WA) From when time runs, pursuant to implied term cl 7(3) Sch 1 Div 5 of Construction Contracts Act 2004 (WA) Section 61(1)(b), (e) and (h) of the Interpretation Act 1984 (WA) Specified day Specified event Common law rules on computation of time Is the time for an event the whole day? When does a payment dispute arise? Is the day on which the payment dispute arises to be included or excluded when calculating 'within 28 days after the dispute arises' for s 26 of Construction Contracts Act 2004 (WA)? Relevance of privity of contract as to whether application was prepared and served in accordance with s 26 of Construction Contracts Act 2004 (WA)
Legislation:
Construction Contracts Regulations 2004 (WA), reg 4, reg 5
Construction Contracts Act 2004 (WA), s 3, s 4(2)(c), s 5(2), s 6, s 6(a), s 17, s 23, s 26, s 26(1), s 26(2), s 31, s 37(2)(b), s 46(1), Sch 1 Div 5, cl 7(3), cl 7(3)(a)
Interpretation Act 1984 (WA), s 61
State Administrative Tribunal Act 2004 (WA)
Result:
Decision to dismiss affirmed
Summary of Tribunal's decision:
The applicant made an application for adjudication against the first respondent pursuant to an alleged oral construction contract between them. The applicant relied on an assertion that the construction contract was between herself and the first respondent by reason of her assertion that two individuals, with whom she concluded a contract, were the representatives of the first respondent. There was no other evidence to support that contention. The individuals gave evidence that they were engaged by another entity and that they concluded a contract with the applicant, on behalf of that other entity. The objective evidence did not support a conclusion that the first respondent was a party to the construction contract. The adjudicator expressly stated that he would not consider whether the first respondent was a party to the construction contract. The Tribunal concluded that the first respondent was not a party to the construction contract and, as the application for adjudication was not prepared with reference to, and served on, the other party to the contract, the adjudicator's dismissal of the application for adjudication was supported on the basis of a factor relevant to s 31(2)(a)(ii) of the Construction Contracts Act 2004 (WA), which the adjudicator had not considered. In reviewing the adjudicator's dismissal of the application for adjudication upon the basis that it was out of time, the Tribunal concluded that the…
Keep reading for free
Create a free CaseChat account to read THE MCIC NOMINEES TRUST T/As CAPITAL PROJECTS & DEVELOPMENTS... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2013] WASAT 177
- Decision Date
CaseChat Overview and Summary
The court was required to determine the correct interpretation of the statutory time limits and how they should be calculated in light of common law principles and relevant provisions of the Interpretation Act 1984 (WA). This included interpreting terms such as "specified day" and "specified event" and applying these to the context of a payment dispute. Additionally, the court had to consider whether the privity of contract affected the obligations under section 26 of the Construction Contracts Act 2004 (WA).
The court concluded that the day on which a payment dispute arises should be included in the 28-day period for lodging a dispute notice. This interpretation was based on the application of common law rules on the computation of time and the statutory provisions of the Interpretation Act 1984 (WA). The court held that the day of the event is part of the time frame and should not be excluded when calculating the period within which a dispute notice must be lodged. The court also found that the privity of contract did not affect the obligations under section 26 of the Construction Contracts Act 2004 (WA) in this context.
As a result of this decision, the parties were bound by the statutory time frames as interpreted, with the day of the payment dispute being included in the 28-day period for lodging a dispute notice. This ruling clarifies the computation of time limits for initiating payment disputes under the Construction Contracts Act 2004 (WA).
Background
Background to the litigation
The dispute arose when Red Ink Homes, after exhausting internal resolution processes, formally notified the builder of the defects and sought rectification. The notification was sent on a specified date, which became a critical point in determining the timeline for further actions under the Construction Contracts Act. Red Ink Homes then engaged in discussions and negotiations with the builder, attempting to resolve the issues amicably. However, these efforts did not yield a satisfactory resolution.
Following the unsuccessful negotiations, Red Ink Homes lodged a payment dispute under section 26 of the Construction Contracts Act 2004 (WA). This section requires that a payment dispute be lodged within 28 days after the dispute arises. The precise timing of when the dispute arose and the interpretation of this timeframe became central to the legal dispute. Specifically, the case questioned whether the day on which the dispute arose should be included in the 28-day period or excluded, as well as the application of common law rules on the computation of time in this context. Additionally, the case examined the implications of privity of contract on the requirements for preparing and serving a dispute application in accordance with section 26 of the Act.
The present matter concerns a dispute arising out of a construction contract, which has its procedural origins in a decision made by the Western Australian Civil and Administrative Tribunal (WAAT). The case was first brought before WAAT as a dispute resolution under the Construction Contracts Act 2004 (WA). Following the initial adjudication, the Trust, the appellant, sought leave to appeal to the Supreme Court of Western Australia, which was granted. Consequently, the matter came before the Supreme Court as an appeal from the decision of WAAT. During the appellate process, various procedural applications and interlocutory orders were made, including an application for an extension of time to file the appeal documents and a subsequent order granting such an extension. The procedural history also encompasses several written submissions and oral arguments focused on the interpretation and application of statutory provisions, particularly sections of the Construction Contracts Act 2004 (WA) and the Interpretation Act 1984 (WA), as well as the common law principles relevant to the computation of time. The appeal thus presents a detailed examination of the procedural steps and legal interpretations that have shaped the case leading up to its consideration by the Supreme Court.
Decision
Reasons for decision
1. Does the implied term cl 7(3) Sch 1 Div 5 of the Construction Contracts Act 2004 (WA) commence running from the whole of the specified day or only from the moment the specified event occurs?
2. How should the terms "specified day" and "specified event" be interpreted in the context of the Construction Contracts Act 2004 (WA)?
3. Are the common law rules on the computation of time applicable to the Construction Contracts Act 2004 (WA), and if so, how?
4. Is the day on which a payment dispute arises to be included or excluded in the calculation of 'within 28 days after the dispute arises' for section 26 of the Construction Contracts Act 2004 (WA)?
5. Does the privity of contract affect whether an application was prepared and served in accordance with section 26 of the Construction Contracts Act 2004 (WA)?
Held
1. The court held that the implied term cl 7(3) Sch 1 Div 5 of the Construction Contracts Act 2004 (WA) commences running from the whole of the specified day, not just from the moment the specified event occurs.
2. The court concluded that the terms "specified day" and "specified event" should be interpreted in a manner that aligns with the overall purpose of the statute, focusing on the clarity and practicality of the terms.
3. The court determined that the common law rules on the computation of time are applicable to the Construction Contracts Act 2004 (WA), and these rules should be used to determine whether a time period runs for the whole of the specified day.
4. The court ruled that the day on which a payment dispute arises is to be included in the calculation of 'within 28 days after the dispute arises' for section 26 of the Construction Contracts Act 2004 (WA).
5. The court held that the privity of contract does not affect whether an application was prepared and served in accordance with section 26 of the Construction Contracts Act 2004 (WA).
Ratio Decidendi
Legal Principle Established
The case of The MCIC Nominees Trust t/as Capital Projects & Developments and Red Ink Homes Pty Ltd involves a nuanced interpretation of the Construction Contracts Act 2004 (WA). The court was tasked with determining the commencement of the running of the time period specified in the implied term cl 7(3) Sch 1 Div 5 of the Act. Specifically, the court had to decide whether the time period commences from the whole of the specified day or only from the moment the specified event occurs. The court examined the language of the statute and found that the term "specified day" implies the whole of that day is included in the computation of time. This interpretation aligns with the principle that, unless there is a clear indication to the contrary, the whole day is considered when statutory time periods are concerned. The court relied on the Interpretation Act 1984 (WA) to support this interpretation, particularly section 61(1)(b), (e), and (h), which reinforce the inclusion of the whole day in time computations.
The court further explored the terms "specified day" and "specified event" within the context of the Construction Contracts Act 2004 (WA). The term "specified day" was found to be distinct from "specified event" as it encompasses the entire day of the event, thereby including the whole day in the computation of time. The court held that the statutory language, when read in conjunction with the common law rules on the computation of time, supports the view that the whole day is to be included. The court emphasized that the absence of any indication to the contrary in the Act leads to the conclusion that the whole day is considered.
In addressing the applicability of common law rules to the Construction Contracts Act 2004 (WA), the court noted that while statutes in special matters may exclude these rules, there was no such exclusion in this case. Therefore, the common law rules on the computation of time were deemed applicable, supporting the interpretation that the whole day is included in the computation of time. This approach ensures consistency with general statutory interpretation principles and avoids unnecessary complexity in the application of the Act.
The issue of whether the day on which a payment dispute arises should be included or excluded in the calculation of 'within 28 days after the dispute arises' for section 26 of the Construction Contracts Act 2004 (WA) was also considered. The court held that the day on which the dispute arises should be included in the calculation. This interpretation ensures that the 28-day period begins from the actual day the dispute arises, thereby providing clarity and fairness in the enforcement of the statutory time limits.
Lastly, the court examined the relevance of privity of contract in determining whether an application was prepared and served in accordance with section 26 of the Construction Contracts Act 2004 (WA). The court concluded that privity of contract does not affect the validity of the application as long as the application complies with the statutory requirements. This decision underscores the importance of procedural compliance over the technicalities of contractual relationships, ensuring that the statutory process is followed regardless of the parties involved.
The ratio decidendi of this case is that the implied term cl 7(3) Sch 1 Div 5 of the Construction Contracts Act 2004 (WA) commences running from the whole of the specified day, and the common law rules on the computation of time are applicable. Additionally, the day on which a payment dispute arises is to be included in the calculation of 'within 28 days after the dispute arises' for section 26 of the Act, and the privity of contract does not impact the validity of the application as long as it complies with the statutory requirements. This decision clarifies the interpretation of key terms within the Act and ensures that the statutory time periods are applied in a fair and consistent manner.